summaryrefslogtreecommitdiff
path: root/42149-0.txt
diff options
context:
space:
mode:
Diffstat (limited to '42149-0.txt')
-rw-r--r--42149-0.txt7263
1 files changed, 7263 insertions, 0 deletions
diff --git a/42149-0.txt b/42149-0.txt
new file mode 100644
index 0000000..03dc666
--- /dev/null
+++ b/42149-0.txt
@@ -0,0 +1,7263 @@
+*** START OF THE PROJECT GUTENBERG EBOOK 42149 ***
+
+[Transcribers' notes:
+
+Some tables don't sum to the numbers indicated; no corrections have been
+made. All numbers are from the original.
+
+Minor inconsistencies in hyphenation have been retained.
+
+Subscripts are represented by underscore and curly braces e.g., CO_{2}.
+
+Italics are represented by underscores before and after e.g., _italics_.
+
+Bold is represented by equal signs before and after e.g., =bold=.
+
+Small caps have been replaced with ALL CAPS.]
+
+
+
+
+ AMERICAN SOCIETY OF CIVIL ENGINEERS
+
+ INSTITUTED 1852
+
+ TRANSACTIONS
+
+ Paper No. 1155
+
+ THE NEW YORK TUNNEL EXTENSION OF THE
+ PENNSYLVANIA RAILROAD.
+
+ THE NORTH RIVER TUNNELS.[A]
+
+ BY B. H. M. HEWETT AND W. L. BROWN, MEMBERS, AM. SOC. C. E.
+
+ [A] Presented at the meeting of June 1st, 1910.
+
+
+INTRODUCTION.
+
+The section of the Pennsylvania Railroad Tunnel work described in this
+paper is that lying between Tenth Avenue, New York City, and the large
+shaft built by the Company at Weehawken, N. J., and thus comprises the
+crossing of the North or Hudson River, the barrier which has stood for
+such a long time between the railroads and their possession of terminal
+stations in New York City. The general plan and section, Plate XXVIII,
+shows the work included.
+
+This paper is written from the point of view of those engaged by the
+Chief Engineer of the Railroad Company to look after the work of
+construction in the field. The history of the undertaking is not
+included, the various phases through which many of the designs and plans
+passed are not followed, nor are the considerations regarding
+foundations under the subaqueous portions of the tunnels and the various
+tests made in connection with this subject set out, as all these matters
+will be found in other papers on these tunnels.
+
+This paper only aims to describe, as briefly as possible, the actual
+designs which were finally adopted, the actual conditions met on the
+ground, and the methods of construction adopted by the contractors.
+For easy reference, and to keep the descriptions of work of a similar
+character together, the subject will be treated under the four main
+headings, viz.: Shafts, Plant, Land Tunnels, and River Tunnels.
+
+
+SHAFTS.
+
+It is not intended to give much length to the description of the Shafts
+or the Land Tunnels, as more interest will probably center in the River
+Tunnels.
+
+The shafts did not form part of the regular tunnel contract, but were
+built under contract by the United Engineering and Contracting Company
+while the contract plans for the tunnel were being prepared. In this
+way, when the tunnel contracts were let, the contractor found the shafts
+ready, and he could get at his work at once.
+
+Two shafts were provided, one on the New York side and one on the New
+Jersey side. Their exact situation is shown on Plate XXVIII. They were
+placed as near as possible to the point at which the disappearance of
+the rock from the tunnels made it necessary to start the shield-driven
+portion of the work.
+
+The details of the shafts will now be described briefly.
+
+_The Manhattan Shaft._--The Manhattan Shaft is located about 100 ft.
+north of the tunnel center; there was nothing noticeable about its
+construction. General figures relating to both shafts are given in Table
+1.
+
+_The Weehawken Shaft._--The Weehawken Shaft is shown in Fig. 1. This, as
+will be seen from Table 1, was a comparatively large piece of work. The
+shaft is over the tunnels, and includes both of them. In the original
+design the wall of the shaft was intended to follow in plan the property
+line shown in Fig. 2, and merely to extend down to the surface of the
+rock, which, as disclosed by the preliminary borings, was here about 15
+ft. below the surface. However, as the excavation proceeded, it was
+found that this plan would not do, as the depth to the rock surface
+varied greatly, and was often much lower than expected; the rock itself,
+moreover, was very treacherous, the cause being that the line of
+junction between the triassic sandstone, which is here the country rock,
+and the intrusive trap of the Bergen Hill ridge, occurs about one-third
+of the length of the shaft from its western end, causing more or less
+disintegration of both kinds of rock. Therefore it was decided to line
+the shaft with concrete throughout its entire depth, the shape being
+changed to a rectangular plan, as shown in the drawings. At the same
+time that the shaft was excavated, a length of 40 ft. of tunnels at each
+end of it was taken out, also on account of the treacherous nature of
+the ground, thus avoiding risk of injury to the shaft when the tunnel
+contractors commenced work. There was much trouble with floods during
+the fall of 1903, and numerous heavy falls of ground occurred, in spite
+of extreme care and much heavy timbering. The greatest care was also
+taken in placing the concrete lining, and the framing to support the
+forms was carefully designed and of heavy construction; the forms were
+of first-class workmanship, and great care was taken to keep them true
+to line. A smooth surface was given to the concrete by placing a 3-in.
+layer of mortar at the front of the walls and tamping this dry facing
+mixture well down with the rest of the concrete. The east and west walls
+act as retaining walls, while those on the north and south are facing
+walls, and are tied to the rock with steel rods embedded and grouted
+into the rock and into the concrete. Ample drainage for water at the
+back of the wall was provided by upright, open-joint, vitrified drains
+at frequent intervals, with dry-laid stone drains leading to them from
+all wet spots in the ground. A general view of the finished work is
+shown in Fig. 1, Plate XXIX, and Table 1 gives the most important dates
+and figures relating to this shaft.
+
+TABLE 1.--PARTICULARS OF SHAFTS ON THE NORTH RIVER TUNNELS OF THE
+PENNSYLVANIA RAILROAD TUNNELS INTO NEW YORK CITY.
+
+ +===========+=====+======+======+==========+========+===========+========+
+ |Location. |Depth| Width|Length|Excavation|Concrete| Date| Date|
+ | | in| in| in|(including|in cubic|commenced.|finished.|
+ | |feet.| feet.| feet.| drifts),| yards.| | |
+ | | | | | in cubic| | | |
+ | | | | | yards. | | | |
+ +-----------+-----+------+------+----------+--------+----------+---------+
+ |Manhattan: | 55| 22| 32| 2,010| 209|June 10th,| December|
+ |11th Avenue| | | | | | 1903.| 11th,|
+ |and 32d | | | | | | | 1903.|
+ |Street. | | | | | | | |
+ | | | | | | | | |
+ |Weehawken: | 76| At| At| 55,315| 9,810|June 11th,|September|
+ |Baldwin | |bottom|bottom| | | 1903.|1st, |
+ |Avenue. | |56, at|115.75| | | |1904. |
+ | | | top|at top| | | | |
+ | | | 100.| 154.| | | | |
+ |===========+=====+======+======+==========+========+==========+=========+
+
+ +==========+====================+=============+============+===========+
+ |Location. |Ground met: |Lined with: | Cost to | Cost per |
+ | | | | Railroad |cubic foot.|
+ | | | | Company. | |
+ +----------+--------------------+-------------+------------+-----------+
+ |Manhattan:|Top 13 ft. filled; |Concrete | $12,943.75 | $0.335 |
+ |11th |red mica schist and |reinforced | | |
+ |Avenue and|granite. |with steel | | |
+ |32d | |beams down to| | |
+ |Street. | |rock. | | |
+ | | | | | |
+ |Weehawken:|Top 6 ft. filled, 30|Concrete with| 166,162,98 | 0.337 |
+ |Baldwin |ft. sand and |steel | | |
+ |Avenue. |hardpan, decomposed |tie-rods in | | |
+ | |rock (trap and |rock. | | |
+ | |sandstone) below. | | | |
+ +==========+====================+=============+============+===========+
+
+[Illustration: FINAL DESIGN OF WEEHAWKEN SHAFT PLAN LONGITUDINAL SECTION
+TRANSVERSE SECTION FIG. 1.]
+
+After the tunnel work was finished, both shafts were provided with
+stairs leading to the surface, a protective head-house was placed over
+the New York Shaft, and a reinforced concrete fence, 8 ft. high, was
+built around the Weehawken Shaft on the Company's property line, that
+is, following the outline of the shaft as originally designed.
+
+
+PLANT.
+
+Working Sites.
+
+Before beginning a description of the tunnel work, it may be well to set
+out in some detail the arrangements made on the surface for conducting
+the work underground.
+
+All the work was carried on from two shafts, one at Eleventh Avenue and
+32d Street, New York City--called the Manhattan Shaft--and one at
+Baldwin Avenue, Weehawken, N. J.--called the Weehawken Shaft.
+
+[Illustration: WEEHAWKEN SHAFT. EXCAVATION FIG. 2.]
+
+The characteristics of the two sites were radically different, and
+called for different methods of handling the transportation problem. The
+shaft site at Manhattan is shown on Plate XXX. It will be seen that
+there was not much room, in fact, the site was too cramped for comfort;
+the total area, including the space occupied by the old foundry, used
+for power-houses, offices, etc., was about 3,250 sq. yd. This made it
+necessary to have two stages, one on the ground level for handling
+materials into the yard, and an overhead gantry on which the excavated
+materials were handled off the premises. The yard at Weehawken was much
+larger; it is also shown on Plate XXX. Its area was about 15,400 sq. yd.
+in the yard proper, and there was an additional space of about 750 sq.
+yd. alongside the wharf at the "North Slip," on the river front,
+connected with the main portion of the yard by an overhead trestle.
+
+All the cars at Manhattan were moved by hand, but at Weehawken two
+electric locomotives with overhead transmission were used.
+
+
+Power-House Plant.
+
+At the Manhattan Shaft the power-house plant was installed on the ground
+floor of the old foundry building which occupied the north side of the
+leased area. This was a brick building, quite old, and in rather a
+tumble-down condition when the Company took possession, and in
+consequence it required quite a good deal of repair and strengthening
+work. The first floor of the building was used by the contractor as
+offices, men's quarters, doctor's offices, and so on, and on the next
+one above, which was the top floor, were the offices occupied by the
+Railroad Company's field engineering staff.
+
+On the Weehawken side, the plant was housed in a wooden-frame,
+single-story structure, covered with corrugated iron. It was rectangular
+in plan, measuring 80 by 130 ft.
+
+At both sides of the river the engines were bedded on solid concrete on
+a rock foundation.
+
+The installation of the plant on the Manhattan side occupied from May,
+1904, to April, 1905, and on the Weehawken side from September, 1904, to
+April, 1905. Air pressure was on the tunnels at the New York side on
+June 25th, 1905, and on the Weehawken side on the 29th of the same
+month.
+
+[Illustration: PLATE XXIX. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1. FIG. 2.]
+
+The plants contained in the two power-houses were almost identical,
+there being only slight differences in the details of arrangement due to
+local conditions. A list of the main items of the plant at one
+power-house is shown in Table 2.
+
+TABLE 2.--PLANT AT ONE POWER-HOUSE.
+
+ +======+======================================================+========+
+ |No. of| | |
+ |items.|Description of item. | Cost.|
+ |------+------------------------------------------------------+--------|
+ |Three |500-h.p. water-tube Sterling boilers | $15,186|
+ |Two |Feed pumps, George F. Blake Manufacturing Company | 740|
+ |One |Henry R. Worthington surface condenser | 6,539|
+ |Two |Electrically-driven circulating pumps on river front | 5,961|
+ |Three |Low-pressure compressors, Ingersoll-Sergeant Drill | 33,780|
+ | |Company | |
+ |One |High-pressure compressor, Ingersoll-Sergeant Drill | 6,665|
+ | |Company | |
+ |Three |Hydraulic power pumps, George F. Blake Manufacturing | 3,075|
+ | |Company | |
+ |Two |General Electric Company's generators coupled to Ball | 7,626|
+ | |and Wood engines | |
+ |------+------------------------------------------------------+--------|
+ | |Total cost of main items of plant | $79,572|
+ |------+------------------------------------------------------+--------|
+ | SUMMARY OF COST OF ONE PLANT.
+ |-------------------------------------------------------------+--------+
+ |Total cost of main items of plant | $79,572|
+ | | |
+ |Cost of four shields (including installation, demolition, | 103,560|
+ |large additions and renewals, piping, pumps, etc.) | |
+ | | |
+ |Cost of piping, connections, drills, derricks, installation | 101,818|
+ |of offices and all miscellaneous plant | |
+ | | |
+ |Cost of installation, including preparation of site | 39,534|
+ |-------------------------------------------------------------+--------|
+ |Total prime cost of one power-house plant |$324,484|
+ |=============================================================+========|
+
+The following is a short description of each item of plant in Table 2:
+
+_Boilers._--At each shaft there were three 500-h.p., water-tube boilers,
+Class F (made by Sterling and Company, Chicago, Ill.). They had
+independent steel stacks, 54 in. in diameter and 100 ft. above grate
+level; each had 5,000 sq. ft. of heating surface and 116 sq. ft. of
+grate area. The firing was by hand, and there were shaking grates and
+four doors to each furnace. Under normal conditions of work, two boilers
+at each plant were able to supply all the steam required. The average
+working pressure of the steam was 135 lb. per sq. in.
+
+The steam piping system was on the loop or by-pass plan. The diameter of
+the pipes varied from 14 in. in the main header to 10 in. in the body of
+the loop. The diameter of the exhaust steam main increased from 8 in. at
+the remote machines to 20 in., and then to 30 in., at the steam
+separator, which in turn was connected with the condensers. A pipe with
+an automatic relief valve from the exhaust to the atmosphere was used
+when the condensers were shut down. All piping was of the standard,
+flanged extra-heavy type, with bronze-seated gate-valves on the
+principal lines, and globe-valves on some of the auxiliary ones. There
+was an 8-in. water leg on the main header fitted with a Mason-Kelly
+trap, and other smaller water traps were set at suitable intervals.
+
+Each boiler was fitted with safety valves, and there were automatic
+release valves on the high-and low-pressure cylinders of each
+compressor, as well as on each air receiver.
+
+Buckwheat coal was used, and was delivered to the bins on the Manhattan
+side by teams and on the Weehawken side by railroad cars or in barges,
+whence it was taken to the power-house by 2-ft. gauge cars. An average
+of 20 tons of coal in each 24 hours was used by each plant.
+
+The water was taken directly from the public service supply main. The
+daily quantity used was approximately 4,000 gal. for boiler purposes and
+4,400 gal. for general plant use. Wooden overhead tanks having a
+capacity of 14,000 gal. at each plant served as a 12-hour emergency
+supply.
+
+_Feed Pumps._--There were two feed pumps at each plant. They had a
+capacity of 700 cu. ft. per min., free discharge. The plungers were
+double, of 6-in. diameter, and 10-in. stroke, the steam cylinders were
+of 10-in. diameter and 10-in. stroke. An injector of the "Metropolitan
+Double-Tube" type, with a capacity of 700 cu. ft. per min., was fitted
+to each boiler for use in emergencies.
+
+The feed-water heater was a "No. 9 Cochrane," guaranteed to heat 45,000
+lb. of water per hour, and had a total capacity of 85.7 cu. ft. It was
+heated by the exhaust steam from the non-condensing auxiliary plant.
+
+_Condenser Plant._--There were two surface condensers at each plant.
+Each had a cooling surface sufficient to condense 22,500 lb. of steam
+per hour, with water at a temperature of 70° Fahr. and barometer at 30
+in., maintaining a vacuum of 26 in. in the condenser. Each was fitted
+with a Blake, horizontal, direct-acting, vacuum pump.
+
+_Circulating-Water Pumps._--Two circulating-water pumps, supplying salt
+water directly from the Hudson River, were placed on the wharf. They
+were 8-in. centrifugal pumps, each driven by a 36-h.p., General Electric
+Company's direct-current motor (220 volts and 610 rev. per min.), the
+current being supplied from the contractor's power-house generators. The
+pumps were run alternately 24 hours each at a time. Those on the
+Manhattan side were 1,300 ft. from the power-house, and delivered their
+water through a 16-in. pipe; those on the Weehawken side were 450 ft.
+away, and delivered through a 14-in. pipe. There was also a direct
+connection with the city mains, in case of an accident to the salt-water
+pumps.
+
+_Low-Pressure Compressors._--At each plant there were three low-pressure
+compressors. These were for the supply of compressed air to the working
+chambers of the subaqueous shield-driven tunnels. They were also used on
+occasions to supply compressed air to the cylinders of the high-pressure
+compressors, thus largely increasing the capacity of the latter when
+hard pressed by an unusual call on account of heavy drilling work in the
+rock tunnels. They were of a new design, of duplex Corliss type, having
+cross-compound steam cylinders, designed to operate condensing, but
+capable of working non-condensing; the air cylinders were simple duplex.
+The steam cylinder valves were of the Corliss release type, with vacuum
+dash-pots. The valves in the air cylinders were mechanically-operated
+piston valves, with end inlet and discharge. The engines used steam at
+135 lb. pressure. The high-and low-pressure steam cylinders were 14 in.
+and 30 in. in diameter, respectively, with a stroke of 36 in. and a
+maximum speed of 135 rev. per min. The two air cylinders were 23½ in.
+in diameter, and had a combined capacity of 35.1 cu. ft. of free air per
+revolution, and, when running at 125 rev. per min., each machine had an
+actual capacity of 4,389 cu. ft. of free air per min., or 263,340 cu.
+ft. per hour. The air cylinders were covered by water-jackets through
+which salt water from the circulating pumps flowed. A gauge pressure of
+50 lb. of air could be obtained.
+
+Each compressor was fitted with an automatic speed and air-pressure
+regulator, designed to vary the cut-off according to the volume of air
+required, and was provided with an after-cooler fitted with tinned-brass
+tube and eight Tobin-bronze tube-plates having 809 sq. ft. of cooling
+surface; each one was capable of reducing the temperature of the air
+delivered by it to within 10° Fahr. of the temperature of the cooling
+water when its compressor was operated at its fullest capacity. From the
+after-cooler the air passed into a vertical receiver, 4 ft. 6 in. in
+diameter and 12 ft. high, there being one such receiver for each
+compressor. The receivers were tested to a pressure of 100 lb. per sq.
+in. The after-coolers were provided with traps to collect precipitated
+moisture and oil. The coolers and receivers were fitted with safety
+valves set to blow off at 1 lb. above the working pressure. The air
+supply was taken from without, and above the power-house roof, but in
+very cold weather it could be taken from within doors.
+
+_High-Pressure Compressors._--There was one high-pressure compressor at
+each plant. Each consisted of two duplex air cylinders fitted to a
+cross-compound, Corliss-Bass, steam engine. The two steam cylinders were
+14 and 26 in. in diameter, respectively, and the air cylinders were
+14¼ in. in diameter and had a 36-in. stroke. The air cylinder was
+water-jacketed with salt water supplied from the circulating water
+pumps.
+
+The capacity was about 1,100 cu. ft. of free air per min. when running
+at 85 rev. per min. and using intake air at normal pressure, but, when
+receiving air from the low-pressure compressors at a pressure of 30 lb.
+per sq. in., the capacity was 3,305 cu. ft. of free air per min.;
+receiving air at 50 lb. per sq. in., the capacity would have been 4,847
+cu. ft. of free air per min. This latter arrangement, however, called
+for more air than the low-pressure compressors could deliver. With the
+low-pressure compressor running at 125 rev. per min. (its maximum
+speed), it could furnish enough air at 43.8 lb. per sq. in. to supply
+the high-pressure compressor running at 85 rev. per min. (its maximum
+speed); and, with the high-pressure compressor delivering compressed air
+at 150 lb., the combined capacity of the arrangement would have been
+4,389 cu. ft. of free air per min.
+
+The air passed through a receiver, 4 ft. 6 in. in diameter and 12 ft.
+high, tested under a water pressure of 225 lb. per sq. in., before being
+sent through the distributing pipes.
+
+_Hydraulic Power Pumps._--At each power-house there were three hydraulic
+power pumps to operate the tunneling shields. One pump was used for each
+tunnel, leaving the third as a stand-by. The duplex steam cylinders were
+15 in. in diameter, with a 10-in. stroke; the duplex water rams were
+2-1/8 in. in diameter with a 10-in. stroke. The pumps were designed to
+work up to 6,000 lb. per sq. in., but the usual working pressure was
+about 4,500 lb. The piping, which was extra heavy hydraulic, was
+connected by heavy cast-steel screw couplings having a hexagonal
+cross-section in the middle to enable tightening to be done with a bolt
+wrench. The piping was designed to withstand a pressure of 5,500 lb. per
+sq. in.
+
+_Electric Generators._--At each plant there were two electric generators
+supplying direct current for both lighting and power, at 240 volts,
+through a two-wire system of mains. They were of Type M-P, Class 6, 100
+kw., 400 amperes, 250 rev. per min., 240 volts no load and 250 volts
+full load. They were connected direct to 10 by 20 by 14-in.,
+center-crank, tandem-compound, engines of 150 h.p. at 250 rev. per min.
+A switch-board, with all the necessary fuses, switches, and meters, was
+provided at each plant.
+
+_Lubrication._--In the lubricating system three distinct systems were
+used, each requiring its own special grade of oil.
+
+The journals and bearings were lubricated with ordinary engine oil by a
+gravity system; the oil after use passed through a "White Star" filter,
+and was pumped into a tank about 15 ft. above the engine-room floor.
+
+The low-pressure air cylinders were lubricated with "High Test" oil,
+having a flash point of 600° Fahr. The oil was forced from a receiving
+tank into an elevated tank by high-pressure air. When the tank was full
+the high-pressure air was turned off and the low-pressure air was turned
+on, in this way the air pressure in the oil tank equalled that in the
+air cylinder being lubricated, thus allowing a perfect gravity system to
+exist.
+
+The steam cylinders and the high-pressure air cylinders were fed with
+oil from hand-fed automatic lubricators made by the Detroit Lubrication
+Company, Detroit, Mich.
+
+"Steam Cylinder" oil was used for the steam cylinders and "High Test"
+oil (the same as used for the low-pressure air cylinders) for the
+high-pressure air cylinders. The air cylinder and steam cylinder
+lubricators were of the same kind, except that no condensers were
+necessary. The steam cylinder and engine oil was caught on drip pans,
+and, after being filtered, was used again as engine oil in the bearings.
+The oil from the air cylinders was not saved, nor was that from the
+steam cylinders caught at the separator.
+
+_Cost of Operating the Power-House Plants._--In order to give an idea of
+the general cost of running these plants, Tables 3 and 4 are given as
+typical of the force employed and the general supplies needed for a
+24-hour run of one plant. Table 3 gives a typical run during the period
+of driving the shields, and Table 4 is typical of the period of concrete
+construction. In the latter case the tunnels were under normal air
+pressure. Before the junction of the shields, both plants were running
+continuously; after the junction, but while the tunnels were still under
+compressed air, only one power-house plant was operated.
+
+TABLE 3.--COST OF OPERATING ONE POWER-HOUSE FOR 24 HOURS DURING
+EXCAVATION AND METAL LINING.
+
+ ===+===================+====================+=============
+ No.| Labor. | Rate per day. | Amount.
+ ---+-------------------+--------------------+-------------
+ 6 |Engineers | $3.00 | $18.00
+ 6 |Firemen | 2.50 | 15.00
+ 2 |Oilers | 2.00 | 4.00
+ 2 |Laborers | 2.00 | 4.00
+ 4 |Pumpmen | 2.75 | 11.00
+ 2 |Electricians | 3.50 | 7.00
+ 1 |Helper | 3.00 | 3.00
+ ---+-------------------+--------------------+-------------
+ Total per day | $62.00
+ --------------------------------------------+-------------
+ Total for 30 days | $1,860.00
+ --------------------------------------------+-------------
+ Supplies.
+ -----------------------+--------------------+-------------
+ Coal (14 tons per day) | $3.25 | $45.50
+ Water | 7.00 | 7.00
+ Oil (4 gal. per day) | 0.50 | 2.00
+ Waste (4 lb. per day) | 0.07 | 0.28
+ Other supplies | 1.00 | 1.00
+ -----------------------+--------------------+-------------
+ Total per day | $55.78
+ --------------------------------------------+-------------
+ Total for 30 days | $1,673.00
+ --------------------------------------------+-------------
+ Total cost of labor and supplies for 30 days| $3,533.00
+ ============================================+=============
+
+_Stone-Crusher Plant._--A short description of the stone-crusher plant
+will be given, as it played an important part in the economy of the
+concrete work. In order to provide crushed stone for the concrete, the
+contractor bought (from the contractor who built the Bergen Hill
+Tunnels) the pile of trap rock excavated from these tunnels, which had
+been dumped on the piece of waste ground to the north of Baldwin Avenue,
+Weehawken, N. J.
+
+The general layout of the plant is shown on Plate XXX. It consisted of a
+No. 6 and a No. 8 Austin crusher, driven by an Amex, single-cylinder,
+horizontal, steam engine of 120 h.p., and was capable of crushing about
+225 cu. yd. of stone per 10-hour day. The crushers and conveyors were
+driven from a countershaft, in turn driven from the engine by an 18-in.
+belt.
+
+TABLE 4.--COST OF OPERATING THE ONE PLANT FOR 24 HOURS DURING CONCRETE
+LINING.
+
+ ===+===================+====================+=============
+ No.| Labor. | Rate per day. | Amount.
+ ---+-------------------+--------------------+-------------
+ 2 |Engineers | $3.00 | $6.00
+ 2 |Firemen | 2.50 | 5.00
+ 2 |Pumpmen | 3.00 | 6.00
+ 1 |Foreman Electrician| 6.00 | 6.00
+ 1 |Electrician | 3.00 | 3.00
+ 1 |Laborer | 2.00 | 2.00
+ ---+-------------------+--------------------+-------------
+ Total per day | $28.00
+ --------------------------------------------+-------------
+ Total for 30 days | $840.00
+ --------------------------------------------+-------------
+ Supplies.
+ -----------------------+--------------------+-------------
+ Coal (14 tons per day) | $3.15 | $44.10
+ Oil (4 gal. per day) | 0.50 | 2.00
+ Water | 13.00 | 13.00
+ Other supplies | 2.00 | 2.00
+ -----------------------+--------------------+-------------
+ Total per day | $61.10
+ --------------------------------------------+-------------
+ Total for 30 days | $1,833.00
+ --------------------------------------------+-------------
+ Total cost of labor and supplies for 30 days| $2,673.00
+ ============================================+=============
+
+The process of crushing was as follows: The stone from the pile was
+loaded by hand into scale-boxes which were lifted by two derricks into
+the chute above the No. 6 crusher. One derrick had a 34-ft. mast and a
+56-ft. boom, and was worked by a Lidgerwood steam hoister; the other had
+a 23-ft. mast and a 45-ft. boom, and was worked by a "General Electric"
+hoist. All the stone passed first through the No. 6 crusher, after which
+it was lifted by a bucket conveyor to a screen, placed about 60 ft.
+higher than and above the stone bin. The screen was a steel chute
+pierced by 2½-in. circular holes, and was on a slope of about 45°; in
+order to prevent the screen from choking, it was necessary to have two
+men continually scraping the stone over it with hoes. All the stone
+passing the screen was discharged into a bin below with a capacity of
+about 220 cu. yd. The stone not passing the screen passed down a
+diagonal chute to a No. 8 crusher, from which, after crushing, it was
+carried back by a second bucket conveyor to the bin, into which it was
+dumped without passing a screen. The No. 8 crusher was arranged so that
+it could, when necessary, receive stone direct from the stone pile. The
+cars in which the stone was removed could be run under the bin and
+filled by opening a sliding door in the bottom of the bin. A track was
+laid from the bin to connect with the contractor's surface railway in
+the Weehawken Shaft yard, and on this track the stone could be
+transported either to the Weehawken Shaft direct, for use on that side
+of the river, or to the wharf, where it could be dumped into scows for
+transportation to New York.
+
+The cars used were 3-cu. yd. side-dump, with flap-doors, and were hauled
+by two steam Dinky locomotives.
+
+The average force employed was:
+
+ 1 foreman @ $3.00 per day. Supervising.
+ 24 laborers " 1.75 " " Loading scale-boxes for derricks.
+ 4 laborers " 1.75 " " Feeding crushers.
+ 2 laborers " 1.75 " " Watching screens to prevent clogging.
+ 1 engineer " 4.00 " " Driving steam engine.
+ 2 engineers " 3.50 " " On the derricks.
+ 1 night watchman. Watching the plant at night.
+
+Owing to the constant break-down of machinery, chutes, etc., inseparable
+from stone-crushing work, there was always at work a repair gang
+consisting of either three carpenters or three machinists, according to
+the nature of the break-down.
+
+The approximate cost of the plant was:
+
+ Machinery $5,850
+ Lumber 3,305
+ Erection labor 3,999
+ ------
+ Total $13,154
+
+The cost of the crushed stone at Weehawken amounted to about $0.91 per
+cu. yd., and was made up as follows:
+
+ Cost of stone $0.22
+ Labor in operation of plant 0.31
+ Plant supplies 0.11
+ [B]Plant depreciation 0.27
+ -----
+ Total $0.91
+
+[B] Assuming that the scrap value of derricks and engines is one-half
+the cost, crushers one-third the cost, and other items nothing.
+
+The crushed stone at the Manhattan Shaft cost about $1.04 per cu. yd.,
+the difference of $0.13 from the Weehawken cost being made up of the
+cost of transfer across the river, $0.08, and transport from the dock to
+the shaft, $0.05.
+
+_Miscellaneous Plant._--The various pieces of plant used directly in the
+construction work, such as derricks, hauling engines, pumps, concrete
+mixers, and forms, will be found described or at least mentioned in
+connection with the methods used in construction.
+
+The tunneling shields, however, will be described now, as much of the
+explanation of the shield-driven work will not be clear unless preceded
+by a good idea of their design.
+
+
+Tunneling Shields.
+
+During the period in which the original contract drawings were being
+made, namely, in the latter part of 1903 and the early part of 1904,
+considerable attention was given to working out detailed studies for a
+type of shield which would be suitable for dealing with the various
+kinds of ground through which the shield-driven tunnels had to pass.
+This was done in order that, when the contract was let, the engineer's
+ideas of the requirements of the shields should be thoroughly
+crystallized, and so that the contractor might take advantage of this
+long-thought-out design, instead of being under the necessity of placing
+a hurried order for a piece of plant on which so much of the safety as
+well as of the speed of his work depended. Eventually, the contractor
+took over these designs as they stood, with certain minor modifications,
+and the shields as built and worked gave entire satisfaction. The chief
+points held in view were ample strength, easy access to the working face
+combined with ease and quickness of closing the diaphragm, and general
+simplicity. A clear idea of the main features of the design can be
+gathered from Fig. 3 and Plate XXXI.
+
+[A]The interior diameter of the skin was 2 in. greater than the
+external diameter of the metal lining of the tunnel, which was 23 ft.
+The skin was made up of three thicknesses of steel plate, a ¾-in.
+plate outside and inside, with a 5/8-in. plate between; thus the
+external diameter of the skin was 23 ft. 6¼ in. The length over all
+(exclusive of the hood, to be described later) was 15 ft. 11-7/16 in.
+The maximum overlap of the skin over the erected metal lining was 6 ft.
+4½ in., and the minimum overlap, 2 ft.
+
+There were no inside or outside cover-plates, the joints of the various
+pieces of skin plates being butt-joints covered by the overlap of
+adjoining plates. All riveting was flush, both inside and outside. The
+whole circumference of each skin plate was made up of eight pieces, each
+of which extended the entire length of the shield, the only
+circumferential joint on the outside being at the junction of the
+removable cutting edge (or of the hood when the latter was in position)
+with the shield proper.
+
+Forward of the back ends of the jacks, the shield was stiffened by an
+annular girder supporting the skin, and in the space between the
+stiffeners of which were set the 24 propelling rams used to shove the
+shield ahead by pressure exerted on the last erected ring of metal
+lining, as shown on Plate XXXI.
+
+To assist in taking the thrust of these rams, gusset-plates were placed
+against the end of each ram cylinder, and were carried forward to form
+level brackets supporting the cast-steel cutting-edge segments. The
+stiffening gussets, between which were placed the rams, were also
+carried forward as level brackets, for the same purpose. The cast-steel
+segmental cutting edge was attached to the front of the last mentioned
+plates.
+
+The interior structural framing consisted of two floors and three
+vertical partitions, giving nine openings or pockets for access to the
+face; these pockets were 2 ft. 7 in. wide, the height varying from 2 ft.
+2 in. to 3 ft. 4 in., according to their location. The openings were
+provided with pivoted segmental doors, which were adopted because they
+could be shut without having to displace any ground which might be
+flowing into the tunnel, and while open their own weight tended to close
+them, being held from doing so by a simple catch.
+
+[Illustration: PROPOSED SHIELD FOR SUBAQUEOUS TUNNELING GENERAL
+ELEVATION FIG. 3.]
+
+For passing through the varied assortment of ground before entering on
+the true sub-river silt, it was decided to adopt the forward detachable
+extension, or hood, which has so often proved its worth in ground
+needing timber for its support, as shown in Fig. 2, Plate XXIX. This
+hood extended 2 ft. 1 in. beyond the cutting edge, and from the top down
+to the level of the upper platform. Additional pieces were provided by
+which the hood might have been brought down as far as the lower
+platform, but they were not used. Special trapezoidal steel castings
+formed the junction between the hood and the cutting edge. The hood was
+in nine sections, built up of two ¾-in. and one 5/8-in. skin plates,
+as in the main body of the skin, and was supported by bracket plates
+attached to the forward ends of the ram chambers. The hoods were bolted
+in place, and were removed and replaced by regular cutting-edge steel
+castings after the shields had passed the river lines.
+
+The floors of the two platforms, of which there were eight, formed by
+the division of the platforms by the upright framing, could be extended
+forward 2 ft. 9 in. in front of the cutting edge, or 8 in. in front of
+the hood. This motion was given by hydraulic jacks. The sliding platform
+could hold a load of 7,900 lb. per sq. ft., which was equal to the
+maximum head of ground and water combined. The uses of these platforms
+will be described under the heading "Construction." The weight of the
+structural portion of each shield was about 135 tons.
+
+The remainder of the shield was the hydraulic part, which provided its
+motive force and gave the power to the segment erector. The hydraulic
+fittings weighed about 58 tons per shield, so that the total weight of
+each shield was about 193 tons. The hydraulic apparatus was designed for
+a maximum pressure of 5,000 lb. per sq. in., a minimum pressure of 2,000
+lb., and a test pressure of 6,000 lb. The actual average pressure used
+was about 3,500 lb. per sq. in.
+
+There were 24 shoving rams, with a diameter of 8½ in. and stroke of
+38 in. The main ram was single-acting. The packings could be tightened
+up from the outside without removing the ram, a thing which is of the
+greatest convenience, and cannot be done with the differential plunger
+type. Some of the chief figures relating to the shield rams, with a
+water pressure of 5,000 lb. per sq. in., are:
+
+ Forward force of one ram 275,000 lb.
+ Forward force of 24 rams (all) 6,600,000 "
+ Forward force of 24 rams 3,300 tons of 2,000 lb.
+ Equivalent pressure per square inch of face 105 lb.
+ Equivalent pressure per square foot of face 15,200 "
+ Pull-back force of one ram 26,400 "
+ Pull-back pressure on full area of ram 480 " per sq. in.
+
+The rams developed a tendency to bend, under the severe test of shoving
+the shield all closed, or nearly so, through the river silt, and it is
+probable that it would have been better to make the pistons 10 in. in
+diameter instead of 8½ in.
+
+Each sliding platform was actuated by two single-acting rams, 3½ in.
+in diameter and having a stroke of 2 ft. 9 in. The rams were attached to
+the rear face of the shield diaphragm inside the box floors, and the
+cylinders were movable, sliding freely on bearings in the floor. The
+front ends of the cylinders were fixed to the front ends of the sliding
+platforms. The cylinder thus supported the front end of the sliding
+platform, and was designed to carry its half of the load on the
+platform. Some of the leading figures in connection with the platform
+rams, at a working pressure of 5,000 lb. per sq. in., are:
+
+ Forward force of each pair of rams (in each platform) 96,000 lb.
+ Total area of nose of sliding platform 1,060 sq. in.
+ Maximum reaction per square inch on nose 90 lb.
+ Maximum reaction per square foot on nose 13,040 "
+
+Each shield was fitted with a single erector mounted on the rear of the
+diaphragm. The erector consisted of a box-shaped frame mounted on a
+central shaft revolving on bearings attached to the shield. Inside of
+this frame there was a differential hydraulic plunger, 4 in. and 3 in.
+in diameter and of 48-in. stroke. To the plunger head were attached two
+channels sliding inside the box frame, and to the projecting ends of
+these the grip was attached. At the opposite end of the box frame a
+counterweight was attached which balanced about 700 lb. of the tunnel
+segment at 11 ft. radius.
+
+The erector was revolved by two single-acting rams fixed horizontally to
+the back of the shield above the erector pivot through double chains and
+chain wheels keyed to the erector shaft.
+
+The principal figures connected with the erector, assuming a water
+pressure of 5,000 lb. per sq. in., are:
+
+ Weight of heaviest tunnel segment 2,584 lb.
+ Weight of erector plunger and grip 616 "
+ Total weight to be handled by the erector ram 3,200 "
+ Total force in erector ram moving from center of shield 35,000 "
+ Total force in erector ram moving toward center of shield 27,500 "
+ Weight at 11-ft. radius which is balanced by counterweight 700 "
+ Maximum net weight at 11-ft. radius to be handled by
+ turning rams 1,884 "
+ Total force of each rotating ram, at 5,000 lb. per sq. in. 80,000 "
+ Load at 11-ft. radius, equivalent to above 3,780 "
+
+When the shield was designed, a grip was also designed by which the
+erector could handle segments without any special lugs being cast on
+them. A bolt was passed through two opposite bolt holes in the
+circumferential flanges of a plate. The grip jaws closed over this bolt
+and locked themselves. The projecting fixed ends of the grip were for
+taking the direct thrust on the grip caused by the erector ram when
+placing a segment.
+
+It happened, however, that there was delay in delivering these grips,
+and, when the shield was ready to start, and the grip was not
+forthcoming, Mr. Patrick Fitzgerald, the Contractor's Superintendent,
+overcame this trouble by having another grip made.
+
+In this design, also, a self-catching bolt is placed through the segment
+and the grip catches the bolt. In simplicity and effectiveness in
+working, this new design eventually proved a decided advance on the
+original one, and, as a result, all the shields were fitted with the new
+grip, and the original design was discarded.
+
+The great drawback to the original grip was that the plate swung on the
+lifting bolt, and thus brought a great strain on the bolt when held
+rigidly at right angles to the erector arm. The original design was able
+to handle both _A_ and _B_ segments, and key segments, without
+alteration; in the new design, an auxiliary head had to be swung into
+position to handle the key, but this objection did not amount to a
+practical drawback.
+
+The operating floor from which the shield was controlled, and at which
+the valves were situated, was placed above the rams which rotate the
+erector, and formed a protection for them. The control of the shield
+rams was divided into four groups: the seven lower rams constituted one
+group, the upper five, another, and the six remaining on each side, the
+other two. Each group was controlled by its own stop and release valve.
+Individual rams were controlled by stop-cocks.
+
+The control of the sliding platform rams was divided into two groups, of
+which all the rams on the upper floor made one, and all those in the
+lower floor, the other; here, again, each group had its own stop and
+release valve, and individual platforms were controlled by stop-cocks
+arranged in blocks from which the pipes were carried to the rams.
+
+The in-and-out movements of the erector ram were controlled by a
+two-spindle, balanced, stop and release valve, controlled by a
+hand-wheel. The erector rotating rams were controlled by a similar
+valve, with four spindles, also operated by a single hand-wheel. Both
+wheels were placed inside the top shield pockets, and within easy reach
+of the operating platform.
+
+The hydraulic pressure was brought through the tunnel by a 2-in.
+hydraulic pipe. Connection with the shield was made by a flexible copper
+pipe, the 2-in. line being extended as the shield advanced.
+
+
+LAND TUNNELS.
+
+General.
+
+The following is a brief account of the main features of the "Land
+Tunnel" work, by which is meant all the part of the structure built
+without using tunneling shields.
+
+The Land Tunnels consist of about 977 ft. of double tunnel on the New
+York side and 230 ft. on the New Jersey side, or a total of 1,207 lin.
+ft. of double tunnel.
+
+The general design of the cross-section consists of a semi-circular
+arch, vertical side-walls and a flat invert. The tunnel is adapted for
+two lines of track, each being contained in its compartment or tunnel.
+The span of the arch is wider than is absolutely necessary to take the
+rolling stock, and the extra space is utilized by the provision of a
+sidewalk or "bench" forming by its upper surface a gangway, out of the
+way of traffic, for persons walking in the tunnels, and embedded in its
+mass are a number of vitrified earthenware ducts, for high-and
+low-tension electric cables. The provision of this bench enables its
+vertical wall to be brought much nearer to the side of the rolling stock
+than is usually possible, thus minimizing the effects of a derailment or
+other accident. Refuge niches for trackmen, and ladders to the top of
+the bench are provided at frequent intervals. In cases where a narrow
+street limits the width of the structure, as on the New York side, the
+two tunnels are separated by a medial wall of masonry, thus involving
+excavation over the entire width of both tunnels, and in such case the
+tunnels are spoken of as "Twin Tunnels"; where the exigencies of width
+are not so severe, the two tunnels are entirely distinct, and are
+separated by a wall of rock. This type is found on the Weehawken side.
+The arches are of brick, the remainder of the tunnel lining being of
+concrete.
+
+
+New York Land Tunnels.
+
+The work on the Land Tunnels on the Manhattan side was carried on from
+the shaft at 11th Avenue and 32d Street.
+
+The plans and designs for these tunnels are shown on Plate XXXII. In
+this short length of about 977 ft. there are no less than nine different
+kinds of cross-section. The reason for these changes is the fact that
+the two lines of track are here not straight and parallel to the center
+line between the tunnels, but are curved, although symmetrical about
+this center line. The various changes of section are to enable the
+tunnels to be built in straight lengths, thus avoiding the disadvantages
+attending the use of curved forms, and at the same time minimizing the
+quantity of excavation, an item which accounts for from 60 to 70% of the
+total cost of tunnels of this type. Of course, there are corresponding
+and obvious disadvantages in the adoption of many short lengths of
+different cross-sections, and these disadvantages were well brought out
+in the course of the work; on the whole, however, they may be said to
+have justified their adoption. These New York Land Tunnels were divided
+into three contracts, viz.: From Station 190 + 15 (the Portal to the
+open work of the Terminal Station at the east side of Tenth Avenue, New
+York City) to Station 197 + 60, called "Section Gy-East." The next
+contract, called "Section Gy-West Supplementary," extended from Station
+197 + 60 to Station 199 + 20, which is the east side of Eleventh Avenue.
+The third contract was called "Section Gy-West," and extended from
+Station 199 + 20 to Station 231 + 78 (the dividing line between the
+States of New York and New Jersey). Thus, for nearly all its length,
+this contract consists of shield-driven tunnel. The portion between
+Stations 199 + 20 and 199 + 91.5, however, was of the Land Tunnel type,
+and therefore will be included here. A fourth contract extended from
+Station 231 + 78 to the Weehawken Shaft at Station 263 + 50, and of this
+all but 230 ft. was of the shield-driven type, only the portion next to
+the Weehawken Shaft being of the Land Tunnel type.
+
+The four contracts were let to one contractor (The O'Rourke Engineering
+Construction Company), and the work was carried on simultaneously in all
+four, so that the division into contracts had no bearing on the methods
+of work adopted, and these will now be described as a whole and with no
+further reference to the different sections.
+
+
+Excavation.
+
+Work was started on the New York side on April 18th, 1904, the Weehawken
+shaft being at that date still under construction. As will have been
+noted in the description of the shafts, the contractor found a shaft
+already prepared for his use, and cross-drifts at grade and at right
+angles to the future tunnels, and extending across their entire width.
+The first essential was to get access to the shield chambers, which were
+to lie about 330 ft. to the west of the shaft, so that the construction
+of these enlargements in which the shields for the subaqueous tunnels
+were to be built might be finished as soon as possible and thus allow
+the earliest possible start to be made with the shield-driven tunnels.
+
+With this in view, two bottom headings, on the center line of each of
+the two tracks, were driven westward from the western cross-heading at
+the foot of the shaft. When about 138 ft. had been made in this way,
+the two headings were brought together and a break-up was made to the
+crown level of the tunnel, as the depth of rock cover was doubtful. From
+this break-up a top heading was driven westward to Station 200 + 30.
+While widening the heading out at Station 200 + 20 the rock was
+penetrated on the south side. The exposed wet sand and gravel started to
+run, and, as a consequence, a change in design was made, the shield
+chambers (and consequently the start of the shield-driven tunnels) being
+moved eastward from their original location 133 ft. to their present
+location. A certain amount of time was necessarily spent in making these
+changes of design, which involved a rearrangement of the whole layout
+from the Terminal Station to the start of the River Tunnels. On July
+5th, 1904, however, the new design was formally approved. No sooner had
+this been decided than a strike arose on the work, and this was not
+settled until August 1st, 1904, but from that time the work progressed
+without delay. No further reference will be made to the work in the
+shield chambers, as that will come under the heading of "River Tunnels,"
+being of the segmental, cast-iron lined type.
+
+A top heading was now driven over the original bottom heading west of
+the shaft, and at the same time the original cross-drifts from the shaft
+were amalgamated with and broken down by a heading driven at the crown
+level of the "Intercepting Arch" which here cuts across the ordinary run
+of tunnel at right angles and affords access to the tunnels from the
+shafts.
+
+The excavation of the upper portion of the intercepting arch at its
+southern end gave some trouble, and caused some anxiety, as the rock
+cover was penetrated and the wet sand and gravel were exposed. This made
+it necessary to timber all this section heavily, and the tracks of the
+New York Central Railroad directly above were successfully supported.
+The general way in which this timbering was carried out will be
+described under the head of "Timbering."
+
+Meanwhile, the excavation of the tunnels west of the intercepting arch
+was continued until the North and South Tunnels were taken out to their
+full outlines, leaving a core of rock between them. This core was
+gradually removed, and timbering supporting the rock above the middle
+wall was put in as excavation went on. The ground, which was entirely of
+micaceous schist, typical of this part of Manhattan, seamed with veins
+of granite, was rather heavy at the west end, or adjacent to the shield
+chambers, and required complete segmental timbering across the whole
+span. One heavy fall of rock in the corewall between the North and South
+Tunnels took place on November 2d, but fortunately did not extend beyond
+the limits of the permanent work. On November 7th, 1904, the excavation
+east of the intercepting arch was begun by driving a bottom heading in
+the South Tunnel. This was continued to Station 197 + 14 and then was
+taken up to the crown level and worked as a top heading with the view of
+keeping track, by making exploratory borings upward from the roof at
+frequent intervals, of the rock surface, which was here irregular and
+not known with any degree of certainty. The work was not pressed with
+any vigor, because all efforts were then being bent toward excavating
+from the River Tunnels as much rock as possible. In Section Gy-East the
+conditions were exceptionally variable, as the rock was subject to
+sudden changes from a soft crumbling mica schist to broad bands of hard
+granite, and, in addition, the rock surface was very irregular, and, for
+a good length of this section, was below the crown of the tunnel, a
+condition which led to the adoption of the cut-and-cover method for part
+of the work.
+
+The irregularity in conditions called for varying methods of procedure,
+but in general the methods were as shown on Plate XXXIII, and described
+as follows:
+
+_In Solid Rock._--Where there was plenty of good rock cover, a top
+middle heading was driven, which was afterward widened out to the full
+cross-section of the twin tunnel arches. If necessary, a few lengths of
+segmental timbering were put in before taking down the bench, which was
+generally kept some 40 or 50 ft. behind the breast of the heading. After
+the bench was down, the middle conduit trench was excavated and the
+trimming done.
+
+_In Soft Rock._--Where there was not enough rock cover, or where there
+was actual soft ground in the roof, wall-plate headings at the springing
+line level were driven ahead of the remainder of the work. The
+wall-plates were laid in these, the roof was taken out in short lengths,
+and segmental timbering spanning from wall-plate to wall-plate was put
+in. The roof being thus held, the bench excavation proceeded without
+trouble. Where the rock was penetrated and soft ground showed in the
+roof, poling boards were driven ahead over the crown-bars, as shown in
+Fig. 4.
+
+_Cut-and-Cover Work._--After some 225 ft. had been driven from the
+intercepting arch, it was found that the crown of the tunnel was
+continually in soft ground. To ascertain the extent of this condition
+the contractor decided to make soundings as far as Tenth Avenue, which
+was done by sinking trial pits and making wash-borings in the street.
+These soundings showed that there would be soft ground in the crown from
+Station 194 + 75 to Station 194 + 25 (at one point to a depth of 12 ft.
+below the crown), and on each side of this section the cover was
+insufficient from Station 193 + 58 to Station 195 + 30. This condition
+being known, it was decided to adopt cut-and-cover work for this length,
+the principal reasons being that repairs to sewers, streets, and drains
+would be no more, and probably less, expensive than with the tunnel
+method; the underpinning of a heavy brick brewery building adjoining the
+works on the north side would be facilitated, and the opening in the
+street, through which muck and materials could be handled, would relieve
+the congested shaft, through which the large volume of muck from the
+River Tunnels was then being conveyed. On the other hand, the
+cut-and-cover method was adversely affected by the presence of a heavy
+timber trestle built down the south side of the street and over which
+passed all the excavation from the Terminal Station, amounting to a very
+heavy traffic. As this trestle had to be supported, it complicated the
+situation considerably. Very little active progress was made between
+June, 1905, and April, 1906, as the contractor's energies during that
+time were much taken up with the progress of the shield-driven tunnels.
+In April, 1906, preparations were made to start a 50-ft. length of open
+cut, rangers being fixed and sheathing driven; and the sewer which ran
+down the middle of this street was diverted to the outside of the
+open-cut length.
+
+April and May were occupied in driving the sheathing down to rock,
+supporting the trestle, underpinning the adjoining brewery, and
+excavating the soft material above the rock. On June 2d, 1906, rock was
+reached, and, by July 31st, the excavation was down to subgrade over
+nearly the whole 50 ft. in the first length. In the meantime another
+length was opened up, and eventually a third.
+
+The surface of the rock now seemed to be rising, and the heavy buildings
+had been passed, so that tunneling was reverted to for the rest of the
+work, though many difficulties were caused by soft rock in the roof from
+time to time.
+
+[Illustration: METHOD OF DRIVING ROOF LAGGING IN SOFT GROUND. FIG. 4.]
+
+When the excavation for the open-cut work of the Terminal Station had
+advanced to the line of Tenth Avenue, the contractor started a heading
+from this point and drove westward under Tenth Avenue until the headings
+driven eastward from the cut-and-cover portion, were met.
+
+This was done to expedite the work under Tenth Avenue, where the ground
+was not very good, where there were several important gas and water
+mains in the street, and where, moreover, the tunnels were of
+exceptionally large span (24 ft. 6 in.), making a total width of some 60
+ft. for the excavation. The excavation for the New York Tunnels was
+practically finished in January, 1908.
+
+_Drilling and Blasting._--The foregoing short description will serve to
+show in a general way the scheme adopted in making the excavation. A few
+details on drilling and blasting methods may not be out of place.
+
+Percussive drills run by air pressure were used. They were
+Ingersoll-Sergeant, Nos. 3½, A-86, C-24, and F-24. The air came from
+the high-pressure compressor previously described. This compressor,
+without assistance, could supply air for nine drills, but, when fed by
+compressed air from the lower pressure, its capacity was increased three
+or four times.
+
+The air was compressed to 100 lb. per sq. in. in the power-house, and
+was delivered at about 80 lb. per sq. in. at the drills. A 3-in. air
+line was used. The drill steel was 1-1/8-to 1-3/8-in. octagonal. The
+holes were about 3¼ in. in diameter at starting and 2-5/8 in. at the
+full depth of 10 ft. The powder used on the New York side was 40%
+Forcite, the near presence of heavy buildings and lack of much rock
+cover necessitating light charges and many holes spaced close together.
+
+To compensate the contractor for the inevitable excavation done outside
+the neat lines of the masonry lining, the excavation was paid for to the
+"Standard Section Line" which was 12 in. outside the neat lines on top
+and sides and 6 in. outside at the bottom of the cross-section. The
+actual amount of excavation done was about 11% greater than that paid
+for. The distance excavated beyond the neat line, because of the very
+heavy timbering necessary, was about 2.1 ft. instead of the 1 ft.
+allowed, and at the bottom about 0.85 ft. instead of the 0.50 ft. paid
+for.
+
+For a period of 5 months detailed records were kept of the drilling and
+blasting. About 12,900 cu. yd. of excavation are included. A sketch and
+table showing the method of driving the heading, the number and location
+of the holes drilled, and the amount of powder used, is given in Fig. 5.
+From this and similar figures the information in Table 5 is derived.
+
+TABLE 5.
+
+ +========================+=======+=======+=======+======+=======+======|
+ | | FEET OF HOLE | POUNDS OF POWDER |
+ | |DRILLED PER CUBIC YARD | USED PER CUBIC YARD |
+ | | OF EXCAVATION. | OF EXCAVATION. |
+ | +-------+-------+-------+------+-------+------|
+ |Portion of excavation. |15-ft. |19-ft. |24-ft. | | | |
+ | | 4-in. | 6-in. | 6-in. |15-ft.|19-ft. |24-ft.|
+ | |span-- |span-- |span-- |4-in. | 6-in. | 6-in.|
+ | | twin | twin | twin | | | |
+ | |tunnel.|tunnel.|tunnel.| | | |
+ |------------------------+-------+-------+-------+------+-------+------+
+ |Wall-plate heading[C] | 13.0 | 10.97 | 10.97 |3.77 | 2.85 | 2.85 |
+ | | | | | | | |
+ |Total heading[C] | 7.87 | 8.17 | 7.81 |2.31 | 2.02 | 1.78 |
+ | | | | | | | |
+ |Bench and raker bench[C]| 5.97 | 6.15 | 7.56 |0.94 | 0.93 | 1.13 |
+ | | | | | | | |
+ |Trench[C] | 9.82 | 15.96 | 18.10 |1.84 | 2.49 | 2.73 |
+ |------------------------+-------+-------+-------+------+-------+------+
+ |Average for section[C] | 6.69 | 7.43 | 8.95 |1.28 | 1.30 | 1.45 |
+ |------------------------+-------+-------+-------+------+-------+------|
+ |Actual amount[D] | 6.82 | 7.27 | 8.95 |1.22 | 1.24 | 1.27 |
+ +========================+=======+=======+=======+======+=======+======+
+
+[C] Figures taken from typical cross-sections.
+
+[D] This gives the actual amount of drilling done and powder used per
+cubic yard for the whole period of 5 months of observation, but as this
+length included 280 ft. of heading and only 220 ft. of bench, the
+average figures (for powder especially) are too low.
+
+Table 6 gives the rate and cost of drilling, and the cost of powder. It
+will be seen that the average rate of drilling was 2.71 ft. per hour per
+drill or 27.1 ft. per drill per shift.
+
+Table 7 shows the result of observation as to the time taken in various
+subdivisions of the drilling operations. These observations were not
+carried on for a long enough period to give correct results, but the
+percentages of time spent on each division of the operation are believed
+to be about right. The headings of this table are self-explanatory. The
+necessary delays include all time spent in changing bits, making
+air-line connections, etc. The unnecessary delays are stoppages caused
+by lack of supplies or insufficient air pressure.
+
+By Table 6 it will be noticed that the cost of labor for drilling and
+sharpening steels was about $0.29 per lin. ft. of hole drilled. The
+total cost, including repairs, supply of air, etc., came to about $0.38,
+as will be seen from Table 8.
+
+_Timbering._--On the New York side nearly the whole length of the
+excavation needed timbering, to a greater or less extent, and for the
+most part required timbering of quite a heavy type.
+
+TABLE 6.--ROCK TUNNEL EXCAVATION UNDER 32D STREET, EAST OF CUT-AND-COVER
+SECTION. DRILLING AND BLASTING.--DETAILED COST OF LABOR IN DRILLING,
+ALSO QUANTITY AND COST OF POWDER USED.
+
+ +=====================================================================+
+ | DRILLING AND BLASTING. |
+ |-----+-----+------+------+------+-----+-----+------+-----+-----+-----|
+ |Type.|Date.|Total feet drilled. | No. drill shifts| Feet drilled |
+ | | | | | | of (10-hour.) |per man per hour.|
+ | +-----+------+------+------+-----+-----+------+-----+-----+-----+
+ | |1907 |Head- |Bench |Total |Head-|Bench|Total |Head-|Bench|Total|
+ | | | ing | | | ing | | | ing | | |
+ |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+
+ |_Ke._|May | 2,971| 5,578| 8,549| 98 | 204 | 302 |3.031|2.734|2.831|
+ | |June | 2,093| 6,194| 8,287| 85 | 223 | 308 |2.462|2.777|2.691|
+ | |July | | 7,627| 7,627| | 268 | 268 | |2.845|2.845|
+ | |Aug. | | 2,552| 2,552| | 95 | 95 | |2.688|2.688|
+ | |Sept.| | 2,133| 2,133| | 79 | 79 | |2.700|2.700|
+ | +-----+------+------+------+-----+-----+------+-----+-----+-----+
+ | |Total| 5,064|24,084|29,148| 183 | 869 |1,052 |2.767|2.77 |2.77 |
+ |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+
+ |_Ki._|May | 6,976| | 6,976| 216 | | 216 |3.229| |3.229|
+ | |June | 4,089| | 4,089| 135 | | 135 |3.029| |3.029|
+ | |July | | 3,733| 3,733| | 140 | 140 | |2.666|2.666|
+ | |Aug. | | 6,715| 6,715| | 249 | 249 | |2.769|2.769|
+ | |Estim| |14,742|14,742| | 46 | 546 | |2.700|2.700|
+ | +-----+------+------+------+-----+-----+------+-----+-----+-----+
+ | |Total|11,065|25,190|36,255| 351 | 935|1,286 |3.152|2.694|2.819|
+ |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+
+ |_Ko._|May | | 1,617| 1,617| | 55| 55 | |2.921|2.921|
+ | |June | | 2,948| 2,948| | 107| 107 | |2.755|2.755|
+ | |July | | 3,734| 3,734| | 131| 131 | |2.850|2.850|
+ | |Aug. | | 8,260| 8,260| | 290| 290 | |2.848|2.848|
+ | |Estim| | 4,787| 4,787| | 285| 285 | |1.180|1.680|
+ | +-----+------+------+------+-----+-----+------+-----+-----+-----+
+ | |Total| |21,346|21,346| | 868| 868 | |2.460|2.460|
+ |-----+-----+------+------+------+-----+-----+------+-----+-----+-----+
+ |Grand|Total|16,129|70,620|86,749| 534 |2,672|3,206 |3.020|2.710|2.710|
+ +=====+=====+======+======+======+=====+=====+======+=====+=====+=====+
+
+ +==================================================+=====================+
+ | DRILLING AND BLASTING | POWDER USED. |
+ |-----+----------+------+--------------------------+--------+-------+----+
+ | | | | Cost of labor only. | | | |
+ | | | | Drilling and sharpening. | | | |
+ | | | +------+------+-------+----+ | | |
+ | | | | | | Per | | | Cost | |
+ | | | | | | cubic | | | per | |
+ | | | | | | yard. | | | cubic | |
+ | | | | | | | | |yard at| |
+ | | | | | | | | | 11 | |
+ | | | | | | | | | cents | |
+ | | | | | | | | | per | |
+ | | | | | | | | |pound. | |
+ | +----------+------+------+------+-------+----+--------+-------+----+
+ |Type.| Quantity | |Total.| Per |Actual.|Paid| Total |Actual.|Paid|
+ | | of | | |linear| |for |Quantity| |for.|
+ | |excavation| | |feet. | | | | | |
+ | | in cubic | | | | | | | | |
+ | | yards. | | | | | | | | |
+ | +----------+------+------+------+-------+----+--------+-------+----+
+ | | Actual. | Paid | $ | $ | $ | |Pounds. | $ | $ |
+ | | [E] | for | | | | | | | |
+ | | | [F] | | | | | | | |
+ |-----+----------+------+------+------+-------+----+--------+-------+----+
+ |_Ke._| 1,736 | 1,664| 2,331| 0.27 | 1.34 |1.40| 1,595 | 0.10 |0.10|
+ | | 809 | 698| 2,440| 0.29 | 3.01 |3.49| 1,960 | 0.27 |0.31|
+ | | 1,022 | 960| 2,031| 0.26 | 1.98 |2.11| 966 | 0.10 |0.11|
+ | | 743 | 716| 640| 0.25 | 0.86 |0.89| 430 | 0.06 |0.07|
+ | | 238 | 238| 533| 0.25 | 2.24 |2.24| 280 | 0.13 |0.13|
+ | |----------+------+------+------+-------+----+--------+-------+----+
+ | | 4,548 | 4,276| 7,975| 0.27 | 1.75 |1.87| 5,231 | 0.13 |0.13|
+ |-----+----------+------+------+------+-------+----+--------+-------+----+
+ |_Ki._| 614 | 527| 1,604| 0.23 | 2.61 |3.04| 1,230 | 0.22 |0.26|
+ | | 357 | 259| 1,234| 0.30 | 3.45 |4.76| 1,036 | 0.32 |0.44|
+ | | 530 | 404| 1,084| 0.29 | 2.04 |2.68| 550 | 0.11 |0.15|
+ | | 925 | 890| 1,901| 0.28 | 2.05 |2.13| 905 | 0.10 |0.11|
+ | | 3,254 | 2,908| 4,570| 0.31 | 1.40 |1.57| 2,470 | 0.08 |0.09|
+ | |----------+------+------+------+-------+----+--------+-------+----+
+ | | 5,680 | 4,988|10,393| 0.29 | 1.83 |2.08| 6,191 | 0.12 |0.14|
+ |-----+----------+------+------+------+-------+----+--------+-------+----+
+ |_Ko._| 250 | 188| 471| 0.29 | 1.88 |2.50| 376 | 0.17 |0.22|
+ | | 496 | 347| 883| 0.29 | 1.78 |2.54| 357 | 0.08 |0.11|
+ | | 626 | 606| 1,003| 0.27 | 1.60 |1.65| 609 | 0.11 |0.11|
+ | | 718 | 709| 2,161| 0.26 | 3.00 |3.04| 918 | 0.14 |0.14|
+ | | 605 | 535| 2,397| 0.50 | 3.96 |4.48| 762 | 0.14 |0.16|
+ | |----------+------+------+------+-------+----+--------+-------+----+
+ | | 2,695 | 2,385| 6,915| 0.32 | 2.57 |2.90| 3,022 | 0.12 |0.14|
+ | |---------+-------+------+------+-------+----+--------+-------+----+
+ | |12,923 |11,649|25,283| 0.29 | 1.96 |2.17|14,444 | 0.12 |0.14|
+ +=====+==========+======+======+======+=======+====+========+=======+====+
+
+The work done during the 5 months when these analyzed cost figures were
+kept includes 280 ft. of bench and 220 ft. of heading. This excess of
+bench over heading causes the general average amounts per cubic yard to
+be too low.
+
+[E] Actual amount of excavation.
+
+[F] Amount of excavation paid for.
+
+[Illustration: 24' 6" SPAN TWIN TUNNELS DETAILS OF METHOD OF DRILLING
+AND BLASTING IN A TYPICAL (NOT EXACT AVERAGE) SECTION]
+
+ +---------+--------+--------+-----+-----+------+------+-------+
+ | Drilling and Firing Data for |
+ | Each Sub-division of Section |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | Sub | Volume | No. of | No. | No. |Total |Linear| Total |
+ |divisions|of each |sets of | of | of | lbs. | feet |length |
+ | | sub- | holes |holes|times| of | of |drilled|
+ | |division| | in |fired|powder|tunnel| |
+ | |paid for| | set | | per |broken| |
+ | | | | | | hole | | |
+ | | | | | |fired | | |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _a_ | _b_ | _c_ | _d_ | _e_ | _f_ | _g_ | _h_ |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _A_ | 17.775 | {[G] 1 | 6 | 3 | 4.50 | | |
+ | | | {[H] 1 | 9 | 1 | 1.50 | | |
+ | | | {[I] 1 | 6 | 1 | 1.00 | | |
+ | | | {[J] 1 | 6 | 1 | 0.75 | 6.0 | 195 |
+ | | | | | | | | |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _A'_ | 1.00 | 2 | 3-4 | 1 | 0.25 | 5.0 | 21 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _B_ | 5.925 | {[G] 2 | 3-4 | 1 | 1.00 | 4.0 | 35 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _C_ | | {[K] 1 | 3 | 2 | 1.125| | |
+ | | 33.33 | 4 | 7 | 1 | 1.125| 5.0 | 186 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _D_ | 6.665 | 2 | 5-6 | 1 | 0.75 | 3.0 | 33 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | | | |
+ | | | |
+ |=========+========+========+=====+=====+======+======+=======|
+ | _E_ | 50.00 | | 5 | 1 | 1.50 | 5.0 | 405 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _F_ | 88.88 |{ 10.5| 4 | 2 | 1.50 | | |
+ | | |{[L] 5.0| 4 | 1 | 1.50 | 4.0 | 682 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _G_ | 22.22 | 5.5| 4 | 2 | 1.00 | 5.0 | 132 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | | | |
+ | | | |
+ |=========+========+========+=====+=====+======+======+=======|
+ | _H_ | 9.77 |{ 5 | 3 | 1 | 0.50 | | |
+ | | |{ 4 | 6 | 1 | 0.50 | 6.0 | 156 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | _I_ | 26.66 | 8 | 5 | 1 | 1.00 | 6.0 | 252 |
+ |---------+--------+--------+-----+-----+------+------+-------|
+ | | | |
+ | | | |
+ | | |========+=====+=====+======+======+=======|
+ | | | |
+ | | | |
+ | | | |
+ | | |========+=====+=====+======+======+=======|
+ | | | |
+ +---------+--------+--------+-----+-----+------+------+-------+
+
+ +---------+------+-------+------+------+---------+-------+------+
+ | Drilling and Firing Data for |
+ | Total Sections |
+ |---------+------+-------+------+------+---------+-------+------|
+ | Sub |Total |Length | Cu. | Cu. | Total | Total | Total|
+ |divisions|length|drilled| yds. | yds. | lbs. of |lbs. of| lbs. |
+ | | of | per | per | per | powder | powder| of |
+ | |simi- |linear |linear|linear| per | per |powder|
+ | |lar |foot of| foot | foot | linear | foot | per |
+ | |head- |tunnel | of | of | foot of |drilled|cubic |
+ | |ings | |tunnel|tunnel| tunnel | | yard |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _a_ | _i_ | _j_ | _k_ | _l_ | _m_ | _n_ | _o_ |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _A_ | |Sigma | | | | | |
+ | | | c + d |b + i | j |c + d + f| m | m |
+ | | | ----- |------| --- | ----- | --- | --- |
+ | | | g | g | k | g | j | k |
+ | | 2 | 65.00 | 5.925|10.97 | 17.00 | 0.261 |2.848 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _A'_ | 2 | 8.40 | 0.400|21.00 | 0.70 | 0.166 |1.750 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _B_ | 2 | 17.50 | 2.962| 5.90 | 3.50 | 0.200 |1.181 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _C_ | | | | | | | |
+ | | 1 | 37.20 | 6.666| 5.58 | 6.975 | 0.187 |1.046 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _D_ | 2 | 22.00 | 4.444| 4.95 | 5.500 | 0.250 |1.237 |
+ |---------+------+-------+------+------+---------+-------+------|
+ |Total for| |150.10 |20.397| 7.81 | 33.675 | 0.227 |1.778 |
+ | Heading | | | | | | | |
+ |=========+======+=======+======+======+=========+=======+======|
+ | _E_ | 1 | 81.00 |10.000| 8.10 | 13.500 | 0.167 |1.350 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _F_ | | | | | | | |
+ | | 1 |170.50 |22.222| 7.67 | 23.230 | 0.136 |1.046 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _G_ | 1 | 26.40 | 4.444| 5.94 | 4.400 | 0.166 |0.990 |
+ |---------+------+-------+------+------+---------+-------+------|
+ |Total for| |277.90 |36.666| 7.56 | 41.150 | 0.150 |1.133 |
+ | Bench | | | | | | | |
+ |=========+======+=======+======+======+=========+=======+======|
+ | _H_ | | | | | | | |
+ | | 1 | 26.00 | 1.628|15.96 | 3.250 | 0.125 |1.995 |
+ |---------+------+-------+------+------+---------+-------+------|
+ | _I_ | 2 | 84.00 | 4.444|18.90 | 13.333 | 0.158 |3.000 |
+ |---------+------+-------+------+------+---------+-------+------|
+ |Total of | |110.00 | 6.072|18.10 | 16.583 | 0.151 |2.731 |
+ | Trench | | | | | | | |
+ |=========+======+=======+======+======+=========+=======+======|
+ |Total for| |548.00 |63.135| 8.95 | 91.408 | 0.172 |1.446 |
+ | Whole | | | | | | | |
+ |Section | | | | | | | |
+ |=========+======+=======+======+======+=========+=======+======|
+ |Powder taken at 0.5 lb. per stick |
+ +---------+------+-------+------+------+---------+-------+------+
+
+[G] 6 Cut Holes-8 feet (Black circle)
+
+[H] 9 First Side Rd. and Bottom-7 feet (Circle with dot in it)
+
+[I] 6 Back Round-7 feet (Circle with line in it)
+
+[J] 6 Top Back Round-7 feet (Circle with x in it)
+
+[K] A' 7 Holes-3 feet (Open circle)
+
+[L] line holes (Plus sign)
+
+TABLE 7.--Analysis of Drilling Time on Section Gy-East.
+
+ +========+======+========+=====+=====+=======+========+========+=======+
+ | | | | AVERAGE TIME TAKEN: |
+ |Position|Nature| No. of |-----+-----+-------+--------+--------+-------|
+ | in | of | Drill | | | | | | |
+ |Section.|Rock. | Shifts |Set- |Dril-|Neces- |Unneces-| Taking |Loading|
+ | | |observed|ting |ling.| sary | sary | down | and |
+ | | | for | up. | |delays.|delays. |machine.|firing.|
+ | | |average.| | | | | | |
+ |--------+------+--------+-----+-----+-------+--------+--------+-------|
+ | | | |h. m.|h. m.| h. m. | h. m. | h. m. | h. m. |
+ | | | |-----+-----+-------+--------+--------+-------|
+ |Heading |Quartz| 8 |0:38 |4:52 | 1:40 | | 0:05 | 0:04 |
+ | | | | | | | | | |
+ |Heading | Hard | 1 |0:15 |8:00 | 1:45 | | | |
+ | | mica | | | | | | | |
+ | |schist| | | | | | | |
+ | | | | | | | | | |
+ | Bench |Quartz| 23 |1:23 |5:57 | 2:23 | 0:05 | 0:05 | 0:07 |
+ | | | | | | | | | |
+ | Bench |Medium| 16 |1:10 |6:08 | 1:50 | 0:12 | 0:07 | 0:07 |
+ | | mica | | | | | | | |
+ | |schist| | | | | | | |
+ | | | | | | | | | |
+ | Center |Medium| 10 |0:58 |5:53 | 1:33 | 0:06 | 0:12 | 0:30 |
+ | trench | mica | | | | | | | |
+ | |schist| | | | | | | |
+ | | | | | | | | | |
+ | Center | Soft | 9 |1:10 |6:40 | 1:17 | 0:10 | 0:20 | 0:23 |
+ | trench | mica | | | | | | | |
+ | |schist| | | | | | | |
+ |--------+------+--------+-----+-----+-------+--------+--------+-------|
+ |General | | 67 |1:08 |5:58 | 1:53 | 0:07 | 0:09 | 0:12 |
+ |average | | | | | | | | |
+ |--------+------+--------+-----+-----+-------+--------+--------+-------|
+ | Per- | | |11.3%|59.7%| 18.9% | 1.1% | 1.5% | 2% |
+ |centage | | | | | | | | |
+ +========+======+========+=====+=====+=======+========+========+=======+
+
+ +========+======+=========+========+======+======+========+
+ | | | AVERAGE TIME TAKEN: | FEET DRILLED. |
+ |Position|Nature|---------+--------+------+------+--------|
+ | in | of | | | | | |
+ |Section.|Rock. | Total |Mucking.|Total.| Per | Per |
+ | | |drilling.| | |shift.|working |
+ | | | | | | | hour. |
+ | | | | | | | |
+ |--------+------+---------+--------+------+------+--------|
+ | | | h. m. | h. m. |h. m. | | |
+ | | |---------+--------+------+------+--------|
+ |Heading |Quartz| 7:19 | 2:41 |10:00 | 22.0 | 2.86 |
+ | | | | | | | |
+ |Heading | Hard | 10:00 | |10:00 | 42.0 | 4.20 |
+ | | mica | | | | | |
+ | |schist| | | | | |
+ | | | | | | | |
+ | Bench |Quartz| 10:00 | |10:00 | 25.9 | 2.59 |
+ | | | | | | | |
+ | Bench |Medium| 9:34 | 0:26 |10:00 | 22.22| 2.32 |
+ | | mica | | | | | |
+ | |schist| | | | | |
+ | | | | | | | |
+ | Center |Medium| 9:12 | 0:48 |10:00 | 22.0 | 2.39 |
+ | trench | mica | | | | | |
+ | |schist| | | | | |
+ | | | | | | | |
+ | Center | Soft | 10:00 | |10:00 | 26.44| 2.64 |
+ | trench | mica | | | | | |
+ | |schist| | | | | |
+ |--------+------+---------+--------+------+------+--------|
+ |General | | 9:27 | 0:33 |10:00 | 24.1 | 2.54 |
+ |average | | | | | | |
+ |--------+------+---------+--------+------+------+--------|
+ | Per- | | 94.5% | 5.5% | 100% | | |
+ |centage | | | | | | |
+ +========+======+=========+========+======+======+========+
+
+TABLE 8.--ANALYZED COST OF DRILLING.
+
+ +=============+===========================+===========================+
+ | | COST PER FOOT OF HOLE | COST PER DRILL SHIFT |
+ |Item of Cost.| DRILLED. | |
+ | +-------+-----+-----+-------+-----+------+------+-------+
+ | | 15 ft | 9 ft|24 ft|Average|15 ft|19 ft |24 ft |Average|
+ | | 4 in | 6 in| 6 in| | 4 in| 6 in | 6 in | |
+ |-------------+-------+-----+-----+-------+-----+------+------+-------+
+ |Drilling | $0.25 |$0.28|$0.31| $0.28 |$6.95| $7.75| $7.60| $7.45 |
+ |labor | | | | | | | | |
+ | | | | | | | | | |
+ |Sharpening | 0.02 | 0.02| 0.01| 0.016| 0.58| 0.42| 0.34| 0.43 |
+ | | | | | | | | | |
+ |Drill steel | 0.007|0.007|0.006| 0.007| 0.19| 0.20| 0.15| 0.19 |
+ |(5 in. per | | | | | | | | |
+ |drill shift) | | | | | | | | |
+ | | | | | | | | | |
+ |Drill repairs| 0.02 | 0.02| 0.02| 0.02 | 0.61| 0.59| 0.42| 0.54 |
+ | | | | | | | | | |
+ |High-pressure|[M]0.05| 0.04| 0.07| 0.07 | 1.39| 1.86| 1.67| 1.82 |
+ |air | | | | | | | | |
+ |-------------+-------+-----+-----+-------+-----+------+------+-------+
+ |Totals | $0.35 |$0.38|$0.41| $0.385|$9.67|$10.82|$10.18|$10.43 |
+ +=============+=======+=====+=====+=======+=====+======+======+=======+
+
+[M] This is an estimated figure, ascertained by taking a proportion of
+the whole charge for plant running.
+
+_General Methods._--Whenever any considerable support was needed for the
+ground, segmental timbering was used. In most cases, this was supported
+by wall-plates at the springing line, and was set with an allowance for
+settlement, so that it would be clear of the work when the masonry
+lining was put in. As the twin-tunnel section involved the excavation of
+the North and South Tunnels at the same time, the cross-section of the
+upper part of the excavation consisted of two quadrants rising from the
+springing line and connected at the top by a horizontal piece from 19 to
+28 ft. in length. This made a rather flat arch to support by timbering.
+
+The timber for the segmental work was 12 by 12-in. yellow pine. In light
+ground the bents were spaced at 5-ft. centers, in heavy ground 2-ft.
+6-in. centers.
+
+When the soft ground in the roof was struck, posts had to be used in the
+heading to support the caps. When the bench was removed, the posts were
+replaced by others down to the bottom of the excavation. These long
+posts were a great hindrance to all the work, and each replacement of
+short posts by long ones meant a settlement of the caps; consequently,
+it was decided to use in the section east of the cut-and-cover, where
+all the ground was heavy, a temporary inner bent of segmental timber,
+within and reinforcing the permanent bent, and resting on separate
+wall-plates. This is shown by Fig. 6. These temporary bents were inside
+the work, and were removed as the arch was built. However, the caps
+settled considerably in some cases, so that it was not possible to do
+away with posting entirely.
+
+In heavy ground the caps were set about 1 ft. above the neat line of the
+crown of the brick arch, in some cases they were set only 6 in. above,
+but the settlement was often more than this, causing great trouble in
+cutting out the encroaching timber when the arch had to be built.
+
+[Illustration: DETAILS OF LONGITUDINAL SECTIONAL SHOWING METHOD OF
+PLACING LAGGING IN CROWN WITH SOFT ROOF TYPICAL SECTION LOOKING EAST
+FIG. 6.]
+
+
+In the tunnels east of the cut-and-cover portion, wall-plate headings
+were driven (shown by areas marked _A_ on Fig. 5), and, when a length of
+wall-plate had been set, the full-width heading was advanced a foot or
+two at a time, the timber segmental bents being set up as soon as
+possible; lagging was then driven over the cap into the soft ground.
+Fig. 6 shows the double set of segmental bents adopted in the 15-ft.
+4-in. twin tunnels east of the cut-and-cover section.
+
+When the soft ground came down so low as to interfere with the
+excavation of the wall-plate headings, a small heading was driven into
+the soft ground on the line of the ends of the caps, and lagging was
+driven down from this to the wall-plate heading, as illustrated in Fig.
+4.
+
+In the 19-ft. 6-in. tunnels the wall-plate for the inner bent was
+supported by a side-bench, termed the "Raker" bench. This was left in
+position until the rest of the bench and the middle subgrade conduit
+trench had been excavated; it was then possible to support the caps by
+two rows of posts from subgrade level, take out the inner bents, and
+excavate the raker bench.
+
+The 24-ft. 6-in. twin tunnels, which are at the extreme eastern end of
+this section, adjoining the open-cut work of the Terminal Station, and
+under Tenth Avenue, were driven from the Terminal Station-West, and the
+timbering had to be made very secure on account of the pipes and sewers
+in the street above. Detailed records were kept of the amount of timber
+used and the cost of labor and material expended in timbering. These
+records cover the same portion of tunnel as that for which the detailed
+records of drilling costs, previously referred to, were kept. These
+records are shown in Tables 9 and 10. It will be noted that the timber
+used in blocking, that is, filling up voids outside the main timbering,
+amounted to more than two-thirds of the total timber, and that the cost
+of labor in erecting the timbering exceeds the prime cost of the timber
+by about one-third. The following distinction is made between permanent
+and temporary timbering: The permanent timbering is that which is
+concreted in when the masonry is built; the temporary consists of the
+lower bents and posts, which have to be removed when the masonry is
+built.
+
+_Force Employed in Excavation._--A typical day's working force for
+drilling, blasting, mucking, and timbering is shown in Table 11.
+
+Where there was any large quantity of soft ground in the roof, the
+timber gang was much larger than shown in Table 11, and was helped by
+the mucking gang. The drillers did most of the mucking out of the
+heading before setting up the drills.
+
+_Excavation of Weehawken Rock Tunnels._--This subject may be dismissed
+in a few words, as very few features of interest were called into play.
+The rock was of good quality, being the sandstone typical of this part
+of the country. Little or no timbering was needed, there were no
+buildings above the tunnel to be taken care of, and large charges of
+powder could be used.
+
+TABLE 9.--SUPPLEMENTARY ANALYSIS OF TIMBERING, ROCK TUNNEL EXCAVATION
+UNDER 32D STREET, EAST OF CUT-AND-COVER SECTION. ANALYZED COST OF
+TIMBERING, PER FOOT RUN AND PER BENT.
+
+ +=============================+================================
+ | | _Ke_
+ | |--------+------------+----------
+ | |Per foot|Per bent, |Per cubic
+ | |run of |3 ft, 6 in.,|yard
+ | |tunnel |center to |excavation
+ | | |center |
+ |-----------------------------+--------+------------+----------
+ |PERMANENT TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Upper Bent. | 274 | 685 | 7.8
+ | Blocking. | 294 | 735 | 8.3
+ | Total. | 568 | 1,420 | 16.1
+ |Cost, in dollars. | | |
+ | Lumber. | 23.75| 59.38 | 0.67
+ | Labor. | 37.50| 93.75 | 1.06
+ | Total. | 61.25| 153.13 | 1.73
+ | | | |
+ |TEMPORARY TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Lower Bent. | 479 | 11.97 | 13.6
+ | Blocking. | 193 | 483 | 5.5
+ | Total. | 672 | 16.80 | 19.1
+ |Cost, in dollars. | | |
+ | Lumber. | 29.13| 72.81 | 0.82
+ | Erection labor. | 28.85| 72.13 | 0.82
+ | Removal labor. | 8.29| 20.73 | 0.23
+ | Total labor. | 37.14| 92.86 | 1.05
+ | Total. | 66.27| 165.67 | 1.87
+ | | | |
+ |GRAND TOTAL. | | |
+ |Lumber in feet, B. M. |1,240 | 3,100 | 35.2
+ |Cost, in dollars. | | |
+ | Lumber. | 52.88| 132.19 | 1.49
+ | Labor. | 74.64| 186.61 | 3.60
+ | Total. | 127.52| 318.80 |
+ |-----------------------------+--------+------------+----------
+ | | _Ki_
+ | |--------+------------+----------
+ | |Per foot|Per bent, |Per cubic
+ | |run of |3 ft, 6 in.,|yard
+ | |tunnel |center to |excavation
+ | | |center |
+ |-----------------------------+--------+------------+----------
+ |PERMANENT TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Upper Bent. | 227 | 830 | 5.3
+ | Blocking. | 164 | 601 | 3.8
+ | Total. | 391 | 1,431 | 9.1
+ |Cost, in dollars. | | |
+ | Lumber. | 16.84| 61.56 | 0.39
+ | Labor. | 12.82| 46.88 | 0.30
+ | Total. | 29.66| 108.44 | 0.69
+ | | | |
+ |TEMPORARY TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Lower Bent. | 186.33| 681.25 | 4.33
+ | Blocking. | 42.80 156.50 | 0.99
+ | Total. | 229.13| 837.75 | 5.32
+ |Cost, in dollars. | | |
+ | Lumber. | 9.65| 35.31 | 0.22
+ | Erection labor. | 10.38| 37.97 | 0.24
+ | Removal labor. | 9.74| 34.09 | 0.23
+ | Total labor. | 20.12| 72.06 | 0.47
+ | Total. | 29.77| 107.37 | 0.69
+ | | | |
+ |GRAND TOTAL. | | |
+ |Lumber in feet, B. M. | 6.20| 22.69 | 14.4
+ |Cost, in dollars. | | |
+ | Lumber. | 26.49| 96.87 | 0.61
+ | Labor. | 32.94| 118.94 | 0.77
+ | Total. | 59.43| 215.81 | 1.38
+ |-----------------------------+--------+-----------------------
+ | | _Ko_
+ | |--------+------------+----------
+ | |Per foot|Per bent, |Per cubic
+ | |run of |3 ft, 6 in.,|yard
+ | |tunnel |center to |excavation
+ | | |center |
+ |-----------------------------+--------+------------+----------
+ |PERMANENT TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Upper Bent. | 261 | 962 | 4.1
+ | Blocking. | 408 | 1,508 | 6.5
+ | Total. | 669 | 24.70 | 10.5
+ |Cost, in dollars. | | |
+ | Lumber. | 28.00| 103.38 | 0.44
+ | Labor. | 29.79| 110.00 | 0.47
+ | Total. | 57.79| 213.38 | 0.91
+ | | | |
+ |TEMPORARY TIMBERING. | | |
+ |Lumber in feet, B. M. | | |
+ | Lower Bent. | 350 | 1,291 | 5.5
+ | Blocking. | 61 | 227 | 1.0
+ | Total. | 411 | 1,518 | 6.5
+ |Cost, in dollars. | | |
+ | Lumber. | 18.45| 68.16 | 0.29
+ | Erection labor. | 20.83| 76.92 | 0.33
+ | Removal labor. | 12.16| 44.59 | 0.19
+ | Total labor. | 32.99| 121.51 | 0.52
+ | Total. | 51.44| 189.67 | 0.81
+ | | | |
+ |GRAND TOTAL. | | |
+ |Lumber in feet, B. M. |1,080 | 3,988 | 17.1
+ |Cost, in dollars. | | |
+ | Lumber. | 46.45| 171.54 | 0.73
+ | Labor. | 62.78| 231.50 | 0.99
+ | Total. | 109.23| 403.04 | 1.72
+ +=============================+========+============+=========
+
+TABLE 10.--TIMBERING:--DETAILED COST OF TIMBER, LABOR, AND
+SUPERINTENDENCE. ROCK TUNNEL EXCAVATION UNDER 32D STREET, EAST OF
+CUT-AND-COVER SECTION.
+
+ +====+=======+======================================+====================+
+ | | | | EXCAVATION | |
+ | | | TIMBER USED, IN | IN CUBIC | COST OF |
+ | | | FEET, B. M. | YARDS | TIMBER |
+ | | |------------------------+-------------+--------------------+
+ | | | Main |Blocking| Total | | Paid | | | |
+ | |Date |timber.|timber. |timber.|Actual| for. | Main |Block.|Total.|
+ | |-------+-------+--------+-------+------+------+------+------+------+
+ | |1907 | _a_ | _b_ | _c_ | _d_ | _e_ | _f_ | _g_ | _h_ |
+ | |-------+-------+--------+-------+------+------+------+------+------+
+ |_Ke_|May | 18,016| 15,234 | 33,250| 1,736| 1,664| $810| $565|$1,375|
+ | |June | 14,048| 11,528 | 25,576| 809| 698| 680| 457| 1,087|
+ | |July | 20,092| 7,339 | 27,431| 1,022| 960| 900| 300| 1,200|
+ | |August | 6,485| 2,632 | 9,117| 743| 716| 290| 110| 400|
+ | |Sept. | 1,632| 2,224 | 3,856| 238| 238| 73| 94| 167|
+ | |Removal| | | | | | | | |
+ | |-------+-------+--------+-------+------+------+------+------+------+
+ | |Total | 60,273| 38,957 | 99,230| 4,548| 4,276|$2,703|$1,526|$4,229|
+ |----+-------+-------+--------+-------+------+------+------+------+------+
+ |_Ki_|May | | 3,537 | 3,537| 614| 527| | $150| $150|
+ | |June | 300| | 300| 357| 259| $14| | 14|
+ | |July | 7,776| 5,811 | 13,587| 530| 404| 350| 233| 583|
+ | |August | 19,712| 5,702 | 25,414| 925| 890| 887| 220| 1,107|
+ | |Sept. | 20,556| 9,218 | 29,774| 1,585| 1,501| 925| 325| 1,250|
+ | |Removal| | | | 1,669| 1,407| | | |
+ | |-------+-------+--------+-------+------+------+------+------+------+
+ | |Total | 48,344| 24,268 | 72,612| 5,680| 4,988|$2,176| $928|$3,104|
+ |----+-------+-------+--------+-------+------+------+------+------+------+
+ |_Ko_|May | 4,332| 8,788 | 13,120| 250| 188| $175| $366| $561|
+ | |June | 7,132| 10,017 | 17,149| 496| 347| 324| 396| 720|
+ | |July | 3,070| 200 | 3,270| 626| 606| 134| 10| 144|
+ | |August | 10,704| 2,102 | 12,806| 718| 709| 481| 80| 561|
+ | |Sept. | 2,400| 245 | 2,645| 396| 324| 108| 8| 116|
+ | |Removal| | | | 209| 211| | | |
+ |----|-------+-------+--------+-------+------+------+------+------+------+
+ | |Total | 27,638| 21,352 |48,990 | 2,695| 2,385|$1,242| $860|$2,102|
+ |----|-------+-------+--------+-------+------+------+------+------+------+
+ | |Grand |136,255| 84,577 |220,832|12,923|11,649|$6,121|$3,314|$9,435|
+ | |total | | | | | | | | |
+ +====+=======+=======+========+=======+======+======+======+======+======+
+
+ +====+=======+=======+=======+=======+=======+======+=======+=====+=====|
+ | | | | | COST PER | COST PER |
+ | | | | | CUBIC YARD | CUBIC YARD |
+ | | |COST OF| TOTAL | (ACTUAL). | (PAID FOR). |
+ | | | Labor | Cost. |-------+-------+------+-------+-----+-----+
+ | |DATE | | |Timber.|Labor. |Total.|Timber.|Labor|Total|
+ | |-------+-------+-------+-------+-------+------+-------+-----+-----+
+ | | | | | _h_ | _i_ | _j_ | _h_ | _i_ | _j_ |
+ | | | | | --- | --- | --- | --- | --- | --- |
+ | |1907 | _i_ | _j_ | _d_ | _d_ | _d_ | _e_ | _e_ | _e_ |
+ |----+-------+-------+-------+-------+-------+------+-------+-----+-----+
+ |_Ke_|May | $1,792| $3,167| $0.79 | $1.03 | $1.82| $0.82 |$1.07|$1.90|
+ | |June | 1,576| 2,663| 1.34 | 1.95 | 3.29| 1.55 | 2.25| 3.81|
+ | |July | 1,580| 2,780| 1.16 | 1.55 | 2.72| 1.25 | 1.64| 2.89|
+ | |August | 300| 700| 0.53 | 0.40 | 0.94| 0.57 | 0.41| 0.98|
+ | |Sept. | 60| 227| 0.70 | 0.25 | 0.95| 0.70 | 0.25| 0.95|
+ | |Removal| 663| 663| | | | | | |
+ | |-------+-------+-------+-------+-------+------+-------+-----+-----+
+ | |Total | $5,971|$10,200| $0.91 | $1.51 | $2.22| $1.00 |$1.40|$2.40|
+ |----+-------+-------+-------+-------+-------+------+-------+-----+-----+
+ |_Ki_|May | $100| $250| $0.24 | $0.16 | $0.40| $0.28 |$0.19|$0.47|
+ | |June | 44| 58| 0.04 | 0.12 | 0.16| 0.05 | 0.17| 0.22|
+ | |July | 525| 7,108| 1.10 | 0.99 | 2.09| 1.44 | 1.30| 2.74|
+ | |August | 1,018| 2,125| 1.20 | 1.10 | 2.30| 1.24 | 1.14| 2.38|
+ | |Sept. | 1,028| 2,278| 0.79 | 0.65 | 1.44| 0.83 | 0.68| 1.51|
+ | |Removal| 1,139| 1,139| | 0.68 | 0.68| | 0.81| 0.81|
+ | |-------+-------+-------+-------+-------+------+-------+-----+-----+
+ | |Total | $3,854| $6,958| $0.55 | $0.68 | $1.23| $0.63 |$0.77|$1.40|
+ |----+-------+-------+-------+-------+-------+------+-------+-----+-----+
+ |_Ko_|May | $303| $864| $2.24 | $1.21 | $3.45| $3.00 |$1.61|$4.61|
+ | |June | 562| 1,282| 1.45 | 1.18 | 2.58| 2.07 | 1.61| 3.68|
+ | |July | 156| 300| 0.23 | 0.25 | 0.48| 0.23 | 0.26| 0.49|
+ | |August | 727| 1,288| 0.78 | 1.01 | 1.79| 0.80 | 1.02| 1.82|
+ | |Sept. | 400| 516| 0.29 | 1.01 | 1.30| 0.36 | 1.23| 1.59|
+ | |Removal| 535| 535| | 2.56 | 2.56| | 2.54| 2.54|
+ | |-------+-------+-------+-------+-------+------+-------+-----+-----+
+ | |Total | $2,683| $4,785| $0.78 | $1.00 | $1.78| $0.88 |$1.12|$2.00|
+ |----+-------+-------+-------+-------+-------+------+-------+-----+-----+
+ | |Grand |$12,508|$21,943| $0.73 | $0.97 | $1.70| $0.81 |$1.07|$1.88|
+ | |total | | | | | | | | |
+ +====+=======+=======+=======+=======+=======+======+=======+=====+=====+
+
+ +====+===========+======================+
+ | | | COST, PER 1,000 |
+ | | | FT., B. M., OF |
+ | | | TOTAL TIMBER. |
+ | | |-------+------+-------|
+ | | | Total | | |
+ | | Date |timber.|Labor.|Total. |
+ | |-----------+-------+------+-------|
+ | | | _h_ | _i_ | _j_ |
+ | | | --- | --- | --- |
+ | | 1907 | _c_ | _c_ | _c_ |
+ |----+-----------+-------+------+-------|
+ |_Ke_|May |$41.35 |$53.89| $95.24|
+ | |June | 42.50 | 61.62| 104.12|
+ | |July | 43.74 | 57.60| 101.34|
+ | |August | 43.87 | 32.90| 76.77|
+ | |Sept. | 43.31 | 15.56| 58.87|
+ | |Removal | | | |
+ | |-----------+-------+------+-------|
+ | |Total |$42.62 |$60.19|$102.81|
+ |----+-----------+-------+------+-------|
+ |_Ki_|May |$42.41 |$28.27| $70.68|
+ | |June | 46.66 |146.33| 193.33|
+ | |July | 42.91 | 38.64| 81.54|
+ | |August | 43.56 | 40.06| 83.61|
+ | |Sept. | 41.98 | 34.53| 76.51|
+ | |Removal | | | |
+ | |-----------+-------+------+-------|
+ | |Total |$42.75 |$53.09| $95.84|
+ |----+-----------+-------+------+-------|
+ |_Ko_|May |$42.76 |$23.10| $65.86|
+ | |June | 41.98 | 32.77| 74.75|
+ | |July | 44.04 | 47.70| 91.74|
+ | |August | 43.80 | 56.77| 100.57|
+ | |Sept. | 43.85 |151.23| 195.08|
+ | |Removal | | | |
+ | |-----------+-------+------+-------|
+ | |Total |$42.91 |$54.75| $97.65|
+ |----+-----------+-------+------+-------|
+ | |Grand total|$42.73 |$56.65| $99.38|
+ +====+===========+=======+======+=======+
+
+Work was begun on September 1st, 1904, immediately on the completion of
+the work on the shaft. The North and South Tunnels in this case are
+completely independent, as will be seen from Plate XXXIV. The procedure
+adopted was to drive a top heading on the center line of each tunnel and
+to break down the bench from this. The drilling was at first supplied
+with steam power from a temporary plant, as the contractor was at that
+time installing his permanent plant, which was finished at the end of
+November, 1904. At this time the rate of advance averaged 3½ lin. ft.
+of full section per day of 24 hours. By the end of January the Weehawken
+rock tunnels were completely excavated, and by the middle of April,
+1905, the excavation for the shield chambers was finished; the erection
+of the shields was started at the end of that month.
+
+TABLE 11.
+
+ ==================+=========+========+=============+========+==========
+ Grade. |Total No.|Rate per|Drilling and |Mucking:|Timbering:
+ | | day. |blasting: No.| No. | No.
+ ------------------+---------+--------+-------------+--------+----------
+ Superintendent | 1 | $7.70 | ½ | 1/8 | 3/8
+ Assistant engineer| 1 | 5.80 | ½ | 1/8 | 3/8
+ Electrician | 1 | 3.50 | ½ | 1/8 | 3/8
+ Engineer | 1 | 3.50 | | 1 |
+ Signalman | 1 | 2.00 | | 1 |
+ Foreman | 3 | 4.00 | 1 | 1 | 1
+ Driller | 5 | 3.00 | 5 | |
+ Driller's helper | 5 | 2.00 | 5 | |
+ Laborers | 14 | 2.00 | | 14 |
+ Timbermen | 3 | 3.00 | | | 3
+ " helpers | 4 | 2.00 | | | 4
+ Machinist | 1 | 4.00 | 1 | |
+ Blacksmith | 2 | 3.50 | 2 | |
+ " helper | 2 | 2.00 | 2 | |
+ Nipper | 2 | 2.00 | 2 | |
+ Waterboy | 1 | 2.00 | 1 | |
+ ------------------+---------+--------+-------------+--------+---------
+ Total | 47 | | 20½ | 17-3/8 | 9-1/8
+ ==================+=========+========+=============+========+=========
+
+The general scheme of excavation is shown by Plate XXXIII. The bench was
+kept 50 or 60 ft. behind the face of the heading. The powder used was
+60% Forcite. The general system of drilling was as shown in Fig. 7. The
+average length of hole drilled per cubic yard of excavation was 2.9 ft.,
+as against 7.70 ft. at Manhattan; and the amount of powder used was 1.96
+lb. per cu. yd., as against 1.24 lb. at Manhattan. There was little
+timbering. A length of about 30 or 40 ft. adjoining the Weehawken shaft
+was timbered, and also a shattered seam of about 17 ft. in width between
+Stations 262 + 10 and 262 + 27.
+
+[Illustration: LAND TUNNELS TYPICAL METHOD OF DRILLING USED IN THE
+WEEHAWKEN TUNNELS FIG. 7]
+
+The two entirely separate tunnels gave a cross-section which was much
+more easily timbered than the wide flat span at Manhattan, and the
+segmental timbering was amply strong without posts or other
+reinforcement.
+
+Table 12 is a summary of the cost of excavating the Land Tunnels, based
+on actual records carefully kept throughout the work.
+
+TABLE 12.--COST OF EXCAVATION OF LAND TUNNELS, IN DOLLARS PER CUBIC
+YARD.
+
+ ======================================+=========+=========+=============
+ | | |Total yardage
+ | | | and
+ |Manhattan|Weehawken|average cost.
+ --------------------------------------+---------+---------+-------------
+ Cubic yards excavated |43,289 | 8,311 | 51,600
+ _Labor._ | | |
+ Surface transport | $0.49| $0.87| $0.55
+ Drilling and blasting | 2.37| 1.55| 2.24
+ Mucking | 2.49| 2.08| 2.42
+ Timbering | 0.87| 0.18| 0.76
+ --------------------------------------+---------+---------+-------------
+ Total labor | $6.22| $4.68| $5.97
+ --------------------------------------+---------+---------+-------------
+ _Material._ | | |
+ Drilling | $0.15| $0.15| $0.15
+ Blasting | 0.21| 0.21| 0.21
+ Timber | 0.39| 0.20| 0.36
+ --------------------------------------+---------+---------+-------------
+ Total material | $0.75| $0.56| $0.72
+ --------------------------------------+---------+---------+-------------
+ Plant running | $0.76| $0.65| $0.74
+ Surface labor, repairs and maintenance| 0.15| 0.08| 0.14
+ Field office administration | 1.05| 1.18| 1.07
+ --------------------------------------+---------+---------+-------------
+ Total field charges | $8.96| $7.15| $8.64
+ --------------------------------------+---------+---------+-------------
+ Chief office administration | $0.34| $0.38| $0.34
+ Plant depreciation | 0.66| 1.01| 0.72
+ Street and building repairs | 0.27| | 0.23
+ --------------------------------------+---------+---------+-------------
+ Total average cost per cubic yard | $10.23| $8.54| $9.93
+ ======================================+=========+=========+=============
+
+Masonry Lining of Land Tunnels.
+
+Plates XXXII and XXXIV show in detail the tunnels as they were actually
+built. It will be seen that in all work, except in the Gy-East contract,
+there was a bench at each side of each tunnel in which the cable
+conduits were embedded. In Gy-East the bank of ducts which came next to
+the middle wall was carried below subgrade, and the inner benches were
+omitted.
+
+The side-walls and subgrade electric conduits were water-proofed with
+felt and pitch. The water-proofing was placed on the outside of the
+side-walls (that is, on the neat line), and the space between the rock
+and the water-proofing was filled with concrete. This concrete was
+called the "Sand-Wall."
+
+The general sequence of building the masonry lining is shown in Fig. 8.
+The operations were as follows:
+
+ 1.--Laying concrete for the whole height of the
+ sand-walls, and for the floor and foundations for
+ walls and benches up to the level of the base of
+ the conduits;
+
+ 2.--Water-proofing the side-walls, and, where there was
+ a middle trench containing subgrade conduits,
+ laying and water-proofing these conduits;
+
+ 3.--Building concrete wall for conduits to be laid
+ against, and, where there was a middle trench,
+ filling up with concrete between the conduits;
+
+ 4.--Laying conduits;
+
+ 5.--Laying concrete for benches and middle-wall;
+
+ 6.--Building haunches from top of bench to springing of
+ brick arch;
+
+ 7.--Building brick arch and part of concrete
+ back-filling;
+
+ 8.--Finishing back-filling.
+
+The whole work will be generally described under the headings of
+Concrete, Brickwork, Water-proofing, and Electric Conduits.
+
+_Concrete._--The number of types and the obstructions caused by the
+heavy posting of the timbering made it inadvisable to use built-up
+traveling forms at the Manhattan side, though they were used in the
+Weehawken Rock Tunnels.
+
+The specifications required a facing mixture of mortar to be deposited
+against the forms simultaneously with the placing of the concrete. This
+facing mixture was dry, about 2 in. thick, and was kept separate from
+the concrete during the placing by a steel diaphragm. The diaphragm was
+removed when the concrete reached the top of each successive layer, and
+the facing mixture and concrete were then tamped down together. This
+method was at first followed and gave good results, which was indeed a
+foregone conclusion, as the Weehawken shaft had been built in this way.
+However, it was found that as good results, in the way of smooth finish,
+were to be obtained without the facing mixture by spading the concrete
+back from the forms, so that the stone was forced back and the finer
+portion of the mixture came against the forms; this method was followed
+for the rest of the work. All corners were rounded off on a 1-in. radius
+by mouldings tacked to the forms. The side-bench forms were used about
+four times, and were carefully scraped, planed, filled at open joints,
+and oiled with soap grease each time they were set up. When too rough
+for face work they were used for sand-wall and other rough work.
+
+The mixing was done by a No. 4 Ransome mixer, driven by 30-h.p. electric
+motors. The mixer at Manhattan was set on an elevated platform at the
+north end of the intercepting arch; that at Weehawken was placed at the
+entrance to the tunnels. The sand and stone were stored in bins above
+the mixers, and were led to the hoppers of the mixers through chutes.
+The hoppers were divided into two sections, which gave the correct
+quantities of sand and stone, respectively, for one batch. The water was
+measured in a small tank alongside. A "four-bag" batch was the amount
+mixed at one time, that is, it consisted of 4 bags of cement, 8¾ cu.
+ft. of sand, and 17½ cu. ft. of broken stone, and was called a 1 :
+2½ : 5 mixture. It measured when mixed about ¾ cu. yd.
+
+The cement was furnished to the contractor by the Railroad Company,
+which undertook all the purchasing from the manufacturer, as well as the
+sampling, testing, and storing until the contractor needed it. The
+Railroad Company charged the contractor $2 a barrel for this material.
+
+The sand was required by the specifications to be coarse, sharp, and
+silicious, and to contain not more than 0.5% of mica, loam, dirt, or
+clay. All sand was carefully tested before being used. The stone was to
+be a sound trap or limestone, passing a 1½-in. mesh and being
+retained on 3/8-in. mesh. The contractor was allowed to use a coarser
+stone than this, namely, one that had passed a 2-in. and was retained on
+a 1½-in. mesh.
+
+The concrete was to be machine-mixed, except in cases of local
+necessity. The quantity of water used in the mixture was to be such that
+the concrete would quake on being deposited, but the engineer was to use
+his discretion on this point. Concrete was to be deposited in such a
+manner that the aggregates would not separate. It was to be laid in
+layers, not exceeding 9 in. in thickness, and thoroughly rammed. When
+placing was suspended, a joint was to be formed in a manner satisfactory
+to the engineer. Before depositing fresh concrete, the entire surface on
+which it was to be laid was to be cleaned, washed and brushed, and
+slushed over with neat cement grout. Concrete which had begun to set was
+not to be used, and retempering was not to be allowed.
+
+[Illustration: MANHATTAN TYPES FIG. 8.]
+
+The forms were to be substantial and hold their shape until the concrete
+had set. The face forms were to be of matched and dressed planking,
+finished to true lines and surfaces; adequate measures were to be taken
+to prevent concrete from adhering to the forms. Warped or distorted
+forms were to be replaced. Plastering the face was not allowed. Rock
+surfaces were to be thoroughly washed and cleaned before the concrete
+was deposited.
+
+These specifications were followed quite closely.
+
+A typical working gang, as divided among the various operations, is
+shown below:
+
+ _Superintendence._
+ ½ Superintendent @ $250 per month
+ ½ Assistant engineer " 150 " "
+ 1 Assistant superintendent " 150 " "
+ _Surface Transport._
+ 1 Foreman @ $2.50 per day
+ 1 Engineer " 3.00 " "
+ 1 Signalman " 2.00 " "
+ 16 Laborers " 1.75 " "
+ 3 Teams " 7.50 " "
+ _Laying._
+ 1 Foreman @ $4.00 per day
+ 8 Laborers " 2.00 " "
+ _Forms._
+ 1 Foreman @ $4.50 per day
+ 4 Carpenters " 3.25 " "
+ 5 Helpers " 2.25 " "
+ _Tunnel Transport._
+ ¼ Foreman @ $3.25 per day
+ ¼ Engineer " 3.00 " "
+ ¼ Signalman " 2.00 " "
+ 4 Laborers " 1.75 " "
+ _Mixers._
+ ¼ Foreman @ $3.25 per day
+ 2 Laborers " 1.75 " "
+
+The superintendent and assistant engineer looked after the brickwork and
+other work as well as the concrete. The surface transport gang handled
+all the materials on the surface, including the fetching of the cement
+from the cement warehouses.
+
+The tunnel transport gang handled all materials in the tunnel, but, when
+the haul became too long, the gang was reinforced with laborers from the
+laying gang. Of the laying gang, two generally did the spading, two the
+spreading and tamping, and the remaining force dumped the concrete. The
+general cost of this part of the work is shown in Table 13.
+
+The figures in Table 13 include the various items built into the
+concrete and some that are certificate extras in connection with the
+concrete, such as drains, ironwork and iron materials, rods and bars,
+expanded metal, doors, frames and fittings, etc.
+
+_Water-proofing._--According to the specifications, the water-proofing
+was to consist of seven layers of pitch and six layers of felt on the
+side-walls and a ½-in. layer of mastic, composed of coal-tar and
+Portland cement, to be plastered over the outside of the arches.
+
+By the time the work was in hand, some distrust had arisen as to the
+efficiency of this mastic coating, and a great deal of study was devoted
+to the problem of how to apply a felt and pitch water-proofing to the
+arches. The difficulty was that there was no room between the rock and
+the arch or between the timber and the arch (as the case might be) in
+which to work. Several ingenious schemes of putting the felt on in
+layers, or in small pieces like shingles, were proposed and discussed,
+and a full-sized model of the tunnel arch was even built on which to try
+experiments, but it was finally decided to overcome the difficulty by
+leaving out the arch water-proofing altogether, and simply building in
+pipes for grouting through under pressure, in case it was found that the
+arch was wet.
+
+As to the arch built through the length excavated by cut-and-cover on
+the New York side, it was resolved to water-proof that with felt and
+pitch exactly as the side-walls were done, the spandrel filling between
+the arches being raised in a slight ridge along the concrete line
+between tunnels in order to throw the water over to the sides. The
+portions of arch not water-proofed were rather wet, and grouting with a
+1:1 mixture was done, but only with the effect of stopping large local
+leaks and distributing a general dampness over the whole surface of the
+arch.
+
+TABLE 13.--COST OF CONCRETE IN LAND TUNNELS, IN DOLLARS PER CUBIC YARD.
+
+ =======================================+==========+==========+==========
+ | | | Total
+ |Manhattan.|Weehawken.| yardage.
+ ---------------------------------------+----------+----------+----------
+ Cubic yards placed |14,706½ | 3,723 |18,429½
+ ---------------------------------------+----------+----------+----------
+ LABOR. | Average Cost per Cubic Yard.
+ ---------------------------------------+----------+----------+----------
+ Surface transport | $0.31 | $1.43 | $0.54
+ Superintendence and general labor at | | |
+ point of work | 0.31 | 1.31 | 0.51
+ Mixing | 0.52 | 0.56 | 0.53
+ Laying | 1.38 | 1.45 | 1.39
+ Tunnel transport | 1.30 | 1.47 | 1.34
+ Cleaning | 0.21 | | 0.17
+ Forms: erecting and removal | 1.58 | 1.51 | 1.56
+ ---------------------------------------+----------+----------+----------
+ Total labor | $5.61 | $7.73 | $6.04
+ ---------------------------------------+----------+----------+----------
+ MATERIAL.
+ ---------------------------------------+----------+----------+----------
+ Cement | $2.30 | $2.22 | $2.28
+ Sand | 0.34 | 0.40 | 0.36
+ Stone | 0.91 | 0.61 | 0.85
+ Lumber for forms | 0.47 | 0.45 | 0.47
+ Sundry tunnel supplies | 0.16 | 0.17 | 0.16
+ ---------------------------------------+----------+----------+----------
+ Total materials | $4.18 | $3.85 | $4.12
+ ---------------------------------------+----------+----------+----------
+ Plant running | $0.44 | $0.44 | $0.44
+ Surface labor, repairs and maintenance | 0.25 | 1.24 | 0.44
+ Field office administration | 0.50 | 1.72 | 0.75
+ ---------------------------------------+----------+----------+----------
+ Total field charges | $10.98 | $14.98 | $11.79
+ ---------------------------------------+----------+----------+----------
+ Plant depreciation | $0.62 | $1.57 | $0.81
+ Chief office administration | 0.24 | 0.31 | 0.25
+ ---------------------------------------+----------+----------+----------
+ Total average cost per cubic yard | $11.84 | $16.86 | $12.85
+ ---------------------------------------+----------+----------+----------
+ Cost of Miscellaneous Items in Concrete.
+ ---------------------------------------+----------+----------+----------
+ |Manhattan.|Weehawken.| Average.
+ Cubic yards |14,706½ | 3,723 |18,429½
+ Amount, in dollars |$6,184.83 | $1,756.79|$7,941.62
+ Unit cost | 0.42 | 0.47| 0.43
+ =======================================+==========+==========+==========
+
+The 24-ft. 6-in. tunnel adjoining the Terminal Station-West was
+water-proofed by a surface-rendering method which, up to the present
+time, has been satisfactory. Generally speaking, the arches of the Land
+Tunnels, though not dripping with water, are the dampest parts of the
+whole structure from Tenth Avenue to Weehawken, and it would seem as if
+some form of water-proofing over these arches would have been a distinct
+advantage.
+
+There was no difficulty in applying the water-proofing on the
+side-walls, after a little experience had been gained as to the best
+methods. The specifications required the sand-wall to be covered with
+alternate layers of coal-tar pitch and felt, seven layers of the former
+and six layers of the latter, the felt to be of Hydrex brand or other
+equally satisfactory to the engineer. The pitch was to be straight-run,
+coal-tar pitch which would soften at 60° Fahr., and melt at 100° Fahr.,
+being a grade in which distillate oils, distilled from it, should have a
+specified gravity of 1.105. The pitch was to be mopped on the surface to
+a uniform thickness of 1/16 in., and a covering of felt, previously
+mopped with pitch, was to be applied immediately. The sheets were to lap
+not less than 4 in. on cross-joints and 12 in. on longitudinal joints,
+and had to adhere firmly to the pitch-covered surface. This layer was
+then to be mopped, and another layer placed, and so on until all the
+layers were in place. This water-proofing was to extend from the bottom
+of the cable conduits to the springing of the brick arch. Where
+sub-track conduits were used, these were to be surrounded with their own
+water-proofing. The work was carried out as specified; the sand-walls
+were not rendered, but were built smooth enough to apply the
+water-proofing directly to them. They were dried with gasoline torches
+before the application of the pitch, and in very wet sections grooves
+were cut to lead the water away.
+
+The first attempts were with the felt laid in horizontal strips. This
+ended very disastrously, as the pitch could not sustain the weight of
+the felt, and the whole arrangement slipped down the wall. The felt was
+then laid vertically, being tacked to a piece of horizontal scantling at
+the top of the sand-wall and also held by a row of planks braced
+against it at about half its height. A layer of porous brick was laid as
+a drain along the base of the water-proofing, covered by a single layer
+of felt to prevent it from becoming choked with concrete.
+
+The water-proofing of the sub-track conduits was troublesome, as the
+numerous layers and the necessity for preserving the proper laps in both
+directions between adjacent layers made the whole thing a kind of
+Chinese puzzle. Various modifications, to suit local conditions, were
+made from time to time. Conduits outside the general outline of the
+tunnel are difficult to excavate, to lay, and to water-proof, and should
+be avoided wherever possible.
+
+The usual force in water-proofing consisted of a foreman, at $3.50 per
+day, and nine laborers at $1.75 per day. These men not only laid the
+water-proofing, but transported the materials, heated the pitch, and cut
+up the rolls of felt. In general, two men transported material, one
+tended the heater, and the other six worked in pairs, two preparing the
+surface of the concrete sand-wall, two laying pitch, and two laying
+felt.
+
+The cost of the water-proofing operation was about as shown in Table 14.
+
+TABLE 14.--COST OF WATER-PROOFING, IN DOLLARS PER SQUARE FOOT.
+
+ =======================================+==========+===========+========
+ |Manhattan.| Weehawken.| Total.
+ ---------------------------------------+----------+-----------+--------
+ Square feet covered | 47,042 | 13,964 | 60,736
+ ---------------------------------------+----------+-----------+--------
+ Average cost per square foot.
+ ---------------------------------------+----------+-----------+--------
+ Labor | $0.07 | $0.07 | $0.07
+ Material | 0.12 | 0.09 | 0.11
+ ---------------------------------------+----------+-----------+--------
+ Total field charges | $0.19 | $0.16 | $0.18
+ Chief office and plant depreciation | 0.01 | 0.03 | 0.02
+ ---------------------------------------+----------+-----------+--------
+ Total average cost | $0.20 | $0.19 | $0.20
+ =======================================+==========+===========+========
+
+_Brickwork in Arches._--Owing to the heavy timbering, the brickwork at
+Manhattan was interfered with to a considerable extent, and the gang was
+always kept at work at two or more places. The work was carried up to a
+point where it was necessary to back-fill, or prop or cut away
+encroaching timbers, and then the men were moved to another place while
+this was being done.
+
+The centers were set up in sets of seven, spaced 4 ft. apart. Two
+14-ft. lengths of 3 by 4-in. yellow pine lagging were used with each set
+of ribs, with 24 by 8-in. block lagging in the crown.
+
+All centers were set ¼ in. high, to allow for settlement, except in
+the 24-ft. 6-in. span, in which they were set ½ in. high. This proved
+ample, the average settlement of the ribs being 0.01 ft. and of the
+masonry, 0.003 ft. In the 24-ft. 6-in. span the ribs were strengthened
+with 6 by 6-in. blocking and 12 by 12-in. posts to subgrade. Great
+trouble was here encountered with encroaching timbering, due to the
+settlement of the wide flat span. Grout pipes were built in, as
+previously mentioned.
+
+Each mason laid an average of 0.535 cu. yd. of brickwork per hour, or
+4.28 cu. yd. per day. The number of bricks laid per mason per hour was
+218, or 1,744 per day.
+
+The bricks were of the best quality of vitrified paving brick, and were
+obtained from the Jamestown Brick Company, of Jamestown, N. Y. The
+average size was 8¾ by 3-15/16 by 2-7/16 in.; the average number per
+cubic yard of masonry was 408, the arches being from 19 ft. to 24 ft. 6
+in. in span and from 22 to 27 in. thick. The joints were 3/16 in. at the
+face and averaged 9/16 in. through the arch.
+
+The proportions for mortar were 1 of cement and 2½ of sand. One cubic
+yard of masonry was composed of 73.5% brick and 26.5% mortar. The volume
+of the ingredients in a four-bag batch was 12.12 cu. ft., and the
+resulting mixture was 9.54 cu. ft. The number of barrels of cement was
+0.915 per cu. yd. of masonry, and about 17.7% of the mortar made was
+wasted. The average force employed was:
+
+ _Laying._
+ 1 Foreman @ $8.00 per day
+ 4 Layers " 6.00 " "
+ 8 Tenders " 2.00 " "
+ 2 Mixers " 2.00 " "
+ _Forms._
+ 1 Foreman @ $4.50 per day
+ 4 Carpenters " 3.50 " "
+ 5 Helpers " 2.25 " "
+ _Transport._
+ ¼ Hoist engineer @ $3.00 per day
+ ¼ Signalman " 2.00 " "
+ 4 Laborers " 2.00 " "
+
+For materials, the following prices prevailed:
+
+ Cement, $2.00 per bbl.,
+ Sand, $0.90 to $1.00 per cu. yd.,
+ Brick, $16.00 per thousand, delivered at yard,
+ Centers, $26.00 each,
+ Lagging, $45.00 per 1,000 ft. B. M.
+
+The cost of the brickwork is given in Table 15.
+
+TABLE 15.--COST OF BRICKWORK.
+
+ ===========================================+==========+==========+======
+ |Manhattan.|Weehawken.|Total.
+ -------------------------------------------+----------+----------+------
+ Cubic yards placed | 4,137 | 790 |4,927
+ -------------------------------------------+----------+----------+------
+ LABOR. |Average Cost per Cubic Yard.
+ -------------------------------------------+----------+----------+------
+ Surface transport | $0.35 | $1.19 | $0.48
+ Superintendent and general labor at point | | |
+ of work | 0.17 | 0.04 | 0.16
+ Laying and mixing | 2.58 | 3.20 | 2.60
+ Forms: erection and removal | 2.62 | 0.32 | 2.25
+ Tunnel transport | 1.19 | 1.12 | 1.18
+ -------------------------------------------+----------+----------+------
+ Total labor | $6.91 | $5.87 | $6.75
+ -------------------------------------------+----------+----------+------
+ MATERIAL.
+ -------------------------------------------+----------+----------+------
+ Brick | $6.56 | $6.56 | $6.56
+ Cement | 1.76 | 1.75 | 1.76
+ Sand | 0.20 | 0.28 | 0.22
+ Forms | 0.92 | 0.98 | 0.98
+ Overhead conductor pockets | 0.15 | 0.09 | 0.13
+ -------------------------------------------+----------+----------+------
+ Total material | $9.59 | $9.66 | $9.60
+ -------------------------------------------+----------+----------+------
+ Plant running | $0.55 | $0.30 | $0.51
+ Surface labor, repairs and maintenance | 0.36 | 1.30 | 0.51
+ Field office administration | 0.55 | 0.88 | 0.60
+ -------------------------------------------+----------+----------+------
+ Total field charges | $17.96 | $18.01 |$17.97
+ -------------------------------------------+----------+----------+------
+ Chief office administration | $0.60 | $0.66 | $0.61
+ Plant depreciation | 0.35 | 0.64 | 0.39
+ -------------------------------------------+----------+----------+------
+ Total average cost per cubic yard | $18.91 | $19.31 |$18.97
+ ===========================================+==========+==========+======
+
+In Table 16 the cost of grout is expressed in terms of barrels of cement
+used, because in the schedule of prices attached to the contract, that
+was the unit of payment for grout.
+
+ TABLE 16.--COST OF GROUT OVER ARCHES IN LAND TUNNELS.
+ Cost, in Dollars per Barrel of Cement Used.
+
+ ======================================+===============+==========+======
+ | Manhattan. | |
+ |(Gy-East only.)|Weehawken.|Total.
+ --------------------------------------+---------------+----------+------
+ Barrels used | 3,000½ | 261½ |3,262
+ --------------------------------------+---------------+----------+------
+ Average Cost
+ per Barrel of Cement Used.
+ --------------------------------------+---------------+----------+------
+ Labor | $0.55 | $0.46 |$0.53
+ Material | 2.30 | 2.25 | 2.28
+ Field office administration | 0.08 | 0.06 | 0.08
+ Plant and supplies | 0.10 | 0.07 | 0.09
+ --------------------------------------+---------------+----------+------
+ Total field charges | $3.03 | $2.84 |$2.98
+ --------------------------------------+---------------+----------+------
+ Chief office and plant depreciation | 0.21 | 0.22 | 0.28
+ --------------------------------------+---------------+----------+------
+ Total average cost | $3.24 | $3.06 |$3.20
+ ======================================+===============+==========+======
+
+_Vitrified Earthenware Conduits for Electric Cables._--The general
+drawings will show how the ducts were arranged, and that manholes were
+provided at intervals. They were water-proofed, in the case of those
+embedded in the bench, by the general water-proofing of the tunnels,
+which was carried down to the level of the bottom of the banks of ducts;
+and in the case of those below subgrade, by a special water-proofing of
+felt and pitch wrapped around the ducts themselves.
+
+The portion of wall in front of the ducts was bonded to that behind by
+bonds, mostly of expanded metal, passing between the ducts. Examples of
+the bonding will be seen in the drawings.
+
+The joints between successive lengths of 4-way and 2-way ducts were
+wrapped with two thicknesses of cotton duck, 6 in. wide, those of
+single-way ducts were not wrapped, but plastered with cement mortar. The
+ducts were laid on beds of mortar, and were made to break joints at top
+and bottom and side to side with the adjacent ducts. They were laid with
+a wooden mandrel; a square leather washer at the near end acted as a
+cleanser when the mandrel was pulled through.
+
+The specifications required the ducts to be laid at the same time as the
+concrete and be carried up with it, but this was found to be a very
+awkward operation, as the tamping of the concrete and the walking of
+men disturbed the ducts, especially as the bonds lay across them. It was
+resolved, therefore, to build the portion of the wall behind the ducts
+first, with the bonds embedded in it at the proper heights and
+projecting from it, then to lay up the banks of ducts against this wall,
+bending the bonds down as they were reached, and finally, after all the
+ducts were in, to lay the concrete in front of and over the top of the
+ducts. Several detailed modifications of this general scheme were
+followed at one time or another when necessary or advisable.
+
+The laying of ducts below subgrade was not complicated by the presence
+of bonds, the water-proofing caused the trouble here, as before
+described.
+
+The specifications called for a final rodding after completion. A group
+of the apparatus used in this process is shown in Fig. 1, Plate XXXV;
+the various parts are identified by the following key:
+
+ KEY TO FIG. 1, PLATE XXXV.
+
+ 1.--4-way duct, for telephone and telegraph cables,
+ 2.--2-way duct, for telephone and telegraph cables,
+ 3.--1-way duct, for high- and low-tension cables,
+ 4.--Plug for closing open ends of ducts,
+ 5.--Plug for closing open ends of ducts in position,
+ 6, 7, and 8.--Cutters for removing obstructions,
+ 9.--Hedgehog cutter for removing grout in ducts,
+ 10.--Rodding mandrel for multiple ducts,
+ 11.--Laying mandrel,
+ 12.--Rodding mandrel, with jar-link attached,
+ 13.--Laying mandrel,
+ 14 and 15.--Rubber-disk cleaners, used after final
+ rodding,
+ 16 and 17.--Sectional wooden rods used for rodding,
+ 18.--Section of iron rods used for rodding,
+ 19.--Jar-link,
+ 20.--Cotton duck for wrapping joints of multiple ducts,
+ 21.--Hook for pulling forward laying mandrel,
+ 22.--Top view of trap for recovering lost or broken
+ rods left in ducts.
+
+[Illustration: PLATE XXXV. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1. FIG. 2.]
+
+Ordinary ¾-in. gas pipe was used for the rod, and a cutter with
+rectangular cross-section and rounded corners was run through ahead of
+the mandrel: following the cutter came a scraper consisting of several
+square leather washers, of the size of the ducts, spaced at intervals on
+a short rod. The mandrel itself was next put through, three or four men
+being used on the rods. All the ducts in a bank were thus rodded from
+manhole to manhole. When a duct was rodded it was plugged at each end
+with a wooden plug. A solid wooden paraffined plug was used at first,
+but afterward an expansion plug was used.
+
+Very little trouble was met in rodding the power conduits, except for a
+few misplaced ducts, or a small mound of mortar or a laying mandrel left
+in. At such points a cut was made in the concrete and the duct replaced.
+
+In the subgrade telephone and telegraph ducts east of the Manhattan
+Shaft, much trouble was caused by grout in the ducts. The mandrel and
+cutters were deflected and broke through the web of the ducts rather
+than remove this hard grout. Trenches had to be cut from the floor to
+the top of the water-proofing, the latter was then cut and folded back,
+and the ducts replaced. To do this, a number of ducts had to be taken
+out to replace the broken ones and get the proper laps. The
+water-proofing was then patched and the concrete replaced. This grout
+had not penetrated the water-proofing, but had got in through the ends
+of the ducts where they had not been properly plugged and protected. The
+duct gang, both for laying and rodding, generally consisted of
+
+ 1 Foreman, at $3.50 per day,
+ and 9 laborers, at $1.75 per day.
+
+When laying: 4 men were laying, 2 men mixing and carrying mortar, and 3
+were transporting material. When rodding: 4 men were rodding, 2 men at
+adjacent manholes were connecting and disconnecting cutters and
+mandrels, 1 was joining up rods, and 2 men assisting generally.
+
+The cost of this work is shown in Table 17.
+
+
+Transportation and Disposal.
+
+The track on the surface and in the tunnels was of 20-lb. rails on a
+2-ft. gauge.
+
+The excavation was handled in scale-boxes carried on flat cars, and the
+concrete in 1¼-cu. yd. mining cars dumping either at the side or
+end.
+
+TABLE 17.--COST OF CONDUIT WORK.
+
+ =========================================+==========+==========+=======
+ |Manhattan.|Weehawken.| Total.
+ -----------------------------------------+----------+----------+-------
+ Duct feet | 115,962 | 35,155 |151,117
+ -----------------------------------------+----------+----------+-------
+ Average Cost per Duct Foot.
+ -----------------------------------------+----------+----------+-------
+ Labor | $0.035 | $0.032 | $0.034
+ Material | 0.043 | 0.052 | 0.045
+ -----------------------------------------+----------+----------+-------
+ Total field charges | 0.078 | 0.084 | 0.079
+ -----------------------------------------+----------+----------+-------
+ Chief office and plant depreciation | 0.005 | 0.008 | 0.006
+ -----------------------------------------+----------+----------+-------
+ Total average cost | $0.083 | $0.092 | $0.085
+ =========================================+==========+==========+=======
+
+When the haulage was up grade, 6 by 6-in. Lidgerwood hoisting engines,
+with 10-in. single friction drums, and driven by compressed air from the
+high-pressure lines, were used. Down grade, cars were moved and
+controlled by hand.
+
+The muck which came through the shaft at Manhattan was dumped into
+hopper bins on the surface and thence loaded into trucks at convenience.
+At the open cut, the muck was dumped into trucks direct. The trucking
+was sublet by the contractor to a sub-contractor, who provided trucks,
+teams, and trimmers at the pier. At Weehawken, arrangements were made
+with the Erie Railroad which undertook to take muck which was needed as
+fill. The tunnel cars, therefore, were dumped directly on flat cars
+which were brought up to a roughly made platform near the shaft.
+
+The hoisting at Manhattan was by derrick at Tenth Avenue and the open
+cut, and by the elevator at the Manhattan Shaft. At Weehawken, all
+hoisting was done by the elevator in the shaft.
+
+The sand and stone were received at the wharves by scows. At Manhattan,
+these materials were unloaded on trucks by an overhead traveler, and
+teamed to the shaft, where they were unloaded by derricks into the bins.
+At Weehawken, they were unloaded by an orange-peel grab bucket, loaded
+into cars on the overhead trestle, transported in these to the top of
+the shaft, and discharged into the bins.
+
+The cement at Manhattan was trucked from the Company's warehouse, at
+Eleventh Avenue and 38th Street, to the shaft, where it was put into a
+supplementary storage shed at the top of the shaft, whence it was
+removed to the mixer by the elevator when needed. At Weehawken, it was
+taken on flat cars directly from the warehouse to the mixer.
+
+
+Lighting.
+
+Temporarily and for a short time at the start, kerosene flares were used
+for light until replaced by electric lights, the current for which was
+furnished by the contractor's generators, which have been described
+under the head of "Power Plant."
+
+The lamps used along the track were of 16 c.p., and were protected by
+wire screens; these were single, but, wherever work was going on, groups
+of four or five, provided with reflectors, were used.
+
+
+Pumping.
+
+Two pumps were installed at the Manhattan Shaft. They had to handle the
+water, not only from the rock tunnels, but also from those under the
+river. One was a Deane compound duplex pump, having a capacity of 500
+gal. per min., the other, a Blake pump, of 150 gal. per min. They were
+first driven by steam direct from the power-house, but compressed
+air was used later. When the power-house was shut down, an
+electrically-driven centrifugal pump was used. This was driven by a
+General Electric shunt-wound motor, Type C-07½, with a speed of 1,250
+rev. per min. at 250 volts and 37.5 amperes (10 h.p.) when open, and
+22.9 amperes (6 h.p.) when closed, and had a capacity of 450 gal. per
+min. To send the water to the shaft sump during the construction, small
+compressed-air Cameron pumps, of about 140 gal. per min., were used.
+
+At the Weehawken shaft two pumps were used; these dealt with the water
+from the Bergen Hill Tunnels as well as that from the Weehawken Tunnels.
+At first a Worthington duplex pump having a capacity of about 500 gal.
+per min. was used. Later, this was replaced by a General Electric
+shunt-wound motor, Type O-15, with a speed of 925 rev. per min. at 230
+volts and 74 amperes (20 h.p.) when open, and 38.5 amperes (10 h.p.)
+when closed. Its capacity was 240 gal. per min. During the progress of
+the construction, the water was pumped from the working face to the
+shaft by small Cameron pumps similar to those used at Manhattan. When
+the work was finished, a subgrade reversed-grade drain carried the
+water to the shaft sump by gravity.
+
+The work in the Manhattan Land Tunnels was practically finished by May
+1st, 1908, though the ventilating arrangements and overhead platform in
+the intercepting arch were not put in until after the River Tunnel
+concrete was completed, so that the work was not finished until
+September, 1909.
+
+The Weehawken Land Tunnels work was finished in July, 1907, but the
+benches and ventilating arrangements in the Weehawken Shaft were not put
+in until after the completion of the Bergen Hill Tunnels, and so were
+not finished until August, 1909.
+
+The reinforced concrete wall around the Weehawken Shaft, together with
+the stairs from the bench level of the shaft to the surface, was let as
+a separate contract; the work was started on September 15th, 1909, and
+finished by the end of December, 1909.
+
+
+RIVER TUNNELS.
+
+The River Tunnel work, from some points of view, has the most interest.
+It is interesting because it is the first main line crossing of the
+formidable obstacle of the Hudson River, and also by reason of the long
+and anxiously discussed point as to whether, in view of the preceding
+experiences and failures to construct tunnels under that river,
+foundations were needed under these tunnels to keep them from changing
+in elevation under the action of heavy traffic.
+
+The River Tunnels here described start on the east side of the shield
+chambers on the New York side and end at the east side of the shield
+chambers on the New Jersey side. They thus include the New York and
+exclude the New Jersey shield chambers, the reason for such
+discrimination being that the New York shield chambers are lined with
+cast iron while those on the New Jersey side are of the typical rock
+section type, as already described. The design of the tunnels and their
+accessories will be first described, then will come the construction of
+the tunnels as far as the completion of the metal lining, followed by a
+description of the concrete lining and completion of the work.
+
+
+Design of Metal Lining.
+
+_New York Shield Chambers._--The shield chambers may be seen on Plate
+XXXII, previously referred to, which shows the junction of the
+iron-lined tunnels and the shield chambers. They consist of two
+iron-lined pieces of tunnel placed side by side, with semi-circular
+arches and straight side-walls. The segments of the arch are made to
+break joint with one another by making the side-wall or column castings
+of two different heights, as shown in Fig. 9. The length of each ring is
+18 in.
+
+The reason for the adoption of this type of construction was the
+necessity for keeping the width of the permanent structure within the
+60-ft. width of the street. The length of this twin structure is 28.5
+ft., and the weight of the metal in it is as follows:
+
+ 19 long-column arch rings at 22,802 lb. 433,238 lb.
+ 19 short-column arch rings at 23,028 lb. 437,532 "
+ -------
+ Total weight 870,770 lb.
+
+_General Type of River Tunnel Lining._--The main ruling type adopted for
+the tunnels under the Hudson River, and in the soft water-bearing ground
+for some distance on the shoreward side of the river lines, consists of
+two parallel metal-lined tunnels, circular in cross-section, each tunnel
+being 23 ft. outside diameter, and the two tunnels 37 ft. apart from
+center to center, as shown on Fig. 10. The metal lining is of cast iron
+(except for a few short lengths of cast steel) and of the usual
+segmental type, consisting of "Rings" of iron, each ring being 2 ft. 6
+in. in length, and divided by radial joints into eleven segments, or
+"Plates," with one "Key," or closing segment, having joints not radial
+but narrower at the outside circumference of the metal lining than at
+the inside. The whole structure is joined, segment to segment, and ring
+to ring, by mild-steel bolts passing through bolt holes in flanges of
+all four faces of each segment. The joints between the segments are made
+water-tight by a caulking of sal-ammoniac and iron borings driven into
+grooves formed for the purpose on the inner edges of the flanges. The
+clearances between the bolts and the bolt holes are also made
+water-tight by using grummets or rings of yarn smeared with red lead,
+having a snug fit over the shank of the bolt and placed below the washer
+on either end of each bolt. When passing through ground more or less
+self-sustaining, the space outside the iron lining (formed by the
+excavation being necessarily rather larger than the external diameter of
+the lining itself) was filled with grout of 1:1 Portland cement and sand
+forced by air pressure through grout holes in each segment. These holes
+were tapped, and were closed with a screw plug before and after
+grouting.
+
+[Illustration: DETAILS OF MANHATTAN SHIELD CHAMBERS FIG. 9.]
+
+Having thus stated in a general way the main ruling features of the
+design, a detailed description of the various modifications of the
+ruling type will be given.
+
+[Illustration: TYPICAL CROSS-SECTION OF RULING DESIGN OF METAL-LINED
+SHIELD-DRIVEN TUNNELS FIG. 10.]
+
+The two main divisions of the iron lining are the "ordinary" or lighter
+type and the heavy type. The details of the ordinary iron are shown in
+Fig. 11, which shows all types of lining. It was on this design that the
+contract was let, and it was originally intended that this should be the
+only type of iron used. The dimensions of the iron are clearly shown on
+the drawing, and it will be seen that the external diameter is 23 ft.,
+the interior diameter, 21 ft. 2 in., the length of each ring, 2 ft. 6
+in., and the thickness of the iron skin or web, 1½ in. The bolt holes
+in the circumferential flanges are evenly spaced through the circle, so
+that adjacent rings may be bolted together in any relative position as
+regards the radial joints, and, as a matter of fact, in the erection of
+the tunnel lining, all the rings "break joint," with the exception of
+those at the bore segments, as will be described later. This type of
+iron, when the original type was modified, came to be known as the
+ordinary pocketless iron; that is, the weight is of the ordinary or
+lighter type, in contradistinction to the heavier one, which later
+supplanted it, and the caulking groove runs along the edges of the
+flanges and does not form pockets around the bolt holes, as did the
+groove in a later type.
+
+Each ring is made up of eleven segments and a key piece. Of these, nine
+have radial joints at both ends, and are called "_A_" segments; two,
+called "_B_" segments, have a radial joint at one end and a non-radial
+joint at the other. The non-radial joint is placed next to the key,
+which is 12.25 in. wide at the outside circumference of the iron and
+12.50 in. wide at the inside.
+
+The web is not of uniform thickness. The middle part of each _A_ and _B_
+segment is 1½ in. thick; at the distance of 6 in. from the root of
+each flange, the thickness of web begins to increase, so that at the
+root it is 2-3/8 in. thick. The web of the key plate is 1¾ in. thick.
+
+The bolts are of mild steel, and are 1½ in. in diameter; there are 67
+in one circumferential joint and 5 in each radial joint. As there are 12
+such radial joints, there are altogether 60 bolts in the cross-joints,
+making a total of 127 bolts per ring.
+
+This original type of ordinary iron was modified for a special purpose
+as follows: It was known that for some distance on either side of the
+river, and especially at Weehawken, the tunnels would pass through a
+gravel formation, rather open, and containing a heavy head of water. It
+was thought that, by carrying the caulking groove around the bolt holes,
+it would be possible to make them more water-proof than by the simple
+use of the red-leaded grummets. Hence the "Pocket Iron" was adopted for
+this situation, the name being derived from the pocket-like recess which
+the caulking groove formed when extended around the bolt hole. The
+details of this lining are shown on Fig. 11, and the iron (except for
+the pockets) is exactly like the pocketless type.
+
+[Illustration: DETAILS OF ALL TYPES OF METAL LININGS USED IN SUBAQUEOUS
+SHIELD-DRIVEN TUNNELS FIG. 11.]
+
+On the New York side, in both North and South Tunnels, two short lengths
+were built with cast-steel lining. This was done where unusual stresses
+were expected to come on the lining, namely, at the point where the
+invert passed from firm ground to soft, and also where the tunnels
+passed under the heavy river bulkhead wall.
+
+The design was precisely the same as for the ordinary pocketless iron,
+and Fig. 11 shows the details. After the tunnels had entered into the
+actual under-river portion, several phenomena (which will be described
+later) led to the fear that the tunnels, being lighter than the
+semi-liquid mud they displaced, might be subject to a buoyant action,
+and therefore a heavier type of lining was designed. The length of ring,
+number of bolts, etc., were just the same as for the lighter iron, but
+the thickness of the web was increased from 1½ to 2 in., the
+thickness of the flanges was proportionately increased, and the diameter
+of the bolts was increased from 1½ to 1¾ in. This iron was all of
+the pocketless type, shown in Fig. 11. Table 18 gives the weights of the
+various types of lining.
+
+TABLE 18.--WEIGHTS OF TUNNEL LINING, DIAMETER AND WEIGHTS OF BOLTS, ETC.
+
+ +=========+===============+========+========+=======+========+========|
+ |Reference|Type of Lining.| Weight | Weight |Weight | Weight |Diameter|
+ |No. | | of one | of one |of one | of one | of |
+ | | | "A" | "B" |key, in|complete| bolts, |
+ | | |Segment,|Segment,|pounds.|ring, in| in |
+ | | | in | in | |pounds. |inches. |
+ | | |pounds. |pounds. | | | |
+ | | | | | | | |
+ | | | | | | | |
+ | | | | | | | |
+ | | | | | | | |
+ |---------+---------------+--------+--------+-------+--------+--------|
+ |1 |Ordinary cast | 2,063 | 2,068 | 480 | 23,183 | 1½ |
+ | |iron without | | | | | |
+ | |caulking | | | | | |
+ | |pockets. | | | | | |
+ |2 |Ordinary cast | 2,038 | 2,043 | 469 | 22,897 | 1½ |
+ | |iron with | | | | | |
+ | |caulking | | | | | |
+ | |pockets. | | | | | |
+ |3 |Ordinary cast | 2,247 | 2,252 | 522 | 25,249 | 1½ |
+ | |steel without | | | | | |
+ | |caulking | | | | | |
+ | |pockets. | | | | | |
+ |4 |Heavy cast iron| 2,579 | 2,584 | 606 | 28,985 | 1¾ |
+ | |without | | | | | |
+ | |caulking | | | | | |
+ | |pockets. | | | | | |
+ +---------+---------------+--------+--------+-------+--------+--------+
+
+ +=========+===============+========+=======+=========+
+ |Reference|Type of Lining.| Weight |Weight | Total |
+ |No. | | of 1 | of |weight of|
+ | | | bolt, |bolts, |one ring |
+ | | |nut, and| nuts, |(segments|
+ | | | 2 | and | and |
+ | | |washers,|washers| bolts), |
+ | | | in | per | in |
+ | | |pounds. | ring, | pounds. |
+ | | | | in | |
+ | | | |pounds.| |
+ |---------+---------------+--------+-------+---------|
+ |1 |Ordinary cast | 6.62 | 840.7 | 24,024 |
+ | |iron without | | | |
+ | |caulking | | | |
+ | |pockets. | | | |
+ |2 |Ordinary cast | 6.62 | 840.7 | 23,738 |
+ | |iron with | | | |
+ | |caulking | | | |
+ | |pockets. | | | |
+ |3 |Ordinary cast | 6.62 | 840.7 | 26,090 |
+ | |steel without | | | |
+ | |caulking | | | |
+ | |pockets. | | | |
+ |4 |Heavy cast iron| 10.50 |1,333.5| 30,319 |
+ | |without | | | |
+ | |caulking | | | |
+ | |pockets. | | | |
+ +---------+---------------+--------+-------+---------+
+
+
+ WEIGHTS OF VARIOUS TYPES OF LINING PER LINEAR FOOT OF TUNNEL.
+
+ +---------+---------------+--------------+-------------+---------------+
+ |Reference|Type of Lining.|Weights of |Weights of |Weights of |
+ |No. | |complete rings|bolts, nuts, |segments and |
+ | | |(segments |and washers, |bolts in tunnel|
+ | | |only), in |in pounds. |complete, in |
+ | | |pounds. | |pounds. |
+ |---------+---------------+--------------+-------------+---------------|
+ |1 |Ordinary cast | 9,273.0 | 336.3 | 9,609.6 |
+ | |iron without | | | |
+ | |pockets. | | | |
+ | | | | | |
+ |2 |Ordinary cast | 9,158.8 | 336.3 | 9,495.2 |
+ | |iron with | | | |
+ | |pockets. | | | |
+ | | | | | |
+ |3 |Ordinary cast | 10,099.6 | 336.3 | 10,436.0 |
+ | |steel without | | | |
+ | |pockets. | | | |
+ | | | | | |
+ |4 |Heavy cast iron| 11,594.0 | 533.4 | 12,127.6 |
+ | |without | | | |
+ | |pockets. | | | |
+ +=========+===============+==============+=============+===============+
+
+The weights in Table 18 are calculated by assuming cast iron to weigh
+450 lb. per cu. ft., and cast steel 490 lb. In actual practice the
+"ordinary" iron was found to weigh a little more than the weights given,
+and the "heavy" a little less.
+
+The silt in the sub-river portion averaged about 100 lb. per cu. ft., so
+that the weight of the silt displaced by the tunnel was about 41,548 lb.
+per lin. ft.
+
+_Taper Rings._--In order to pass around curves (whether horizontal or
+vertical), or to correct deviation from line or grade, taper rings were
+used; by this is meant rings which when in place in the tunnels were
+wider than the standard rings, either at one side (horizontal tapers or
+"Liners"), or at the top ("Depressors"), or at the bottom ("Elevators").
+
+In the original design a ½-in. taper was called for, that is, the wide
+side of the ring was ½ in. wider than the narrow side, which was of
+the standard width of 2 ft. 6 in. As a matter of fact, during
+construction, not only ½-in., but ¾-in. and 1-in. tapers were often
+used.
+
+These taper rings necessitated each plate having its own unalterable
+position in the ring, hence each plate of the taper ring was numbered,
+so that no mistake could be made during erection.
+
+The taper rings were made by casting a ring with one circumferential
+flange much thicker than usual, and then machining off this flange to
+the taper. This was not only much cheaper than making a special pattern
+for each plate, but made it possible to see clearly where and what
+tapers were used in the tunnel.
+
+Taper rings were provided for all kinds of lining (except the cast
+steel), and the lack of taper steel rings was felt when building the
+steel-lined parts of the tunnel, as nothing could be done to remedy
+deviations from line or grade until the steel section was over and cast
+iron could again be used. Table 19 gives the weights of the different
+kinds of tapers used.
+
+TABLE 19.--WEIGHTS OF CAST-IRON TAPER RINGS, IN POUNDS PER COMPLETE
+RING.
+
+ =================================+======================================
+ Classification. |Weight of cast iron per complete ring,
+ | in pounds.
+ ---------------------------------+--------------------------------------
+ Ordinary pocketless ½- in. taper| 23,767.7
+ " " 1- " " | 24,352.4
+ " pocket ½- " " | 23,481.7
+ Heavy pocketless ½- in. taper | 29,564.8
+ " " ¾- " " | 29,854.7
+ " " 1- " " | 30,144.6
+ =================================+=======================================
+
+_Cast-Steel Bore Segments and Accessories._--The following feature of
+these tunnels is different from any hitherto built. It was the original
+intention to carry the rolling load independent of the tunnel, or to
+assist the support of the silt portion of the structure by a single row
+of screw-piles, under each tunnel, and extending down to firmer ground
+than that through which the tunnels were driven. Therefore, provision
+had to be made whereby these piles could be put down through the invert
+of the tunnel with no exposure of the ground.
+
+[Illustration: DETAILS OF BORE SEGMENTS AND ACCESSORIES USED IN
+SUBAQUEOUS SHIELD DRIVEN TUNNELS FIG. 12.]
+
+This provision was afforded by the "Bore Segments," which are shown in
+detail in Fig. 12. There are two segments, called No. 1 and No. 2,
+respectively. These two segments are bolted together in the bottom of
+two adjacent rings, and thus form a "Pile Bore." As the piles were to be
+kept at 15-ft. centers, and as the tunnel rings were 2 ft. 6 in. in
+length, it will be seen that, between each pair of bore-segment rings,
+there came four "Plain" rings. The plain rings were built up so that the
+radial joints broke joint from ring to ring, but with the bore-segment
+rings this could not be done, without unnecessarily adding to the types
+of segments.
+
+The bore segments were made of cast steel, and were quite complicated
+castings, the principle, however, was quite simple. The segments
+provided an opening just a little larger than the shaft of the pile, the
+orifice being 2 ft. 7 in. in diameter at the smallest (lowest) point,
+while the shaft of the pile was to be 2 ft. 5¼ in. In order to allow
+of the entry of the screw-blade or helix of the pile, a slot was formed
+in the depth of Bore Segment No. 1, so that, when a pile was put in
+position above the bore, the blade, when revolved, would enter the slot
+and thus pass under the metal lining, although the actual orifice was
+only slightly larger than the pile shaft.
+
+The wall of the pile orifice in Segment No. 2 was made lower than that
+in No. 1 so as to allow the blade to enter the slot in Segment No. 1.
+When the pile is not actually in process of being sunk, this lower
+height in No. 2 is made up with the removable "distance piece." This had
+a tongue at one end which engaged in a recess cast to take it in Segment
+No. 2 and was held in place by a key piece at the other end of the
+distance piece. Details of the distance piece and key are shown in Fig.
+12.
+
+The flanges around the pile bore were made flat and furnished with
+twelve tapped holes, six in Segment No. 1 and six in Segment No. 2, for
+the purpose of attaching the permanent arrangements in conjunction with
+which the pile was to be attached to the track system, independently of
+the tunnel shell, or directly to the tunnel. It was never decided which
+of these alternatives would be used, for, before this decision was
+reached, it was agreed that, at any rate for the present, it was better
+not to put down piles at all.
+
+To close the bore, the "Bore Plug" was used. This is shown on Fig. 12.
+It was of cast steel, and was intended to act as a permanent point of
+the screw-pile, that is, the blade section was to be attached to the
+bore plug, the distance piece and key were to be removed, and the pile
+was to be rotated until the blade had cleared the slot; the distance
+piece and key were then to be replaced and sinking resumed.
+
+The plug was held in place against the pressure of the silt by the two
+"dogs," while the dogs themselves were attached to the tunnel, as shown
+in Fig. 12. The ends of the dogs, which rested on the flanges of the
+metal lining of the tunnel, were prevented from being knocked off the
+flanges (and thus releasing the plug) by steel clips.
+
+It was expected that it might be desirable to keep the lower end of the
+piles open during their sinking, so that the bore plugs were not made
+permanently closed, but a seating was formed on the inner circumference
+of the plug, and on the seating was placed the "Plug Cover," made of
+cast iron, 18¾ in. in diameter and 3 in. thick, furnished with a lug
+for lifting and a 3-in. tapped hole closed by a screw-plug, through
+which any soundings or samples of ground could be taken prior to sinking
+the piles. This plug cover was held in place by a heavy steel "Yoke"
+under it, which engaged on the under side of the flange, on top of which
+the cover was set. The yoke was attached to the cover by a 1¾-in.
+tap-bolt, screwed into the yoke and passing through a 2-in. hole bored
+in the center of the cover. This rather peculiar mode of attaching the
+cover was adopted so that the cover could be removed by taking off the
+nut of the yoke, in case it was desired to open the end of the pile
+during the process of sinking.
+
+The plug was a fairly close fit at the bottom of the orifice, that is,
+at the outside circumference of the tunnel, where the bore was 2 ft. 7
+in. in diameter and the plug 2 ft. 6¾ in., but at the top of the
+bore-segment there was more clearance, as the plug was cylindrical while
+the bore tapered outward. To fill this space, it was intended that steel
+wedges should be used while the shield was being driven, so that they
+would withstand the crushing action of the thrusting shield, and, when
+the shield was far enough ahead, that they should be removed and
+replaced by hardwood wedges. This method was only used in the early
+weeks of the work; the modification of not using the shield-jacks which
+thrust against the bore segments was then introduced, and the wooden
+wedges were put in, when the bore plugs were set in place, and driven
+down to the stage of splitting.
+
+When it was resolved not to sink the screw-piles, the bores had to be
+closed before putting in the concrete lining. This was done by means of
+the covers shown in Fig. 13. The bore plug and all its attachments were
+removed, and the flat steel cover, 2 in. thick and with stiffening webs
+on the under side, was placed over the circular flanges of the pile
+bore. The cover was attached to the bore segments by twelve 1½-in.
+stud-bolts, 6 in. long, in the bolt holes already mentioned as provided
+on these flanges.
+
+When these were in place, with lead grummets under the heads of the
+bolts, and the grooves caulked, the bore segments were water-tight,
+except in Bore Segment No. 2, at the joint of the distance piece; and,
+to keep water from entering here, this segment was filled to the level
+of the top of the flanges with 1:1 Portland cement mortar.
+
+[Illustration: SUBAQUEOUS TUNNELS COVER FOR BORE SEGMENTS FIG. 13.]
+
+The weights of the various parts of the bore segments are given in Table
+20.
+
+TABLE 20.--WEIGHTS OF BORE SEGMENTS AND ACCESSORIES, IN POUNDS.
+
+ ====================+=====+====================================
+ Part. | No. | Material. | Weight, in pounds.
+ --------------------+-----+---------------+--------------------
+ Bore Segment No. 1 | 1 | Cast Steel | 3,004.0
+ Bore Segment No. 2 | 1 | " " | 2,628.0
+ Distance piece | 1 | " " | 423.5
+ Key | 1 | " " | 34.3
+ Plug | 1 | " " | 1,192.5
+ Yoke | 1 | " " | 57.3
+ Dogs | 2 | " " | 106.0
+ Slot cover | 1 | Rolled steel | 6.4
+ Plug cover | 1 | Cast iron | 162.0
+ Dog holders | 2 | Rolled steel | 6.4
+ --------------------+-----+---------------+--------------------
+ Complete weight of one pair, without bolts| 7,620.4
+ ==========================================+====================
+
+_Sump Segments._--In order to provide sumps to collect the drainage and
+leakage water in the subaqueous tunnels, special "sump segments" were
+installed in each tunnel at the lowest point--about Station 241 + 00.
+The details of the design are shown in Fig. 14. The segment was built
+into the tunnel invert as though it were an ordinary "_A_" segment. In
+building the sump, three lining castings were bolted, one on top of the
+other, and attached to the flat upper surface of the sump segment;
+meanwhile, the bolts attaching the sump segment to the adjacent tunnel
+plates were taken out and the plate and lining segments were forced
+through the soft mud by hydraulic jacks, the three 6-in. holes in the
+bottom of the sump segment being opened in order to minimize the
+resistance. The sump when built appeared as shown in Fig. 14, the top
+connection being made with a special casting, as shown.
+
+The capacity of each sump is 500 gal., which is about the quantity of
+water entering the whole length of each subaqueous tunnel in 24 hours.
+
+_Cross-Passages._--When the contract was let, provision was made for
+cross-passages between the tubular tunnels, in the form of special
+castings to be built into the tunnel lining at intervals. However, the
+idea was given up, and these castings were not made. Later, however,
+after tunnel building had started, the question was raised again, and it
+was thought that such cross-connections would be very useful to the
+maintenance forces, that it might be possible to build them safely, and
+that their subsequent construction would be made much easier if some
+provision were made for them while the shields were being driven. It was
+therefore arranged to build, at intervals of about 300 ft., two
+consecutive rings in each tunnel, at the same station in each tunnel,
+with their longitudinal flanges together, instead of breaking joint, as
+was usually done. The keys of these rings were displaced twelve bolt
+holes from their normal positions toward the other tunnel. This brought
+the keys about 6 ft. above the bench, so that if they were removed,
+together with the _B_ plates below them, an opening of about 5 by 7 ft.
+would be left in a convenient position with regard to the bench.
+
+[Illustration: DETAILS OF SUMPS IN SUBAQUEOUS TUNNELS AT STATION 241
+FIG. 14.]
+
+Nothing more was done until after the tunnels were driven. It was then
+decided to limit the cross-passages between the tubular tunnels to the
+landward side of the bulkhead walls. They were arranged as follows:
+three on the New York side, at Stations 203 + 22, 206 + 80, and 209 +
+80, and two on the New Jersey side, at Stations 255 + 46 and 260 + 14.
+The cross-passages are square in cross-section.
+
+TABLE 21.--WEIGHTS OF SUMP SEGMENTS.
+
+ ====================+=====+===============+====================
+ Part. | No. | Material. | Weight, in pounds.
+ --------------------+-----+---------------+--------------------
+ Middle top casting | 1 | Cast steel | 880
+ End top castings | 2 | " " | 1,718
+ Lining castings | 3 | " " | 18,232
+ Sump segment | 1 | Cast iron | 3,560
+ --------------------+-----+---------------+--------------------
+ Total weight per sump, exclusive of bolts | 24,390
+ ==========================================+====================
+
+_Turnbuckle Reinforcement for Cast-Iron Segments._--During the period of
+construction, a certain number of cast-iron segments, mostly in the
+roof, but in some cases at Manhattan in the invert, behind the river
+lines, became cracked owing to uneven pressures of the ground. Before
+the concrete lining was put in, considerable discussion occurred as to
+the wisest course to pursue with regard to these broken plates. It was
+finally thought best not to take the plates out, as more harm than good
+might be done, but to reinforce them with turnbuckles, as shown in Fig.
+15. The number of broken segments was distributed as follows:
+
+ North Manhattan Tunnel 87, chiefly in silt (not under the river),
+ South Manhattan Tunnel 7, chiefly in silt ( " " " " ),
+ North Weehawken Tunnel 24, chiefly in sand ( " " " " ),
+ South Weehawken Tunnel 48, chiefly in silt, under the Fowler
+ Warehouse.
+
+The chief features of the tunnel lining have now been described, and,
+before giving any account of the methods of work, it will be well to
+mention briefly the salient features of the concrete lining which is
+placed within the actual lining.
+
+
+Design of Concrete Lining.
+
+This concrete lining will be considered and described in the following
+order:
+
+ The New York Shield Chambers,
+
+ Standard Cross-Section of Concrete Lining of Shield-Driven
+ Tunnels,
+
+ Final Lines and Grades, and How Obtained,
+
+ Steel Rod Reinforcement of Concrete,
+
+ Cross-Passage Lining,
+
+ Special Provision for Surveys and Observations.
+
+[Illustration: SUBAQUEOUS TUNNELS TURNBUCKLES AND RODS REINFORCING
+TUNNEL SEGMENTS FIG. 15.]
+
+_The New York Shield Chambers._--The cross-section of the concrete
+lining of these chambers is shown by Plate XXXII, referred to in the
+Land Tunnel Section. They are of the twin-tunnel double-bench type. The
+deep space beneath the floor is used as a sump for drainage, and
+manholes for access to the cable conduits are placed in the benches.
+
+[Illustration: TYPES OF CONCRETE LINING OF SHIELD-DRIVEN TUNNELS. FIG.
+16.]
+
+_Standard Cross-Section of Concrete Lining of Shield-Driven
+Tunnels._--The cross-section of the concrete lining of the tube tunnel
+is shown in Fig. 16. There are two main types, one extending from the
+shield chambers to the first bore segment, that is, to where the tunnel
+leaves solid ground and passes into silt, and the other which extends
+the rest of the way. The first type has a drain in the invert, the
+second has not.
+
+The height from the top of the rail to the soffit of the arch being less
+than 16 ft. 11 in., overhead pockets for the suspension of electrical
+conductors were set in the concrete arch on the vertical axis line at
+10-ft. centers. These pockets are shown in Fig. 16. The benches are
+utilized for the cable conduits in the usual way. Ladders are provided
+on one side at 25-ft. and on the other side at 50-ft. intervals, to
+give access from the track level to the top of the benches. Refuge
+niches for trackmen are placed at 25-ft. intervals on the single-way
+conduits side only, as there is not enough room in front of the 4-way
+ducts. Manholes for giving access to the cable conduits, both power, and
+telephone and telegraph, are at 400-ft. intervals.
+
+_Final Lines and Grades, and How Obtained._--It may be well to explain
+here how the final lines and grades for the track, and therefore for the
+concrete lining, were obtained and determined. It is first to be
+premised that the standard cross-section of the tunnel (that is, of the
+concrete and iron lining combined) is not maintained throughout the
+tunnel. In other words, the metal lining is of course uniform, or
+practically so, throughout; the interior surface of the concrete lining
+is also uniform from end to end, but the metal lining, owing to the
+difficulty of keeping the shields, and hence the tunnels built within
+them, exactly on the true line and grade, is not on such lines and
+grades; the concrete lining is built exactly on the pre-arranged lines
+and grades, consequently, the relative positions of the concrete and
+metal linings vary continually along the length of the structure,
+according to whether the metal lining is higher or lower than it should
+be, further to the north or to the south, or any combination of these.
+
+As before stated, it was strongly desired to encroach as little as
+possible on the standard 2-ft. concrete arch, and after some discussion
+it was decided that a thickness of 1 ft. 6 in. was the thinnest it was
+advisable to allow. This made it possible to permit the metal lining of
+the tunnel to be 6 in. lower, in respect to the level of the track at
+any point, than the standard section shows, and also allowed the center
+line of the track to have an eccentricity of 6 in. either north or south
+of the center line of the tunnel. This only left to be settled the
+extent to which the metal lining might be higher in respect to the track
+than that shown on the standard section.
+
+This amount was governed by the desirability of keeping sufficient
+clearance between the top of the rail and the iron lining in the invert
+to admit of the attachment of pile foundations and all the accompanying
+girder-track system which would necessarily be caused by the use of
+piles, should it ever become apparent after operation was begun, that,
+after all, it was essential to have the tunnels supported in this way.
+Careful studies were made of the clearance necessary, and it was
+decided that 4 ft. 9 in. was the minimum allowable depth from the top of
+the rail to the outside of the iron at the bottom. This meant that the
+iron lining could be 3 in. higher, with respect to the track level, than
+that shown on the standard section.
+
+All the determining factors for fixing the best possible lines and
+grades for the track within the completed metal lining were now at hand.
+In March, 1908, careful surveys of plan and elevation were made of the
+tunnels at intervals of 25 ft. throughout. The following operations were
+then performed to fix on the best lines and grades:
+
+First, for Line: It has been explained that the permissible deviation of
+the center line of the track on either side of the center line of the
+tunnel was 6 in. Had the metal lining been invariably of the true
+diameter, it would have been necessary to survey only one side of the
+tunnel; this would have given a line parallel to the center line, and
+might have been plotted as such; then, by setting off 6 in. on either
+side of this line, there would have been obtained a pair of parallel
+lines within which the center line of the track must lie. Owing to
+variations in the diameter of the tunnel, however, such a method was not
+permissible, and therefore the following process was used:
+
+When running the survey lines through the tunnel (which were the center
+lines used in driving the shields), offsets were taken to the inner
+edges of the flanges of the metal lining, both on the north and south
+sides, at axis level at each 25-ft. interval. On the plat on which the
+survey lines were laid down, and at each point surveyed, a distance was
+laid off to north and south equal to the following distances:
+
+Offset, as measured in the tunnel to north (or south), minus 10.08 ft.
+
+This 10.08 ft. (or 10 ft, 1 in.) represents 10 ft. 7 in., the true
+radius to inside of iron, minus 6 in., the permissible lateral deviation
+of the track from the axis of the tunnel.
+
+The result of this process was two lines, one on either side of the
+survey lines, not parallel to it or to each other, but approaching each
+other when the horizontal diameter was less than the true diameter,
+receding from each other when the diameter was more, and exactly 12 in.
+apart when the diameter was correct. As long as the center line of the
+track lay entirely within these two limiting lines, the condition that
+the concrete arch should not be 6 in. less in thickness than the
+standard 2 ft. was satisfied, and in order to arrive at the final line,
+the longest possible tangents that would be within these limits were
+adopted as the final lines; and, as the survey lines were those used in
+driving the tunnel shields (that is, the lines to which it was intended
+that the track should be built), the amount by which the new lines thus
+obtained deviated from the survey lines was a measure of the deviation
+of the finally adopted track and concrete line from the original
+contract lines.
+
+Next, for Grades: The considerations for grade were very similar to
+those for line. If the vertical diameter of the tunnel had been true at
+each 25-ft. interval surveyed, it would have been correct to plot the
+elevations of the crown (or invert) as a longitudinal section of the
+tunnel, and to have set up over those points others 6 in. above (as the
+metal lining could have been 6 in. lower than the standard section,
+which is equivalent to the track being an equal amount higher), and
+below these crown or invert elevations others 3 in. lower (as the metal
+lining could be 3 in. higher).
+
+Then, by joining the points 6 in. above in one line and those 3 in.
+below in another, there would have been obtained lines of limitation
+between which the track grades must lie. However, as the tunnel diameter
+was not uniformly correct, a modification of this method had to be made,
+as in the case of the line determination, the principle, however,
+remaining the same.
+
+The elevations were taken on the inner edges of the circumferential
+flanges of the metal lining, not only in the bottom, but also in the
+top, of the tunnel, at each 25-ft. interval; then, for the upper limit
+of the track at each such interval the following was plotted:
+
+Elevation of inner edge of flange at top, minus 16.58 ft.
+
+This 16.58 ft. (or 16 ft. 7 in.) was obtained thus: The standard height
+from the top of the rail to the inner edge of the iron flange is 17 ft.
+1 in., but, as the track may be 6 in. above the standard or normal, the
+minimum height permissible is 16 ft. 7 in. For the lower limit of track
+at each 25-ft. interval the following was plotted:
+
+Elevation of inner edge of flange at bottom, plus 3.83 ft.
+
+This 3.83 ft. (or 3 ft. 10 in.) was obtained thus: The standard height
+from the top of the rail to the inner edge of the iron flange is 4 ft. 1
+in. (5 ft. to outside of iron, less 11 in. for depth of flange), but,
+as the track may be 3 in. below the standard, the minimum height
+permissible is 4 ft, 1 in. less 3 in., or 3 ft. 10 in.
+
+By plotting the elevations thus obtained, two lines were obtained which
+were not parallel but were closer together or further apart according as
+the actual vertical diameter was less or greater than the standard, and
+the track grade had to lie within these two lines in order to comply
+with the requirements indicated above. The results of these operations
+for the North Tunnel are shown on Plate XXXVI.
+
+The greatest deviations between the lines and grades in the subaqueous
+tunnels as determined by these means and those as originally laid out in
+the contract drawings are on the Weehawken side, and were caused by the
+unexpected behavior of the tunnel when the shields were driven "blind"
+into the silt, causing a rise which could not be overcome, and the
+thrusting aside of one tunnel by the passage of the neighboring one. Had
+this unfortunate incident not occurred, it is clear that it would have
+been possible to adhere very closely indeed to the contract lines and
+grades, although the deviation is small, considering all things.
+
+The internal outline of the concrete cross-section is uniform
+throughout, and is built on the lines and grades thus described.
+
+_Steel Rod Reinforcement of Concrete._--The original intention had been
+to line the metal lining of the tube tunnels with plain concrete, but,
+as the discussion on the foundation question continued, it was felt
+advisable, while still it was intended to put in the foundations, to
+guard against any stresses which were likely to come on the structure,
+by using a system of steel rods embedded circumferentially within the
+concrete. Designs were made on this basis, and even the necessary
+material prepared, before the decision to omit the piles altogether was
+reached. However, in order to provide a safeguard for the structure
+where it is partly or wholly beyond the solid rock, it was decided to
+use reinforcement, even with the piles omitted.
+
+For this purpose the tunnel was considered as a girder, and longitudinal
+reinforcement was provided at the top and bottom. The top reinforcement
+extends from a point 25 ft. behind the point where the crown of the
+tunnel passes out of rock on the New York side to where the crown passes
+into rock on the New Jersey side. The bottom reinforcement extends from
+where the invert of the tunnel passes out of rock on the New York side
+to where it passes into rock on the New Jersey side.
+
+The reinforcement both at top and bottom consists of twenty 1-in. square
+twisted rods, ten placed symmetrically on either side of the vertical
+axis, 9 in. apart from center to center and set 4 in. (to their centers)
+back from the face of the concrete.
+
+As a further precaution, circumferentially-placed rods were used on the
+landward side of the river lines, mainly to assist in preventing the
+distortion of shape which might occur here, either under present
+conditions, such as under the Fowler Warehouse at Weehawken, or under
+any possible different future conditions, such as might be brought about
+by building some new structure in the vicinity of the tunnels.
+
+For purposes of classification of the circumferential reinforcement, the
+tunnel was divided into two types, "_B_" and "_C_"; (Type "_A_" covering
+the portion which, being wholly in solid rock, was not reinforced at
+all).
+
+Type "_B_" covers the part of the tunnels on both sides of the river
+lying between the point where the top of the tunnel passes out of rock
+and the point where the invert passes out of rock on the Manhattan side,
+or out of gravel on the Weehawken side. The reinforcement consists of
+twenty 1-in. square longitudinal rods in the crown of the tunnel, as
+described for the general longitudinal reinforcement, together with
+1-in. square circumferential rods at 10-in. centers, and extending over
+the arch to 2 ft. 3 in. below the horizontal axis.
+
+Type "_C_" extends from the latter limit of Type "_B_" to the river line
+on each side, and consists of longitudinal reinforcement in both top and
+bottom, as described before, together with circumferential reinforcement
+entirely around the tunnel, and formed of 1-in. square twisted rods at
+15-in. centers.
+
+Type "_D_" consists of longitudinal reinforcement only, and extends from
+river line to river line, thus occupying 72.5% of the length in which
+concrete is used. The reinforcement consists of twenty 1-in. twisted
+rods at 9-in. centers in the crown, and twenty 1-in. rods at 9-in.
+centers in the invert. In addition to the three standard types, "_B_,"
+"_C_," and "_D_," there were two sub-types which were used in Type
+"_D_," and in conjunction with it wherever the thickness of the center
+of the concrete arch became less than 1 ft. 6 in., measuring to the
+outside of the metal lining. This thickness was one of the limits used
+in laying out the lines and grades, and in general the arch was not less
+than this. There were one or two short lengths, however, where it was
+less, for, if the arch thickness requirement had been adhered to, it
+would have resulted in a break of line or grade for the sake of perhaps
+only a few feet of thin arch, and it was here that the sub-types came
+into play.
+
+Sub-type 1 was used where the arch was less than 1 ft. 6 in. thick at
+the top. The extra reinforcement here consisted of 1-in. square twisted
+rods, 16 ft. long, laid circumferentially in the crown at 10-in.
+centers.
+
+Sub-type 2 was used where the arch was less than 1 ft. 6 in. thick at
+the side. The extra reinforcement here consisted of 1-in. square twisted
+rods, 16 ft. long, laid circumferentially, at the side on which the
+concrete was thin, at 10-in. centers. Very little of either of these two
+sub-types was used. The entire scheme is shown graphically and clearly
+on Plate XXXVII.
+
+_Cross-Passage Lining._--There are two main types of cross-passages:
+Lined with steel plates, and unlined.
+
+There is only one example of lining with steel plates, namely, the most
+western one at Weehawken. This is built in rock which carried so much
+water that, in order to keep the tunnels and the passage dry, it was
+decided to build a concrete-lined passage, without attempting to stop
+the flow of water, and within this to place a riveted steel lining, not
+in contact with the concrete, but with a space between the two. This
+space was drained and the water led back to the shield chamber and
+thence to the Weehawken Shaft sump. The interior of the steel lining is
+covered with concrete.
+
+In the passages not lined with steel plates the square concrete lining
+is rendered on the inside with a water-proof plaster. Each of the
+passages is provided with a steel door.
+
+_Provisions in Concrete Lining for Surveys and Observations._--The long
+protracted discussion as to the provision for foundations in these
+tunnels led to many surveys, tests, and observations, which were carried
+out during the constructive period, and, as it was desired to continue
+as many of these observations as possible up to and after the time when
+traffic started, certain provisions were made in the concrete lining
+whereby these requirements might be fulfilled. The chief points on which
+information was desired were as follows:
+
+ The change in elevation of the tunnel,
+ The change in lateral position of the tunnel,
+ The change in shape of the tunnel,
+ The tidal oscillation of the tunnel.
+
+A detailed account of these observations will be found in another paper
+on this work, but it may be said now that it was very desirable to be
+able to get this information independently of the traffic as far as
+possible, and therefore provision was made for carrying on the
+observations from the side benches.
+
+For studying the changes in level of the tunnel, a permanent bench-mark
+is established in each tunnel where it is in the solid rock and
+therefore not subject to changes of elevation; throughout the tunnel,
+brass studs are set in the bench at intervals of about 300 ft. A series
+of levels is run every month from the stable bench-mark on each of these
+brass plugs, thus obtaining an indication of the change of elevation
+that the tunnels have undergone during the month.
+
+These results are checked on permanent bench-marks in the subaqueous
+portion of the tunnels. These consist of rods, encased in pipes of
+larger diameter, which extend down through the tunnel invert into the
+bed-rock below the tunnel. Leakage is kept out by a stuffing-box in the
+invert. By measuring between a point on these rods where they pass
+through the invert and the tunnel itself a direct reading of the change
+of elevation of the tunnel is obtained. These measurements are taken at
+weekly intervals, and, as the tunnels are subject to tidal influences,
+being lower at high tide than at low tide, are always taken under the
+same conditions as to height of water in the river. These permanent
+bench-marks are at Stations 209 + 05 and 256 + 02 (about 100 ft. on the
+shoreward side of the river line in each case) in the South Tunnel, at
+Stations 220 + 00 and 243 + 86, also in the South Tunnel, and at Station
+231 + 78 in the North Tunnel. In order to study the lateral change of
+position, a base line was established on the side bench at each end of
+each tunnel in the portion built through the solid rock.
+
+At intervals of about 300 ft. throughout each tunnel, alignment pockets
+are formed in the concrete arch, also above the bench, on the south
+bench of the North Tunnel and the north bench of the South Tunnel. In
+each pocket is placed a graduated and verniered brass bar, so that, when
+the base line is projected on these bars, the lateral movement of the
+tunnel can be read directly. As it was desirable to have as much
+cross-connection as possible between the tunnels at the points where the
+instruments were to be set up, five of the main survey stations were set
+opposite each of the five cross-passages. Then, for the purpose of
+increasing the cross-connection still further, pipes 6 in. in diameter
+were put through from one tunnel to the other at axis level at Stations
+220 + 60, 231 + 78, 234 + 64, 241 + 99, and 251 + 13, and a survey
+station was put in opposite each one.
+
+Points were established at Station 220 + 00, which is the point of
+intersection for the curve on the original center line of the tunnel,
+and also at Station 220 + 23, where the intersection of the track center
+line comes in the North Tunnel. As it was desirable to have the survey
+stations not much more than 300 ft. apart, so as to obtain clear sights,
+other stations were established so that the distances between survey
+stations were at about that interval.
+
+For studying changes of shape in the tunnel, brass "diameter markers"
+were inserted at each survey station in the concrete lining at the
+extremities of the vertical and horizontal axes. These were pieces of
+brass bar, 3/8 in. in diameter and 6 in. long, set in the concrete and
+projecting 5/8 in. into the tunnel, so that a tape could be easily held
+against the marker and read.
+
+For obtaining the tidal oscillation of elevation of the tunnel,
+recording gauges are attached to the invert of the tunnel at each of the
+five permanent bench-marks referred to above in such a way that the
+recording pencil of the gauge is actuated by the rod of the permanent
+bench-mark. A roll of graduated paper is driven by clock-work below the
+recording pencil which thus marks automatically the relative movement
+between the moving tunnel and the stable rods. These have shown that in
+the subaqueous part of the tunnel there is a regular tidal fluctuation
+of elevation, the tunnel moving down as the tide rises, and rising again
+when the tide falls. For an average tide of about 5 ft. the tunnel
+oscillation would be about 1/8 in. Before the concrete lining was
+placed, there was a tidal change in the shape of the tunnel, which
+flattened about 1/64 in. at high tide. After the concrete lining was
+placed, this distortion seemed to cease.
+
+The general design and plan of the work have been described, and before
+giving any account of the contractor's methods in carrying it out, Table
+22, showing the chief quantities of work in the river tunnels, is
+presented.
+
+
+Methods of Construction.
+
+The following is an account of the methods used by the contractor in
+carrying out the plans which have already been described. First, it may
+be well to point out the sequence of events as they developed in this
+work. These events may be divided into six periods.
+
+ _1._--Excavation and Iron Lining: June, 1903, to
+ November, 1906;
+
+ _2._--Caulking and grummeting the iron lining:
+ November, 1906, to June, 1907;
+
+ _3._--Surveys, tests and observations: April, 1907, to
+ April, 1908;
+
+ _4._--Building cross-passages and capping pile bores:
+ April, 1908, to November, 1908;
+
+ _5._--Placing the concrete lining: November, 1908, to
+ June, 1909;
+
+ _6._--Cleaning up and various small works: June, 1909,
+ to November, 1909.
+
+The tunnels were under an average air pressure of 25 lb. per sq. in.
+above normal for all except Periods 5 and 6, during which times there
+was no air pressure in the tunnels.
+
+All the work will be described in this paper except that under Period 3
+which will be found in another paper.
+
+_Period 1.--Excavation and Iron Lining, June, 1903, to November,
+1906._--Table 23 gives the chief dates in connection with this period.
+
+_Manhattan Shield Chambers._--The Manhattan shield chamber construction
+will be first described. The Weehawken shield chambers have been
+described under the Land Tunnel Section, as they are of the regular
+masonry-lined Land Tunnels type, whereas the Manhattan chambers are of
+segmental iron lining with a concrete inner lining.
+
+During the progress of excavation, the location of the New York shield
+chambers was moved back 133 ft., as previously described in the "Land
+Tunnel" Section, and when the location had been finally decided, there
+was a middle top heading driven all through the length now occupied by
+the shield chamber. Narrow cross-drifts were taken out at right angles
+to the top heading, and from the ends of these the wall-plate headings
+were taken out. Heavy timbering was used, as the rock cover was only
+about 6 ft., and the whole span to be covered was 60 ft. The process
+adopted was to excavate and timber the north side first, place the iron
+lining, and then excavate the south side, using the iron of the north
+side as the supports for the north ends of the segmental timbering of
+the south. The only incident of note was that at 2:00 A.M., on October
+20th, 1904, the rock at the west end of the south wall-plate heading was
+pierced. Water soon flooded the workings, and considerable disturbance
+was caused in the New York Central Railroad yard above. The cavity on
+the surface was soon filled in, but to stop the flow of mud and water
+was quite a troublesome job.
+
+TABLE 22.--QUANTITIES OF WORK IN SUBAQUEOUS TUNNELS.
+
+ ============================+=========================================
+ | TYPE.
+ |----------+--------------+--------------+
+ DESCRIPTION, QUANTITY, |MANHATTAN | CAST IRON, | CAST IRON, |
+ LENGTH, ETC. |shield | ordinary | ordinary |
+ |chambers. | pocketless. | pocket. |
+ ----------------------------+----------+--------------+--------------+
+ Length, in feet. | 59.00| 4,374.99 | 2,146.3 |
+ ----------------------------+----------+--------------+--------------+
+ Excavation, in cubic yards. | | | |
+ Total. | 1,884 | 67,344 | 33,038 |
+ Per linear foot. | 31.9 | 15.4 | 15.4 |
+ Cast-iron tunnel lining, | | | |
+ in pounds. | | | |
+ Total. |847,042 |39,643,120 |19,715,405 |
+ Per linear foot. | 14,357 | 9,061 | 9,186 |
+ Cast-steel tunnel lining, | | | |
+ in pounds. | | | |
+ Total. | | 1,544,962 | 757,938 |
+ Per linear foot. | | 353.1 | 353.1 |
+ Steel bolts and washers, | | | |
+ in pounds. | | | |
+ Total. | 23,627 | 1,475,991 | 724,095 |
+ Per linear foot. | 400.46| 337.37 | 397.00 |
+ Rust joints, in linear feet.| | | |
+ Total. | 3,376 | 170,755 | 83,935 |
+ Per linear foot. | 57.2 | 39.0 | 39.1 |
+ Concrete, in cubic yards. | | | |
+ Total. | 766 | 20,030 | 9,827 |
+ Per linear foot. | 12.98| 4.58 | 4.58 |
+ Steel beams, plates, etc., | | | |
+ in pounds. | | | |
+ Total. | 12,346 | 83,774 | 41,098 |
+ Per linear foot. | 2,092.5 | 19.1 | 19.1 |
+ Steel bolts, hooks, etc., | | | |
+ in pounds. | | | |
+ Total. | 1,328 | 36,980 | 18,142 |
+ Per linear foot. | 22.5 | 84.5 | 84.5 |
+ Expanded metal, in pounds. | | | |
+ Total. | 594 | 2,215 | 1,086 |
+ Per linear foot. | 10.07| 0.506| 0.506|
+ Vitrified conduits, in | | | |
+ duct feet. | | | |
+ Total. | 2,560 | 235,903 | 115,728 |
+ Per linear foot. | 43.49| 53.92 | 53.92 |
+ ============================+==========+==============+==============+
+
+ ============================+==========================================
+ |
+ |--------------+-------------+-------------
+ DESCRIPTION, QUANTITY, | CAST IRON, | CAST STEEL, |
+ LENGTH, ETC. | heavy | ordinary | Total.
+ | pocketless. | pocketless. |
+ ----------------------------+--------------+-------------+-------------
+ Length, in feet. | 5,522.05 | 152.66 |12,255.00 ft.
+ ----------------------------+--------------+-------------+-------------
+ Excavation, in cubic yards. | | |
+ Total. | 85,001 | 2,349 | 189,616
+ Per linear foot. | 15.4 | 15.4 | cu. yd.
+ Cast-iron tunnel lining, | | |
+ in pounds. | | |
+ Total. |61,559,845 | | 121,765,412
+ Per linear foot. | 11,148 | | lb.
+ Cast-steel tunnel lining, | | |
+ in pounds. | | |
+ Total. | 2,730,905 |1,549,711 | 6,583,516
+ Per linear foot. | 494.5 | 10,151.4 | lb.
+ Steel bolts and washers, | | |
+ in pounds. | | |
+ Total. | 2,935,455 | 51,266 | 5,210,434
+ Per linear foot. | 581.59 | 335.82 | lb.
+ Rust joints, in linear feet.| | |
+ Total. | 218,656 | 5,996 | 482,718
+ Per linear foot. | 39.6 | 39.3 | ft.
+ Concrete, in cubic yards. | | |
+ Total. | 25,282 | 713 | 56,618
+ Per linear foot. | 4.58 | 4.58 | cu. yd.
+ Steel beams, plates, etc., | | |
+ in pounds. | | |
+ Total. | 105,738 | 7,432 | 250,388
+ Per linear foot. | 19.1 | 48.7 | lb.
+ Steel bolts, hooks, etc., | | |
+ in pounds. | | |
+ Total. | 46,675 | 1,471 | 104,596
+ Per linear foot. | 84.5 | 96.4 | lb.
+ Expanded metal, in pounds. | | |
+ Total. | 2,795 | 62 | 6,752
+ Per linear foot. | 0.506| 0.406| lb.
+ Vitrified conduits, in | | |
+ duct feet. | | |
+ Total. | 297,752 | 7,757 | 659,700
+ Per linear foot. | 53.92 | 50.81 | duct ft.
+ ============================+==============+=============+============
+
+TABLE 23.--EXCAVATION AND IRON LINING.
+
+ ====================================+================+================|
+ | North | North |
+ | Manhattan. | Weehawken. |
+ ------------------------------------+----------------+----------------|
+ Shaft and preliminary headings. | June 10, '03. | June 11, '03. |
+ Begun. | | |
+ Shaft and preliminary headings. |December 11, '03|September 1, '04|
+ Finished. | | |
+ Excavation of shield chamber. Begun.| May 24, '04. |January 16, '05.|
+ Excavation of shield chamber. |January 21, '05.| March 25, '05. |
+ Finished. | | |
+ Cast-iron lining of shield chambers.|February 4, '05.| None. |
+ Begun. | | |
+ Cast-iron lining of shield chambers.| March 13, '05. | None. |
+ Finished. | | |
+ Excavation of tunnels begun before |October 17, '04.|January 13, '05.|
+ installation of shield. | | |
+ Commenced building falsework for | March 6, '05. | March 23, '05. |
+ shield. | | |
+ Shield parts received at shaft. | March 11, '05. | March 20, '05. |
+ Erection of shield begun. | March 13, '05. | March 27, '05. |
+ Erection of shield (structural | March 27, '05. | April 12, '05. |
+ steel). Finished. | | |
+ Erection of shield (hydraulic | May 11, '05. | May 25, '05. |
+ fittings). Finished. | | |
+ First ring of permanent cast-iron | May 12, '05. | May 29, '05. |
+ lining put in. | | |
+ First air lock bulkhead wall. Begun.| May 29, '05. | June 15, '05. |
+ First air lock bulkhead wall. | June 7, '05. | June 23, '05. |
+ Finished. | | |
+ Air pressure first put in tunnel. | June 25, '05. | June 29, '05. |
+ Rock disappeared from invert of |December 1, '05.|October 31, '05.|
+ tunnel. | | |
+ First pair of bore segments built in|December 9, '05.|January 12, '06.|
+ tunnel. | | |
+ Rip-rap of river bulkhead wall met. |February 8, '06.| None. |
+ First pile met (in river bulkhead |February 18, '06|January 3, '06. |
+ wall at Manhattan, and Fowler | | |
+ warehouse foundation at Weehawken). | | |
+ Last pile met. | March 2, '06. |February 5, '06.|
+ First ring erected on river side of | March 3, '06. |February 6, '06.|
+ shore line. | | |
+ Removing hood of shield. Begun. | March 27, '06. |February 6, '06.|
+ Removing hood of shield. Finished. | April 1, '06. |February 8, '06.|
+ Second air-lock bulkhead wall. | May 12, '06. | March 19, '06. |
+ Begun. | | |
+ Second air-lock bulkhead wall. | May 21, '06. | March 24, '06. |
+ Finished. | | |
+ ------------------------------------+----------------+----------------|
+ Tunnel holed through with meeting | September 12, 1906. |
+ tunnel. | |
+ Last ring of permanent cast-iron | October 9, 1906. |
+ lining built in. | |
+ ====================================+================+================|
+
+ ====================================+================+================|
+ | South | South |
+ | Manhattan. | Weehawken. |
+ ------------------------------------+----------------+----------------|
+ Shaft and preliminary headings. |June 10, '03. |June 11, '03. |
+ Begun. | | |
+ Shaft and preliminary headings. |December 11, |September 1, 04|
+ Finished. |'03. | |
+ Excavation of shield chamber. Begun.|May 24, '04. |January 16, '05.|
+ Excavation of shield chamber. |May 13, '05. |April 19, '05. |
+ Finished. | | |
+ Cast-iron lining of shield chambers.|May 15, '05. |None. |
+ Begun. | | |
+ Cast-iron lining of shield chambers.|June 14, '05. |None. |
+ Finished. | | |
+ Excavation of tunnels begun before |January 5, '05. |January 25, '05.|
+ installation of shield. | | |
+ Commenced building falsework for |June 19, '05. |April 17, '05. |
+ shield. | | |
+ Shield parts received at shaft. |June 22, '05. |April 24, '05. |
+ Erection of shield begun. |June 22, '05. |April 24, '05. |
+ Erection of shield (structural |June 8, '05. |May 6, '05. |
+ steel). Finished. | | |
+ Erection of shield (hydraulic |August 27, '05. |June 13, '05. |
+ fittings). Finished. | | |
+ First ring of permanent cast-iron |August 27, '05. |June 14, '05. |
+ lining put in. | | |
+ First air lock bulkhead wall. Begun.|September 18, |June 21, '05. |
+ |'05 | |
+ First air lock bulkhead wall. |September 23, |July 3, '05. |
+ Finished. |'05 | |
+ Air pressure first put in tunnel. |October 6, '05. |July 8, '05. |
+ Rock disappeared from invert of |February 8, '06.|September 21, 05|
+ tunnel. | | |
+ First pair of bore segments built in|February 16, |December 12, '05|
+ tunnel. |'06. | |
+ Rip-rap of river bulkhead wall met. |April 11, '06. |None. |
+ First pile met (in river bulkhead |April 18, '06. |December 4, '06.|
+ wall at Manhattan, and Fowler | | |
+ warehouse foundation at Weehawken). | | |
+ Last pile met. |May 1, '06. |January 9 '06. |
+ First ring erected on river side of |May 9, '06. |January 19, '06.|
+ shore line. | | |
+ Removing hood of shield. Begun. |May 9, '06. |January 19, '06.|
+ Removing hood of shield. Finished. |May 12, '06. |January 24, '06.|
+ Second air-lock bulkhead wall. |July 13, '06. |March 11, '06. |
+ Begun. | | |
+ Second air-lock bulkhead wall. |July 21, '06. |March 18, '06. |
+ Finished. | | |
+ ------------------------------------+----------------+----------------|
+ Tunnel holed through with meeting | October 9, 1906. |
+ tunnel. | |
+ Last ring of permanent cast-iron | November 18, 1906. |
+ lining built in. | |
+ ====================================+================+================+
+
+The excavation was begun on May 24th, 1904, and finished on May 15th,
+1905. The segments were placed by an erector consisting of a timber boom
+supported by cross-timbers running on car wheels on longitudinal timbers
+at each side of the tunnel. Motion was transmitted to the boom by two
+sets of tackle, and the heavy (5,000-lb.) segments were easily handled.
+The erection of the lining was started on February 4th, 1905, and
+finished on June 14th, 1905.
+
+While the shield chambers were being excavated, bottom headings were run
+along the lines of the river tunnels and continued until the lack of
+rock cover prevented their being driven further. These were afterward
+enlarged to the full section as far as possible. The typical working
+force in the shield chambers was as follows:
+
+ _Ten-hour Shifts._
+
+ _Drilling and Blasting._
+
+ 1 Foreman @ $3.50
+ 6 Drillers " 3.00
+ 6 Drillers' helpers " 2.00
+ 1 Blacksmith " 3.50
+ 1 Blacksmith's helper " 2.25
+ 1 Powderman " 2.00
+ 1 Waterboy " 2.00
+ 1 Nipper " 2.00
+ 1 Machinist " 3.00
+ 1 Machinist's helper " 1.80
+
+ _Mucking._
+
+ 1 or 2 Foremen @ $3.00
+ 16 Muckers " 2.00
+
+[Illustration: PLATE XXXVIII. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVII,
+NO. 1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1. FIG. 2.]
+
+_Erection of Shields._--The tunneling shields have been described in
+some detail in the section of this paper dealing with the contractor's
+plant. They consist essentially of two parts, the structural steelwork
+and the hydraulic fittings. The former was made by the Riter Conley
+Manufacturing Company, of Pittsburg, Pa., and put up by the Terry and
+Tench Company, of New York City; the hydraulic fittings were made and
+put in by the Watson-Stillman Company, of New York City.
+
+On the New York side, the shields were built inside the iron lining of
+the shield chambers, hence no falsework was needed, as the necessary
+hoisting tackle could be slung from the iron lining; at Weehawken,
+however, the erection was done in the bare rock excavation, so that
+timber falsework had to be used. The assembly and riveting took about 2
+weeks for each shield; the riveting was done with pneumatic riveters,
+using compressed air direct from the tunnel supply.
+
+After the structural steel had been finished, the shields, which had
+hitherto been set on the floor of the chambers in order to give room for
+working over the top, were jacked up to grade; this involved lifting a
+weight of 113 tons. While the hydraulic fittings were being put in, the
+shields were moved forward on a cradle, built of concrete with steel
+rails embedded, on which the shield was driven for the length in which
+the tunnel was in solid rock.
+
+The installation of the hydraulic fittings took from 4 to 6 weeks per
+shield. The total weight of each finished shield was about 193 tons. The
+completed shield, as it appeared in the tunnel, is shown by Fig. 1,
+Plate XXXVIII. The typical force working on shield erection was as
+follows:
+
+ _Ten-hour Shifts._
+
+ _Shield Erection._ (_Terry and Tench._)
+
+ 1 Superintendent @ $13.00 per day
+ 4 Foremen " 5.50 " "
+ 1 Timekeeper " 2.50 " "
+ 2 Engineers " 4.50 " "
+ 34 Iron workers " 4.50 " "
+ 7 Laborers " 2.25 " "
+
+ _Hydraulic Work._ (_Watson-Stillman Company._)
+
+ 4 Mechanics @ $4.00 per day
+ _General Labor._ (_O'Rourke Engineering Construction Company._)
+
+ 1 Inspector @ $4.00 per day
+ 1 Foreman " 4.00 " "
+ 8 Laborers " 2.00 " "
+ 1 Engineer " 2.50 " "
+
+After the shield was finished and in position, the first two rings of
+the lining were erected in the tail of the shield. These first rings
+were then firmly braced to the rock and the chamber lining; then the
+shield was shoved ahead by its own jacks, another ring was built, and so
+on.
+
+The description of the actual methods of work in the shield-driven
+tunnels can now be given; this will be divided generally into the
+different kinds of conditions met at the working face, for example, Full
+Face of Rock, Mixed Face, Full Face of Sand and Gravel, Under River
+Bulkhead, and Full Face of Silt.
+
+The last heading is the one under which by far the longest length of
+tunnel was driven, and, as not much has hitherto appeared descriptive of
+the handling of a shield, through this material, considerable space will
+be devoted to it.
+
+_Full Face of Rock._--As was described when dealing with the shield
+chambers, as much as possible of the rock excavation was done before the
+shields were installed. On the New York side, about 146 ft. of tunnel
+was completely excavated, with 71 ft. of bottom headings beyond that,
+and at Weehawken, 58 and 40 ft. of tunnel and heading beyond,
+respectively. This was chiefly done to avoid handling the rock through
+the narrow shield doors. Test holes were driven ahead at short intervals
+to make sure that the rock cover was not being lost, but, nevertheless,
+at Weehawken, on February 14th, 1905, a blast broke through the rock and
+let the mud flow in, filling the tunnel for half its height for a
+distance of 300 ft. from its face.
+
+Throughout the rock section the shield traveled on a cradle of concrete
+in which were embedded either two or three steel rails. In the portion
+in which the whole of the excavation had been taken out, it was only
+necessary to trim off projecting corners of rock. In the portion in
+which only a bottom heading had been driven, the excavation was
+completed just in front of the shield, the drilling below axis level
+being done from the heading itself, and above that from the front
+sliding platforms of the shield. The holes were placed near together and
+drilled short, and very light charges of powder were used, so as to
+lessen the chance of knocking the shield about too much. In this work
+the small shield doors hampered the work greatly, and it might have been
+well to have provided a larger bottom opening which could have been
+subdivided or partly closed when soft ground was met; on the other hand,
+the quantity thus handled was small, owing to the fact that the greater
+part of the rock was excavated before the shields were installed.
+
+The space outside the lining was grouted with a 1:1 mixture of Portland
+cement and sand. Large voids were hand-packed with stone before
+grouting. The details of grouting will be described later.
+
+A typical working gang is given herewith. Two such gangs were worked per
+shield per 24 hours, 10 hours per shift. All this work was done under
+normal air pressure.
+
+ _General:_
+
+ ½ Tunnel superintendent @ $200.00 per month
+ 1 Assistant tunnel superintendent " 5.00 per day
+ 1 General foreman " 5.00 " "
+ ½ Electrician " 3.50 " "
+ ½ Electrician's helper " 3.00 " "
+ ½ Pipefitter " 3.00 " "
+ ½ Pipefitter's helper " 2.75 " "
+
+ _Drilling:_
+
+ 1 Foreman " 5.00 " "
+ 3 Drillers " 4.00 " "
+ 3 Drillers' helpers " 3.00 " "
+ 1 Nipper " 2.50 " "
+ ½ Waterboy " 2.50 " "
+ ½ Powderboy " 2.75 " "
+
+ _Mucking:_
+
+ 1 Foreman " 3.50 " "
+ 8 Muckers " 2.75 " "
+
+ _Erecting Iron and Driving Shield:_
+
+ 1 Erector runner " 4.00 " "
+ 3 Iron workers " 3.00 " "
+
+The duties of such a gang were as follows: The tunnel superintendent
+looked after both shifts of one shield. The assistant or "walking boss"
+had charge of all work in the tunnel on one shift. The general foreman
+had charge of the labor at the face. The electricians looked after
+repairs, extensions of the cables, and lamp renewals. The pipefitters
+worked in both tunnels repairing leaks in pipes between the power-house
+and the working faces, extending the pipe lines, and attending to shield
+repairs, and in the latter work the erector runner helped.
+
+The drillers stuck to their own jobs, which were not subject to
+interruption as long as the bottom headings lasted. One waterboy and one
+powderboy served two tunnels. The muckers helped the iron men put up the
+rings of lining, as well as doing their own work. The iron men tightened
+bolts, whenever not actually building up iron. The list does not include
+the transportation gang, which will be described under its own heading.
+
+The rate of progress attained was 4.2 ft. per day per shield where most
+of the excavation had been done before, and 2.1 ft. where none had been
+done before.
+
+When the shields had got far enough away from the shield chamber, and
+before rock cover was lost, the first air-lock bulkhead walls were put
+in.
+
+_Air-Lock Bulkhead Walls._--The specifications required these walls and
+all their fittings to be strong enough to stand a pressure of 50 lb. per
+sq. in. Accordingly, all the walls were of concrete, 10 ft. in
+thickness, except the first two, which were 8 ft. in thickness, and
+grouted up tight.
+
+There were three locks in each bulkhead wall capable of holding men,
+namely, the top or emergency lock which is set high in order to afford a
+safe means of getting away in case of a flood; this lock was used
+continuously for producing the lines and levels into the tunnels. It was
+very small and cramped for this purpose, and a larger one would have
+been better, both for lines and emergencies. This lock was directly
+connected with the overhead platform (also called for in the
+specifications) which ran the whole length of the tunnels. Side by side,
+on the level of the lower or working platform of the tunnel, were the
+man lock and the muck lock. In addition a number of pipes were built in
+to give access to the cables and for passing pipes, rails, etc., in and
+out.
+
+After each tunnel was about 1,200 ft. ahead of the first walls, a second
+wall was built just like the first, and no others were put in, so that
+altogether there were eight walls. This second wall not only gave an
+added safeguard to the tunnel but enabled the air pressure at the
+working face to be divided between the two walls, and this compression
+or decompression in stages, separated by a spell of walking exercise,
+was found to be very good for the health of those working in the air.
+
+_Mixed Face._--When the rock cover became so thin that it was risky to
+go on without the air pressure, the air pressure was turned on, starting
+with from 12 to 18 lb., which was enough to stop the water from the
+gravel on top of the rock. At first, when the surface of the rock was
+penetrated, the soft face was held up by horizontal boards braced from
+the shield until the shield was shoved. The braces were then taken out
+and, as soon as the shield had been shoved, were replaced by others. As
+the amount of soft ground in the face increased, the system of timbering
+was gradually changed to one of 2-in. poling boards resting on top of
+the shield and supported at the face by vertical breast boards, in turn
+held by 6 by 6-in. walings braced both through the upper doors to the
+iron lining and from the sliding platforms of the shield. The latter
+were in their forward position before the shield was shoved, the
+pressure being turned off and the exhaust valves opened just before the
+shove began. As the shield went ahead, the platform jacks gradually
+exhausted and thus held enough pressure on the face to keep it up. Fig.
+17 is a sketch of this method. In driving through mixed ground a typical
+working gang was about as follows:
+
+ _General:_
+
+ 1/3 Tunnel superintendent @ $300.00 per month
+ 1 Assistant tunnel superintendent " 5.00 per day
+ 1 General foreman " 5.00 " "
+ ½ Electrician " 3.50 " "
+ ½ Electrician's helper " 3.00 " "
+ ½ Pipefitter " 3.25 " "
+ ½ Pipefitter's helper " 3.00 " "
+
+ _Drilling:_
+
+ 1 Foreman " 5.00 " "
+ 2 Drillers " 3.25 " "
+ 2 Drillers' helpers " 3.00 " "
+
+ _Timbering:_
+
+ 2 Timbermen @ $2.50 per day
+ 2 Timbermen's helpers " 2.00 " "
+
+ _Mucking:_
+
+ 1 Foreman " 3.50 " "
+ 6 Muckers " 2.75 " "
+
+ _Erecting Iron and Driving Shield:_
+
+ 1 Erector runner " 3.25 " "
+ 3 Iron workers " 3.00 " "
+
+The average rate of progress was 2.6 ft. per day.
+
+In this case there were three such gangs, each on an 8-hour shift.
+
+_Full Face of Sand and Gravel._--This condition of affairs was only met
+at Weehawken. Two systems of timbering were used. In the first system,
+Fig. 17, the ground was excavated 2 ft. 6 in. ahead of the cutting edge,
+the roof being held by longitudinal poling boards, resting on the
+outside of the skin at their back end and on vertical breast boards at
+the forward end. When the upper part of the face was dry, it was held by
+vertical breast boards braced from the sliding platform and through the
+shield doors to cross-timbers in the tunnel; the lower part, which was
+always wet, was held by horizontal breast boards braced through the
+lower shield pockets to cross-timbers in the tunnel. This system worked
+all right as long as the ground in the top was sandy enough and had
+sufficient cohesion to allow the polings to be put in, but, when the
+upper part was in gravel, thus making it impossible to put in the
+longitudinal polings or the vertical breasting, the second system came
+in. Here the excavation was only carried 1 ft. 3 in. (half a shove)
+ahead of the cutting edge, and the longitudinal polings were replaced by
+transverse boards supported by pipes which were placed in the holes
+provided in the shield to accommodate some telescopic poling struts
+which had been designed but not made. These pipes acted as cantilevers,
+and were in two parts, a 2½-in. pipe wedged tight into the holes and
+smaller pipes sliding inside them. After a small section of the ground
+had been excavated, a board was placed against it, one of the pipes was
+drawn out under it, and wedges were driven between it and the board.
+These polings were kept below the level of the hood, so that when the
+shield was shoved they would come inside of it; in addition, they were
+braced with vertical posts from the sliding platforms. The upper part of
+the face was held by longitudinal breast boards braced from the sliding
+platform by vertical "soldier" pieces. The lower part of the face was
+supported by vertical sheet-piling braced to the tunnel through the
+lower doors. Sometimes two rows of piling were used, but generally one,
+as shown in Fig. 17. Notwithstanding the fact that the breasting was
+only 1 ft. 3 in. ahead of the hood, the shield was moved its full stroke
+of 2 ft. 6 in., the ground around the cutting edge of the hood being
+scraped away by men working bars in the place from which the temporary
+breast boards at the circumference had been removed. The back pressure
+on the sliding platform jacks, when the exhaust valves were only partly
+open, offered a good deal of resistance, and held the face as long as
+the movement of the shield was continuous.
+
+[Illustration: METHOD OF TIMBERING FACE IN MIXED GROUND METHOD OF
+TIMBERING FACE IN SAND METHOD OF TIMBERING FACE IN SAND AND GRAVEL FIG.
+17.]
+
+On one occasion, when for some reason the shield was stopped with the
+shove only partly done, and the exhaust valves had not been shut off,
+the platforms continued to slide and allowed the face to collapse; the
+shield platforms and doorways, however, caught the falling sand and
+gravel and the flow choked itself.
+
+As soon as the rock surface was penetrated and the sand and gravel were
+met, which happened almost at the same time in the two Weehawken
+Tunnels, the escape of air increased enormously, and it at once became
+clear that it was impossible to keep enough air in the two tunnels by
+the methods then in use, even when working the three compressors, each
+capable of compressing 4,400 cu. ft. of free air per min. at top speed.
+When the shields just entered the sand and gravel, the face had been
+held by light breasting, without any special effort to prevent the
+escape of air, but when it was found impossible to supply enough air, a
+large amount of straw and clay was used in front of the boards.
+
+This cut down the escape, but, as much air was escaping through the
+joints of the iron lining, these were plastered with Portland cement.
+Even then, the loss was too great, therefore one tunnel was shut down
+entirely and all the air was sent to the other. This allowed a pressure
+of 10 lb. to be kept up in the working tunnel, and this, though less
+than the head, was enough to allow progress to be made. In order to use
+one tunnel as a drain for the other, the two faces were always kept
+within 150 ft. of each other by working them alternately. The timbered
+face was never grouted, though this would have reduced the loss of air,
+as at the same time it would have decreased the progress very much, and
+any one who saw the racing engines in the power-house, and realized
+that a breakdown of one of them would mean the loss of the faces, was
+ready to admit that the quicker this particular period was cut short,
+the better.
+
+Above the sand and gravel lay the silt, and, when it showed in the roof,
+the escape of air was immediately reduced and the two faces could be
+worked simultaneously. Almost at the same time the piles supporting the
+large warehouse, known as the Fowler Building, were met. Although the
+face now took much less timber, the same system of breast boards as had
+been used in the gravel was kept up, but in skeleton form. They were set
+2 ft. 6 in. ahead of the shield, however, instead of 1 ft. 3 in., and
+the transverse roof poling boards were replaced by longitudinals resting
+on the shield. The more piles in the face the less timbering was done.
+The piles were cut into handy lengths with axes and chisels.
+
+All timbering was light compared with the weight of the ground, but, as
+the shove took place as soon as the set was made, it served its purpose.
+When a face was closed down the whole system was greatly reinforced by
+braces from the shield, the face of which was closed by the doors.
+
+In driving through such a face the typical 8-hour shift gang was about
+as follows:
+
+ _General:_
+
+ 1/3 Tunnel superintendent @ $300.00 per month.
+ 1 Assistant tunnel superintendent " 5.00 per day.
+ 1 General foreman " 5.00 " "
+ ½ Pipefitter " 3.25 " "
+ ½ Pipefitter's helper " 2.75 " "
+ ½ Electrician " 3.00 " "
+ ½ Electrician's helper " 2.75 " "
+
+ _Timbering:_
+
+ 3 Timbermen " 2.50 " "
+ 3 Timbermen's helpers " 2.00 " "
+
+ _Mucking:_
+
+ 1 Foreman " 3.50 " "
+ 6 Muckers " 2.75 " "
+
+ _Erecting Iron and Driving Shield:_
+
+ 1 Erector runner " 3.25 " "
+ 1 Foreman " 4.00 " "
+ 4 Iron workers " 3.00 " "
+
+The drillers were not kept on after the rock disappeared; a foreman was
+added who divided his time between iron erection and mucking.
+
+The average rate of progress in sand and gravel without piles was 5.1
+ft. per day per shield. When piles and silt were met in the upper part
+of the face, the speed increased to 7.0 ft. per day.
+
+_Passing Under River Bulkhead._--At Weehawken no trouble was found in
+passing under the river wall, as the bulkhead consisted of only cribwork
+supported on silt, and, though the piles obstructed the motion of the
+shield, they were easily cut out, and the cribwork itself was well above
+the top of the shield.
+
+On the New York side, however, conditions were not nearly as good. The
+heavy masonry bulkhead was supported on piles and rip-rap, as shown in
+Fig. 18. The line of the top of the shield was about 6 ft. above the
+bottom of the rip-rap, the spaces between the stones of which were quite
+open and allowed a free flow of water directly from the river. As soon,
+therefore, as the cutting edge of the shield entered the rip-rap there
+was a blow, the air escaping freely to the ground surface behind the
+bulkhead and to the river in front of it. Clay puddle, or mud made from
+the excavated silt, was used in large quantities to plug up the
+interstices between the stone in the working face, the air pressure
+being slightly greater than that needed to keep out the water holding it
+in place. The excavation of the rip-rap was a tedious affair, for it had
+to be removed one stone at a time and the spaces between the newly
+exposed stones plugged with mud immediately. One man stood ready with
+the mud while another loosened the stones with a bar. When the shield
+had advanced its own length in the rip-rap, another point for the escape
+of the air was exposed at the rear end of the shield. This loss was
+closed at the leading end of the last ring with mud and cement sacks.
+
+[Illustration: SKETCH SHOWING RIVER TUNNELS PASSING UNDER RIVER BULKHEAD
+WALL AT MANHATTAN CROSS-SECTION OF RIVER BULKHEAD WALL ON AXIS OF NORTH
+TUNNEL PLAN SHOWING PILES REMOVED TO ALLOW PASSAGE OF SHIELD FIG. 18.]
+
+As long as the shield was stationary it was possible, by using these
+methods and exercising great care and watchfulness, to prevent excessive
+loss of air; but, while the shield was being shoved ahead, the
+difficulties were much increased, for the movement of the shield
+displaced the bags and mud as fast as they were placed, and it was only
+by shoving slowly and having a large number of men looking out for leaks
+and stopping them up the instant they developed that excessive loss of
+air could be prevented. In erecting the iron lining, as each segment was
+brought into position, it was necessary to clean off the leading
+surface of the previous ring and the adjacent portion of the tail of the
+shield; this was always accompanied by a slight "blow," and for some
+time the air pressure in the tunnel dropped from 25 to 20 lb., that is,
+from greater than the balancing pressure to less, every time a segment
+was placed, and on two occasions the "blow" became so great that the
+tunnel pressure was reduced considerably further, and in consequence the
+water from the river rushed in and was not stopped until it had risen
+about 4 ft. in the tunnel invert. On such occasions the surface of the
+river was greatly disturbed, rising more than 20 ft. in the air in a
+sort of geyser. A large quantity of grout (about 2,500 bbl. of cement
+and a similar quantity of sand in the North Tunnel and 1,000 bbl. in the
+South Tunnel) was used at this point; it was forced through the tunnel
+lining immediately behind the shield, greatly reducing the loss of air
+and helping to bind the rip-rap together.
+
+When the shield had traveled 25 ft. through the rip-rap, the piles which
+support the bulkhead were met. One hundred of these which were spaced at
+3-ft. centers in each direction, were cut out of the path of each shield
+in a distance of 35 ft. The presence of the piles caused considerable
+extra labor, as each pile had to be cut into several pieces with axes to
+enable it to be removed through the shield doors, otherwise they
+presented no difficulties. It was not necessary to timber the face, as
+the piles supported it most effectively.
+
+When the river line had been passed, the "blow" still continued, and as
+there was no heavy ground above the tunnel the light silt was carried
+away into the water by the escaping air. At one time the cover over the
+crown of the tunnel was reduced to such an extent that for a distance of
+30 ft. there was less than 10 ft. of very soft silt, and in some places
+none at all. Therefore, the shield was stopped and the air pressure
+reduced until it was less than the balancing pressure; the blow then
+ceased, and about 28,000 cement bags filled with mud were dumped into
+the hole (the location made it impossible to dump them _en masse_ from a
+scow). They were then weighted down with rip-rap. This sealed the blow,
+and the work was continued without any further disturbance from this
+source. Just before the blow reached its maximum it was found that two
+of the piles which had been encountered were directly in the path of one
+of the proposed screw-piles. It was therefore decided to pull these,
+and this was done with two 40-ton hydraulic jacks supported by the upper
+sliding platforms and acting on a horizontal timber which was connected
+to the piles by tie-rods and chains. The working force here was similar
+to that employed in the sand and gravel section previously described.
+
+_In Full Face of Silt._--A full face of silt was first met under the New
+York Central Railroad freight yard on the New York side. Up to this
+point the ground passed through had been either solid rock or a mixed
+face of rock and gravel. In both of these the full excavation had to be
+taken out before the shield could be shoved, and the soft ground had
+needed timbering. When the rock, gravel, and hardpan gave place to a
+full face of silt, the timber was removed, all the shield doors were
+opened, and the shield was shoved into the ground without any excavation
+being done by hand ahead of the diaphragm. As the shield advanced, the
+silt was forced through the open doors into the tunnel. After the work
+had gone on in this way for some time, taking in about 90% of the full
+volume of the tunnel excavation per foot forward, the air pressure was
+raised from 20 to 22 lb. The result was that the silt in the face got
+harder and flowed less readily through the shield, and the amount taken
+in fell to about 65% of the full volume. This manner of shoving at once
+caused a disturbance on the surface and the railroad tracks above the
+tunnel were raised, so that the pressure was lowered to 16 lb., then the
+muck got softer and the full volume of excavation was taken in; after a
+while the pressure was again raised to 20 lb.
+
+The forcing of the shield through the silt resulted in a rising of the
+bed of the river, the amount that the bed was raised depending on the
+quantity of material brought into the shield.
+
+If the whole volume of excavation was being brought in, the surface of
+the bed was not affected; when about 50% was being taken in, the surface
+was raised about 3 ft.; if the shield was being driven blind, the bed
+was raised about 7 ft.
+
+The number of open doors was regulated so as to take in the minimum
+quantity of muck consistent with causing no surface disturbance. On the
+average, in the North Manhattan Tunnel, all the doors were open, but in
+the South Tunnel there were generally only five or six out of the total
+nine.
+
+In front of the bulkhead wall at Manhattan the tunnels were under Pier
+No. 72. This structure was supported on wooden piles, some 80 ft. or
+more in length, which came down below the tunnel invert. The piles which
+lay directly in the path of the tunnels, with a few exceptions, had been
+pulled. In driving the tunnels through this section, great care had to
+be taken not to disturb the piles on either side of the tunnels, as they
+supported a heavy trestle used in disposing of the excavation from the
+open cut in the terminal yard. To avoid such disturbance, a large
+portion of the total excavation had to be taken through the shields.
+
+The first shield which passed the river bulkhead was the south one at
+Weehawken. As soon as this line was crossed the silt was found to be
+much softer than behind the wall, in fact it was like a fluid in many of
+its properties. The fluidity could be changed by varying the tunnel air
+pressure; for example, when the air pressure was made equal to the
+weight of the overlying material (water and silt), the silt was quite
+stiff, and resembled a rather soft clay; but when the air pressure was
+from 10 to 15 lb. per sq. in. lower, it became so liquid that it would
+flow through a 1½-in. grout hole in the lining, in a thick stream, at
+the rate of from 10 to 50 gal. per min. as soon as the plug was taken
+out. This was the point to which the contractor had long looked forward,
+as he expected to be able to close all his shield doors and drive the
+rest of the way across without taking in a shovelful of muck, as had
+just been done under the Hudson River, on the South Tunnel of the Hudson
+and Manhattan Railroad Company's Tunnels between Morton Street, New York
+City, and Hoboken, N. J. The doors were shut and the shield was shoved;
+the tunnel at once began to rise rapidly, notwithstanding that the
+heaviest possible downward leads that the clearance between the iron and
+the shield would allow were put on. At the same time, the pressures
+induced in the silt by the shield shouldering the ground aside caused
+the iron lining to rise about 2 in. as soon as the shield left it, and
+also distorted it, the horizontal diameter decreasing and the vertical
+diameter increasing by about as much as 1¼ in. An anxious discussion
+followed these phenomena, as the effects had been so utterly unexpected,
+and a good many different theories were advanced as to the probable
+cause. It was thought that the hood of the shield might have something
+to do with the trouble. The shield was stopped, the hood removed, the
+doors were shut, and the driving continued. The same trouble was found,
+and it was impossible to keep to grade. Work was stopped, and the
+question was thoroughly debated; finally, on January 31st, 1906, the
+chief engineer directed that one of the shield doors be opened as an
+experiment and 50% of the excavation taken in.
+
+The effect was instantaneous, the shield began to come down to grade at
+once, and it soon became necessary to close the door partially and
+reduce the quantity of muck taken in in order to prevent the tunnel from
+getting below grade. The other troubles from distortion, etc., ceased at
+the same time.
+
+It was soon found that a powerful aid in the guidance of the shield was
+thus brought to hand, for, if high, the shield could be brought down by
+increasing the quantity of muck taken in, if low, by decreasing it. From
+this time forward, the quantity of muck taken in at each shove was
+carefully regulated according to the position of the tunnel with regard
+to grade and the nature of the ground. The quantity varied from nothing
+to the full volume displaced by the tunnel, and averaged 33% of the
+latter.
+
+To regulate the flow, the bottom middle door was fitted with two steel
+angles behind which were placed 6 by 6-in. timbers. In this way the
+opening could be entirely closed or one of any size left. The muck
+flowed into the tunnel in a thick stream, as shown in Fig. 2, Plate
+XXXV, and, by regulating the rate of shove it could be made to flow just
+as fast as it could be loaded into cars.
+
+In driving through the silt, the typical gang per shift of 8 hours per
+shield was as follows:
+
+ _General:_
+
+ 1/3 Tunnel superintendent @ $300 per month
+ 1 Assistant tunnel superintendent " 6.00 per day
+ 1 General foreman " 5.00 " "
+ ½ Electrician " 3.50 " "
+ ½ Electrician's helper " 3.00 " "
+ 1 Foreman " 4.00 " "
+ 2 Pipefitters " 3.50 " "
+ 2 Pipefitters' helpers " 3.25 " "
+
+ _Mucking:_
+
+ 1 Foreman " 4.00 " "
+ 6 Muckers " 3.00 " "
+
+ _Erecting Iron and Driving Shield:_
+
+ 1 Foreman @ $4.00 per day
+ 1 Erector runner " 3.50 " "
+ 4 Iron workers " 3.00 " "
+ 3 Laborers " 3.00 " "
+
+Three such shifts were worked per day, and the air pressure averaged 25
+lb. per sq. in.
+
+The increase in the number of pipefitters was due to the greatly
+increased speed, and also the steadily increasing length of completed
+tunnel. The three laborers in the erection gang spent their whole time
+tightening bolts. The rate of progress in the silt under the river per
+ring of 2½ ft. was 3 hours 21 min., exclusive of all time when work
+was actually suspended. For a considerable part of the time only two
+8-hour shifts were worked, owing to a shortage of iron caused by the
+change in the design of the lining, whereby the original lining was
+changed to a heavier one, and, as the work was also stopped for
+experiments and observations, the average of the actual total time,
+including all the time during which work was suspended, was 5 hours 32
+min. per ring, or 10.8 ft. per day.
+
+The junction of the shields under the river was made as follows: When
+the two shields of one tunnel, which had been driven from opposite sides
+of the river approached within 10 ft. of each other, the shields were
+stopped, a 10-in. pipe was driven between them, and a final check of
+lines and levels was made through the pipe. Incidentally, also, the
+first through traffic was established by passing a box of cigars through
+the pipe from the Manhattan shield to that from Weehawken. One shield
+was then started up with all doors closed while the doors on the
+stationary shield were opened so that the muck driven ahead by the
+moving shield was taken in through the other one's doors. This was
+continued until the cutting edges came together. All doors in both
+shields were then opened and the shield mucked out. The cutting edges
+were taken off, and the shields moved together again, edge of skin to
+edge of skin. The removal of the cutting edge necessitated the raising
+of the pressure to 37 lb. As the sections of the cutting edges were
+taken off, the space between the skin edges was poled with 3-in. stuff.
+Fig. 1, Plate XXXIX, is a view of the shields of the North Tunnel after
+being brought together and after parts of the interior frames had been
+removed. When everything except the skins had been removed, iron lining
+was built up inside the skins, the gap at the junction was filled with
+concrete, and long bolts were used from ring to ring on the
+circumferential joint. Finally, the rings inside the shield skins were
+grouted.
+
+[Illustration: Plate XXXIX. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1. FIG. 2.]
+
+In order to make clear the nature of the work done in building these
+shield-driven tunnels in silt, a short description will be attempted,
+this description falling into three main divisions, namely, Shoving the
+Shield, Pushing Back the Jacks, and Erecting the Iron Lining.
+
+_Shoving the Shield._--This part of the work is naturally very
+important, as the position of the shield determines within pretty narrow
+limits the position of the iron built within it, hence the shield during
+its forward movement has to be guided very carefully. On this work
+certain instructions were issued for the guidance of the foreman in
+charge of the shield. These instructions were based on results of
+"checks" of the shield and iron's position by the engineering corps of
+the Company, and comprised, in the main, two requirements, namely, the
+leads that were to be got, and the quantity of muck to be taken in. The
+"lead" is the amount that the shield must be advanced further from the
+iron, on one side or the other, or on the top or bottom, as measured
+from the front face of the last ring of iron lining to the diaphragm of
+the shield. These leads are not necessarily true leads from a line at
+right angles to the center line, as the iron may have, and in fact
+usually does have, a lead of its own which is known and allowed for when
+issuing the requirements for the shove.
+
+The foreman, knowing what was wanted, arranged the combination of shield
+jacks which would give the required leads and the amount of opening on
+the shield door which would give the required amount of muck. To see how
+the shield was going ahead, a man was stationed at each side at axis
+level and another in the crown. Each man had a graduated rod on which
+the marks were so distinct that they could be read by anyone standing on
+the lower platform. These rods were held against the shield diaphragm,
+and, as it advanced, its distance from the leading end of the last ring
+could be seen by the man in control of the jack valves. If he found that
+he was not getting the required leads, he could change the combination
+of jacks in action. As the time of a shove was often less than 10 min.,
+the man had to be very quick in reading the rods and changing the jacks.
+If it was found that extensive change in the jack arrangement was
+wanted, the shove could be stopped by a man stationed at the main
+hydraulic control valve; but, as any such stoppage affected the quantity
+of muck taken in, it was not resorted to unless absolutely necessary.
+
+If the quantity of muck coming in was not as desired, a stop had to be
+made to alter the size of the opening, and if, while this was being
+done, the exhaust valves were not closed quite tight, the silt pressure
+on the face of the shield would force it back against the iron. This
+fact was sometimes taken advantage of when a full opening did not let in
+the desired quantity, for the shield could be shoved, allowed to return,
+and shoved again.
+
+The time taken to shove in silt varied greatly with the quantity of
+material taken in; for shoving and mucking combined, it averaged 66
+min., with an average of 13 cu. yd. of muck disposed of, or about 5 min.
+per cu. yd. of material.
+
+_Pushing Back the Jacks._--This was a simple matter, and merely
+consisted in making the loose push-back connection to each jack as it
+had to be sent back. Some of the jacks became strained and bent, and had
+to be taken out and replaced. Where there was silt pressure against the
+face of the shield, the hydraulic pressure had to be kept on until the
+ring was erected. In such cases, only two or three jacks could be pushed
+back at a time, and only after a segment had been set in position, and
+the pressure taken on it, could the next jack be pushed back, and so on
+around the ring. The time between the finish of the shove (hydraulic
+pressure turned off) and the placing of the first segment, was occupied
+in pushing back the bottom jacks and cleaning dirt off the tail of the
+shield, and averaged about 14 min.
+
+_Erecting the Iron Lining._--As soon as the shove was over, the whole
+force, when in silt, set to work at building up the iron and then
+tightening the bolts so that the shield could be shoved again. A section
+of the tunnel with bolting and working platform is shown on Plate XL.
+
+In the early part of the work, when the ground was being excavated ahead
+of the shield, the whole force, with the exception of those working in
+front of the shield, was engaged in erecting the iron, but, as soon as
+this was done, most of the men returned to the mucking, and only the
+iron workers continued to tighten up bolts. On the other sections, where
+the shield was shoved into the silt without excavating ahead, as soon as
+the shove was completed, the whole force was engaged in the erection of
+the iron and the tightening of the bolts, until they were so tight that
+the shield could be shoved again for another ring.
+
+The iron was brought into the tunnel on flat cars, two segments to the
+car, and was lifted from the car and lowered into the invert of the
+shield by a block and fall and chain sling, as shown in Fig. 2, Plate
+XXXIX. The bottom three or four segments were pushed around into
+position with the erector, the head simply bearing against the
+longitudinal flange without being attached to the segment; the upper
+segments, however, were, as shown in Fig. 2, Plate XXXVIII, and Fig. 1,
+Plate XLI, attached to the erector, by using the expanding bar and the
+erector head designed by Mr. Patrick Fitzgerald, the Tunnel
+Superintendent. This was found to be a most convenient arrangement.
+
+The single erector attached to the center of the shield was able to
+erect the iron as fast as it could be brought into the tunnel, and even
+when the weight of the segments was increased 25% (from 2,060 to 2,580
+lb.) it always proved equal to its task, although occasionally one of
+the chains in the mechanism broke and delayed the work for an hour or
+so; but the sum of all the delays from this cause and from breaks and
+leaks in the hydraulic line only averaged 13 min. per ring. The
+operating valve which was first used was a four-spindle turning valve,
+but this was replaced by a sliding valve which was found to be much more
+satisfactory, both in ease of operation and freedom from failure.
+
+As the iron was put into place, two of the middle bolts in each
+longitudinal flange and two in each circumferential one were pulled as
+tight as possible, and the others put in loosely; then, as soon as the
+ring was in position, as large a force as could be conveniently worked
+at one time was engaged in tightening the bolts. The shape of the tunnel
+depended on the thoroughness of the tightening of the bolts, and the
+shield was never shoved until the bolts in all the longitudinal flanges
+had been thoroughly tightened. In addition, all the bolts in the
+circumferential flanges below the axis were tightened, and at least
+three of the six in each segment above. After the shield had been shoved
+ahead, the bolts were found to have slackened, and, where the daily
+progress was four rings, or more, it was necessary to have a small gang
+of men always at this work.
+
+In order to get at the bolts, special platforms were necessary, and
+throughout the greater part of the work, a traveling platform was used.
+This enabled the men to reach handily all parts of the seven leading
+rings. This platform was supported and moved forward on wheels fixed on
+brackets to the tunnel, and was pulled forward by connecting chains
+every time the shield was shoved. In the early part of the work it was
+not possible to use platforms, because, in order to maintain the correct
+circular shape of the iron lining, it was necessary to put in temporary
+horizontal turnbuckles at axis level. These, however, were very
+convenient for supporting the planks which were used as a temporary
+bolting platform for the sides of the tunnel, and a temporary platform
+resting on 6 by 6-in. timbers across the tunnel enabled the bolts in the
+crown of the tunnel to be reached, while the 6 by 6-in. timbers were
+left in to support the emergency platform previously described (Plate
+XL), which extended the entire length of the tunnel.
+
+The time taken to erect the iron lining became shorter and shorter as
+the tunnel organization became more perfect and the force better
+trained, so that, whereas, in the early part of the work, it frequently
+took 6 hours to erect a ring, in the latter part, when the work was
+nearing completion, it was a common occurrence to erect a ring in 30
+min. The average time in the "heavy iron" section, which included the
+greater part of the work under the river, was 1 hour 4 min. for the
+erection of the ring and 40 min. for tightening the bolts after that had
+been completed, so that the total time spent by the whole gang on
+erection and bolting averaged 1 hour 44 min. per ring, exclusive of the
+time spent by the small gang which was always engaged in tightening the
+bolts. The average time spent in erecting and bolting, for the whole
+length of the tube tunnels, was 2 hours 15 min. per ring.
+
+_Tables of Progress._--Tables 24, 25, 26, and 27 have been prepared to
+show the time taken in the various operations at each working face.
+
+[Illustration: PLATE XLI. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1.]
+
+[Illustration: PLATE XLI. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 2.]
+
+In Tables 24, 25, 26, and 27, the following symbols are used:
+
+ _A_--Including assistant superintendents, foremen, and
+ electricians, in driving the shield, erecting iron, mucking,
+ attending to the electric lights, and repairing the pipe line.
+
+ _B_--Drillers, drillers' helpers, drill foremen, and nippers.
+
+ _C_--All men grouting.
+
+ _D_--Engineers and laborers wholly employed on transport between the
+ first lock and the face.
+
+ _E_--In rock, one car = 0.60 cu. yd.; in sand or silt = 1.20 cu. yd.
+ in place.
+
+ _F_--Time between completion of mucking and putting in first plate,
+ spent in shoving the jacks back.
+
+ _G_--In ordinary iron = the whole time spent on erection and
+ bolting. In heavy iron = the time between putting in the first
+ plate and placing the key only.
+
+ _H_--Time between placing the key and starting the next shove, spent
+ by the whole gang in tightening bolts. In addition to this,
+ there was a small gang which spent its whole time at this work.
+
+ _I_--In Table 24 the first pair of bore segments is at ring 207-208.
+ " " 25 " " " " " " " " " 201-202.
+ " " 26 " " " " " " " " " 185-186.
+ " " 27 " " " " " " " " " 171-172.
+
+ Outside diameter of tunnel = 23 ft. 0 in.
+ Inside " " " = 21 ft. 2 in.
+ Length of ring = 2 ft. 6 in.
+
+In the "Ordinary Iron" section the time is divided between mucking
+(which included the shoving and pushing back of the jacks) and the
+erection time (which included the time spent by the whole gang in
+tightening bolts). In the "Heavy Iron" section these times are all
+separated into "Mucking," "Pushing Back Jacks," "Erecting," and
+"Bolting," and here the bolting time included only that spent on bolts
+by the whole gang; in addition, there was a small gang engaged solely in
+tightening bolts. The lost time is the average time lost due to the
+break-down of hydraulic pipe lines, damaged jacks, and broken erector
+chains. The erection time is separated for the various kinds of rings,
+that is, straight ordinary rings, rings containing No. 1 bore segments,
+rings containing No. 2 bore segments, and taper rings, and it will be
+seen that, on the average, taper rings took 22 min. (or 24%) more time
+to erect and to bolt than ordinary ones, and that rings containing No. 2
+bore segments took 14 min. (or 15%) more.
+
+TABLE 24.--SHIELD-DRIVEN TUNNEL WORK, MANHATTAN SHAFT, RIVER TUNNEL
+NORTH. Table showing the size of the gang, the amount of excavation, and
+the time per ring taken for the various operations involved in building
+tunnel through the several kinds of ground encountered; also the extent
+and nature of all the unavoidable delays.
+
+ TABLE 24 PART 1
+
+ =+===========+=======+=============+===+=============+=====+===+==+==|
+ W| | | AVE. NO. |
+ e| | | OF MEN |
+ i| | DESCRIPTION | IN GANG |
+ g| |-------+-------------+---+-------------+--+--+---+--+--|
+ h| | | |Ave| | | | |A | |
+ t| | | |air| | |D |G |i | |
+ | | | | | | |r |r |r | |
+ o| | | |P | |S |i |o | | |
+ f| | | |r | |h |l |u |t |T |
+ | | | |e | |i |l |t |r |o |
+ | | | |s | |e |i |i |a |t |
+ i| | | |s | |l |n |n |n |a |
+ r| Section | | |u | |d |g |g |s |l |
+ o| between | Length| |r |Method of |--+--+---+--| |
+ n| rings |in feet|Material |e |Excavation |A |B |C |D | |
+ -+-----------+-------+-------------+---|-------------+--+--+---+--+--|
+ | 1-54 | 135.0|Rock | |[P] | | | | |14|
+ | 55-80 | 65.0| " |19 |[P] |24| 7|1/3| 1|32|
+ | 81-107 | 65.0|Soft rock |18 |[P] |22| 5| | 2|29|
+ O| 108-153 | 117.5|Rock |14 |[P] |17|11| | 2|30|
+ r| 154-194 | 102.5|Rock and |14 |[P] |23| 6| | 2|31|
+ d| | |earth | | | | | | |
+ i| 195-215 | 52.5|Silt |19 |[P]Breasting |28| | | 2|30|
+ n| 216-393 | 445.0| " |20 |[Q]8 doors |27| | | 4|31|
+ a| 394-429 | 90.0|Silt, piles, |24 |[C]Breasting |28| | | 4|32|
+ r| | |rip-rap | | | | | | |
+ y| 430-509 | 200.0|Silt |23 |[Q]1 door |24| | | 3|27|
+ | 510-692 | 457.5| " |23 |[Q]3 doors |26| | | 4|30|
+ | 55-692 |1,593.0| |20 | |25| 2| | 3|30|
+ | 216-692 |1,192.5| |22 | |26| | | 4|30|
+ -+-----------+-------+-------------+---+-------------+--+--+---+--+--|
+ | 693-954 | 655.0|Silt |24 |[Q]1 door |28| | | 6|34|
+ | 955-1,014 | 150.0| " |24 |[Q]1 " |28| | | 8|36|
+ |1,015-1,074| 150.0| " |24 |[Q]1 " |25| | | 8|33|
+ H|1,075-1,134| 150.0| " |24 |[Q]1 " |27| | | 9|36|
+ e|1,135-1,194| 150.0| " |25 |[Q]1 " |26| | | 8|34|
+ a|1,195-1,224| 75.0| " |25 |[Q]1 " |24| | | 9|33|
+ v|1,225-1,262| 95.0| " |25 |[Q]1 " |23| | | 9|32|
+ y|1,263-1,277| 37.5| " |25 |[Q]1 " |24| | |10|34|
+ |1,278-1,307| 75.0| " |25 |[Q]1 " |21| | |10|31|
+ |1,308-1,326| 47.5| " |28 |[Q]1 " |27| | |11|38|
+ | 955-1,326| 930.0| |24 | |26| | | 9|35|
+ | 693-1,326|1,585.0| |24 | |27| | | 8|35|
+ -+-----------+-------+-------------+---+-------------+--+--+---+--+--|
+ A| 216-1,326|2,777.5| |23 | |27| | | 7|34|
+ l| 55-1,326|3,180.0| |22 | |26| | | 6|32|
+ l| | | | | | | | | | |
+ =+===========+=======+=============+===+=============+==+==+===+==+==|
+
+ TABLE 24 PART 2
+
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+ W| | | |Av. | | TIME FOR RING |
+ e| | | | | | ERECTION, |
+ i| | | |Time | | HRS. AND MIN. |
+ g| |----+-----| | |----+----+----+----+----|
+ h| |Av. |Time |per | | | | | | |
+ t| |No. |Muck-| |T | O | | | | |
+ | |of |ing, |ring,|i | r | | | | |
+ o| |cu. |per | |m | d | B | B | | |
+ f| |yd. |cu. |shov-|e J | i | o | o | T | |
+ | |per |yd. |ing |a | n | r | r | a | M |
+ | |ring| | |f c | a | e | e | p | e |
+ i| | | |and |o k | r | | | e | a |
+ r| Section | | | |r s | y | 1 | 2 | r | n |
+ o| between | | |Muck-+--------+----+----+----+----+----|
+ n| rings |E | |ing | F | G | G | G | G | G |
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 1-54 | | | |Time for|4-00| | |4-21|4-04|
+ | 55-80 |41 |0-31 |21-00|jacks |6-04| | |5-30|5-57|
+ | 81-107 |41 |0-33 |22-30|for |4-26| | | |4-26|
+ O| 108-153 |41 |0-39 |26-31|light |3-10| | |3-30|3-12|
+ r| 154-194 |41 |0-27 |18-34|iron is |2-08| J. | J. |2-40|2-10|
+ d| | | | |included| | | | | |
+ i| 195-215 |41 |0-10 | 6-46|in |3-03|3-30|3-30| |3-09|
+ n| 216-393 |46 |0-05 | 3-53|shoving |2-40|2-56|3-00|3-10|2-50|
+ a| 394-429 |46 |0-18 |17-09|and |3-43|3-39|4-46|4-11|3-56|
+ r| | | | |mucking | | | | | |
+ y| 430-509 |11 |0-10 | 1-42| |3-14|4-12|3-59|3-46|3-34|
+ | 510-692 |30 |0-05 | 1-47| |2-08|2-21|2-32|2-50|2-18|
+ | 55-692 |30 |0-15 | 7-35|[N] |3-02| | |4-31|3-12|
+ | 216-692 |30 |0-07 | 3-42|[N] |2-38|2-59|3-08|1-30|2-50|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 693- 954|11 |0-12 | 1-02|[N] |1-52|2-05|2-15|2-29|2-0 |
+ | 955-1,014|12 |0-04 | 0-48|0-16 |0-51|1-18|1-08|0-50|0-58|
+ |1,015-1,074|12 |0-03 | 0-41|0-13 |0-43|0-46|0-55|0-40|0-45|
+ H|1,075-1,134| 8 |0-04 | 0-34|0-12 |1-04|1-01|1-15|1-20|1-08|
+ e|1,135-1,194| 8 |0-04 | 0-33|0-13 |0-53|0-51|0-58|0-46|0-53|
+ a|1,195-1,224| 6 |0-04 | 0-24|0-12 |0-58|0-42|0-53|0-50|0-54|
+ v|1,225-1,262| 5 |0-05 | 0-23|0-10 |0-48|0-49|0-50|0-35|0-47|
+ y|1,263-1,277|10 |0-04 | 0-36|0-11 |0-47|0-50|0-52|0-48|0-52|
+ |1,278-1,307|17 |0-04 | 1-09|0-10 |1-03|1-01|1-06|0-00|1-04|
+ |1,308-1,326|22 |0-05 | 1-39|0-18 |1-25|1-48|1-50|0-50|1-31|
+ | 955-1,326|11 |0-04 | 0-41|0-13 |0-55|0-59|1-03|0-55|0-58|
+ | 693-1,326|12 |0-04 | 0-51|[N] |1-27|1-34|1-41|1-38|1-31|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ A| 216-1,326|19 |0-06 | 1-59|[N] |1-55|2-08|2-16|1-35|2-03|
+ l| 55-1,326|21 |0-10 | 4-13|[N] | | | | |2-22|
+ l| | | | | | | | | | |
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+
+ TABLE 24 PART 3
+
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+ W| | BOLTING TIME, WHOLE |Time| |
+ e| | TIME ON BOLTS AFTER | | |
+ i| | RING IS COMPLETE. |lost| TOTAL TIME. |
+ g| |----+----+----+----+----| |-----+-----+-----+-----+-----|
+ h| | | | | | |re- | | | | | |
+ t| | O | | | | |pair- | | | | |
+ | | r | | | | |ing | | | | | |
+ o| | d | B | B | | | | O | | | | |
+ f| | i | o | o | T | |hy- | r | | | | |
+ | | n | r | r | a | M |drau- d | B | B | | |
+ | | a | e | e | p | e |lic | i | o | o | T | |
+ i| | r | | | e | a | | n | r | r | a | M |
+ r| Section | y | 1 | 2 | r | n |pip-| a | e | e | p | e |
+ o| between |----+----+----+----+----|ing | r | | | e | a |
+ n| rings | H | H | H | H | H | | y | 1 | 2 | r | n |
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 1-54 | Excavation partially completed previously. |
+ | 55-80 |} {| |27-4 | | |26-30|26-57|
+ O| 81-107 |} {| |26-56| | | |26-56|
+ r| 108-153 |} {| |29-41| | |30-1 |29-43|
+ d| 154-194 |} {| |20-42| | |21-14|20-44|
+ i| |} {| | | | | | |
+ n| 195-215 |} {| | 9-49|10-16|10-16| | 9-55|
+ a| 216-393 |} Bolting time for {|0-09| 6-42| 6-58| 7-02| 7-12| 6-52|
+ r| 394-429 |} light iron is {| |23-79|23-25|24-32|23-57|23-42|
+ y| |} included in {| | | | | | |
+ | 430-509 |} erection. {|0-18| 5-14| 6-12| 5-59| 5-46| 5-34|
+ | 510-692 |} {|0-11| 4-06| 4-19| 4-30| 4-48| 4-16|
+ | 55-692 |} {|0-17|10-54| | |12-23|11-04|
+ | 216-692 |} {|0-25| 6-45| 7-06| 7-15| 5-37| 6-57|
+ -+-----------|} {|----+-----+-----+-----+-----+-----|
+ | 693- 954|} {|0-13| 3-7 | 3-20| 3-30| 3-44| 3-15|
+ | 955-1,014|0-24|0-21|0-37|0-10|0-25|0 | 2-19| 2-43| 2-49| 2-04| 2-27|
+ |1,015-1,074|0-31|0-30|0-52|0-23|0-34|0-02| 2-10| 2-12| 2-43| 1-59| 2-15|
+ H|1,075-1,134|0-28|0-35|1-40|0-52|0-44|0-03| 2-21| 2-25| 3-44| 3-01| 2-41|
+ e|1,135-1,194|0-32|0-20|0-24|0-18|0-26|0 | 2-11| 1-57| 2-08| 1-50| 2-05|
+ a|1,195-1,224|0-19|0-20|0-34|0-35|0-23|0 | 1-53| 1-38| 2-03| 2-01| 1-53|
+ v|1,225-1,262|0-29|0-29|0-36|0-18|0-30|0 | 1-50| 1-51| 1-59| 1-26| 1-50|
+ y|1,263-1,277|0-23|0-23|0-41|0-23|0-27|0 | 1-57| 2-0 | 2-20| 1-58| 2-06|
+ |1,278-1,307|0-33|0-34|0-51|0-0 |0-36|0 | 2-55| 2-54| 3-16| 0-0 | 2-59|
+ |1,308-1,326|0-49|0-42|0-58|0-25|0-48|0 | 4-11| 4-27| 4-45| 3-12| 4-16|
+ | 955-1,326|0-29|0-27|0-49|0-31|0-32|0 | 2-18| 2-20| 2-46| 2-20| 2-24|
+ | 693-1,326|[O] | | | | |0-06| 2-24| 2-31| 2-38| 2-35| 2-28|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ A| 216-1,326|[O] | | | | |0-16| | | | | 4-18|
+ l| 55-1,326|[O] | | | | |0-12| | | | | 6-47|
+ l| | | | | | | | | | | | |
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+
+ TABLE 24 SUMMARY PART 1
+
+ ===+===========+=======+==============+====+============+==+==+===+==+==|
+ | | | AVE. NO. |
+ W| | | OF MEN |
+ e| | DESCRIPTION | IN GANG |
+ i| |-------+--------------+----+------------+--+--+---+--+--|
+ g| | | |Ave.| | | | | | |
+ h| | | |air | | | | | | |
+ t| | | | | | | | | A| |
+ | | | |P | | | D| G | i| |
+ o| | | |r | | | r| r | r| |
+ f| | | |e | | S| i| o | | |
+ | | | |s | | h| l| u | T|T |
+ i| | | |s | | i| l| t | r|o |
+ r| Section | | |u | | e| i| i | a|t |
+ o| between |Length | |r |Method of | l| n| n | n|a |
+ n| rings |in feet| Material |e |Excavation | d| g| g | s|l |
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ O {| 1-54 | 135.0|Rock |0 | [P] | | | | |14|
+ r {| 55-194 | 350.0|Earth and rock|16 | [P] |22| 6|1/3| 2|30|
+ d {| 195-393 | 497.5|Silt |20 |[P]Breasting|27| | | 4|31|
+ i {| 394-440 | 117.5| " |24 |[P]Breasting|28| | | 4|32|
+ n {| 441-692 | 630.0| " |23 |[Q]3 doors |25| | | 4|29|
+ a {|-----------+-------+--------------+----+------------+--+--+---+--+--|
+ r {| 216-692 |1,192.5| |22 | |26| | | 4|30|
+ y {|-----------+-------+--------------+----+------------+--+--+---+--+--|
+ {| 55-692 |1,595.0| |20 | |25| 2| | 3|30|
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ Hvy| 693-1,326|1,585.0|Silt |24 |[Q]1 door |27| | | 8|35|
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ All| 55-1,326|3,180.0| |22 | |26| | | 6|32|
+ ===+===========+=======+==============+====+============+==+==+===+==+==|
+
+ TABLE 24 SUMMARY PART 2
+
+ ===+========+========+=======+=======+====+=====+===============+========|
+ W | | | | UNAVOIDABLE DELAYS |
+ e | | | AVERAGE TIME |(NOT INCLUDED IN AVERAGE|
+ i o| | | PER RING. | TIME PER RING). |
+ g f| | |-------+-------+----+-----+---------------+--------|
+ h |Average | Time | | | | | | |
+ t i| No. of |mucking,|Shoving| | | | | |
+ r| cubic | per | and | Erec- | | | | |
+ o| yards | cubic |mucking| tion |Lost| | | Time |
+ n|per ring| yard | [N] | [O] |time|Total| Items |hrs min|
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ O {| | | | 4-14 | | |First bulkhead |172 00|
+ r {| 41 | 0-32 | 21-44 | 4-4 | |25-48|Second bulkhead|119 00|
+ d {| 38 | 0-7 | 4-11 | 2-52 |0-9 | 7-12|Grouting |200 00|
+ i {| 41 | 0-18 | 11-54 | 4-17 |1-41|17-52|Blowout | 73 00|
+ n {| 17 | 0-6 | 2-04 | 2-34 |0-42| 5-20|Cradle |100 00|
+ a {|--------+--------+-------+-------+----+-----+---------------+--------|
+ r {| 30 | 0-7 | 3-42 | 2-50 |0-25| 6-57|Total |664 00|
+ y {|--------+--------+-------+-------+----+-----+---------------+--------|
+ {| 30 | 0-15 | 7-35 | 3-12 |0-17|11-04|Per ring | 0 30|
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ Hvy| 12 | 0-4 | 0-51 | 1-31 |0-06| 2-28| | |
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ All| 21 | 0-10 | 4-13 | 2-22 |0-12| 6-47| | |
+ ===+========+========+=======+=======+====+=====+===============+========|
+
+[N] Including time for jacks.
+
+[O] Including bolting time.
+
+[P] Excavating ahead of shield.
+
+[Q] Shoving shield into silt with ... doors open.
+
+TABLE 25.--SHIELD-DRIVEN TUNNEL WORK, MANHATTAN SHAFT, RIVER TUNNEL
+SOUTH. Table showing the size of the gang, the amount of excavation, and
+the time per ring taken for the various operations involved in building
+tunnel through the several kinds of ground encountered; also the extent
+and nature of all the unavoidable delays.
+
+ TABLE 25 PART 1
+
+ =+===========+=======+==================+===+============+==+==+==+==+==|
+ W| | | AVE. NO. |
+ e| | | OF MEN |
+ i| | DESCRIPTION | IN GANG |
+ g| |-------+------------------+---+------------+--+--+--+--+--|
+ h| | | |Ave| | | | |A | |
+ t| | | |air| | |D |G |i | |
+ | | | | | | |r |r |r | |
+ o| | | |P | |S |i |o | | |
+ f| | | |r | |h |l |u |t |T |
+ | | | |e | |i |l |t |r |o |
+ | | | |s | |e |i |i |a |t |
+ i| | | |s | |l |n |n |n |a |
+ r| Section | | |u | |d |g |g |s |l |
+ o| between | Length| |r |Method of |--+--+--+--| |
+ n| rings |in feet|Material |e |Excavation |A |B |C |D | |
+ -+-----------+-------+------------------+---+------------+--+--+--+--+--|
+ | 1-68 | 170.0|Rock | 0 |[R] |20| 5| 5|2 |32|
+ | 69-95 | 67.5|Rock and earth |13 |[R] |22| 8| |2 |32|
+ O| 96-141 | 115.0|Rock |10 |[R] |21|13| |2 |36|
+ r|142-191 | 125.0|Rock and earth |15 |[R] |24| 7| |2 |33|
+ d|192-203 | 30.0|Silt |18 |[R]Breasting|23| | |3 |26|
+ i|204-388 | 462.5| " |18 |[S]7 doors |27| | |3 |30|
+ n|389-429 | 102.5|{Silt, piles and} |22 |[S]6 doors |24| | |4 |28|
+ a| | |{rip-rap. } | |[R]Breasting| | | | | |
+ r|430-504 | 187.5|Silt |21 |[S]3 doors |23| | |5 |28|
+ y|505-629 | 312.5| " |22 |[S]4 doors |25| | |6 |31|
+ |630-692 | 157.5| " |23 |[S]2 doors. |24| | |8 |32|
+ |204-692 |1,222.5| |21 | |25| | |5 |30|
+ | 69-692 |1,560.0| |17 | |23|4 | 0|3 |30|
+ -+-----------+-------+------------------+---+------------+--+--+--+--+--|
+ | 693-766 | 185.0|Silt |24 |[S]2 doors |21| | |6 |27|
+ | 767-806 | 100.0| " |24 |[S]2 " |22| | |7 |29|
+ H| 807-900 | 235.0| " |24 |[S]1½ " |23| | |8 |31|
+ e| 901-933 | 82.5| " |25 |[S]1 door |30| | |10|40|
+ a| 934-988 | 137.5| " |25 |[S]1 " |30| | |11|41|
+ v| 989-1,043| 137.5| " |25 |[S]1 " |28| | |11|39|
+ y|1,044-1,053| 25.0| " |26 |[S]1 " |25| | |9 |34|
+ |1,054-1,068| 37.5| " |26 |[S]1 " |26| | |9 |35|
+ |1,069-1,110| 105.0| " |26 |[S]1 " |30| | |11|41|
+ | 693-1,110|1,045.0| |25 | |25| | |8 |33|
+ -+-----------+-------+------------------+---+------------+--+--+--+--+--|
+ A| 204-1,110|2,267.5| |23 | |25| | |6 |31|
+ l| 69-1,110|2,605.0| |20 | |24|2 | |5 |31|
+ l| | | | | | | | | | |
+ =+===========+=======+==================+===+============+==+==+==+==+==|
+
+ TABLE 25 PART 2
+
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+ W| | | |Av. | | TIME FOR RING |
+ e| | | | | | ERECTION, |
+ i| | | |time | | HRS. AND MIN. |
+ g| |----+-----| | |----+----+----+----+----|
+ h| |Av. |Time |per | | | | | | |
+ t| |No. |Muck-| |T | O | | | | |
+ | |of |ing, |ring,|i | r | | | | |
+ o| |cu. |per | |m | d | B | B | | |
+ f| |yd. |cu. |shov-|e J | i | o | o | T | |
+ | |per |yd. |ing | a | n | r | r | a | M |
+ | |ring| | |f c | a | e | e | p | e |
+ i| | | |and |o k | r | | | e | a |
+ r| Section | | | |r s | y | 1 | 2 | r | n |
+ o| between |----| |Muck-+--------+----+----+----+----+----|
+ n| rings | E | |ing | F | G | G | G | G | G |
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 1-68 |41 |0-14 | 9-53|Time for|5-27| | |4-32|5-07|
+ | 69-95 |41 |0-24 |16-18|jacks |3-02| | |2-40|3-00|
+ O| 96-141 |70 |0-16 |18-16|for |2-08| | |2-27|2-09|
+ r| 142-191 |52 |0-20 |17-27|light |2-08| J | J |2-04|2-08|
+ d| 192-203 |36 |0-13 | 7-58|iron is |2-27|6-00|2-10|3-15|2-47|
+ i| 204-388 |37 |0-05 | 3-19|included|2-41|2-49|2-54|2-56|2-47|
+ n| 389-429 |40 |0-17 |12-42|in |3-15|2-36|5-03|3-26|3-27|
+ a| | | | |shoving | | | | | |
+ r| 430-504 |20 |0-06 | 1-51|and |2-53|3-17|3-00|2-57|2-59|
+ y| 505-629 |27 |0-05 | 2-20|mucking |2-23|2-40|2-45|2-28|2-30|
+ | 630-692 |22 |0-05 | 1-53| |1-54|2-10|2-22|2-23|2-02|
+ | 204-692 |30 |0-07 | 3-27| [T] |2-34|2-45|2-58|2-35|2-42|
+ | 69-692 |36 |0-11 | 6-40| [T] |2-47| | |3-18|2-52|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 693-766 |22 |0-05 | 1-35| 0-25 |1-18|1-44|1-30|1-40|1-25|
+ | 767-806 |22 |0-05 | 1-19| 0-21 |1-00|0-56|1-37|1-21|1-08|
+ | 807-900 |19 |0-05 | 1-11| 0-17 |0-58|1-13|1-08|1-12|1-04|
+ H| 901-933 |19 |0-04 | 1-13| 0-09 |0-59|1-05|0-59| |1-00|
+ e| 934-988 |16 |0-04 | 0-54| 0-12 |0-49|0-44|0-56| |0-50|
+ a| 989-1,043|13 |0-05 | 0-52| 0-14 |0-51|0-44|0-52|1-14|0-52|
+ v|1,044-1,053|16 |0-07 | 0-40| 0-15 |1-04|1-15|0-50|0-55|1-02|
+ y|1,054-1,068| 8 |0-05 | 0-36| 0-08 |0-57|0-40|1-02| |0-56|
+ |1,069-1,110|14 |0-06 | 1-00| 0-15 |0-48|0-54|1-06|1-31|0-56|
+ | 693-1,110|18 |0-05 | 1-29| [T] |1-01|1-08|1-09|1-19|1-05|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ A| 204-1,110|25 |0-06 | 2-35| [T] |2-09|2-19|2-33|2-19|2-17|
+ l| 69-1,110|29 |0-09 | 4-36| [T] |2-19| | |2-46|2-25|
+ l| | | | | | | | | | |
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+
+ TABLE 25 PART 3
+
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+ W| | BOLTING TIME, WHOLE |Time| |
+ e| | TIME ON BOLTS AFTER | | |
+ i| | RING IS COMPLETE. |lost| TOTAL TIME. |
+ g| |----+----+----+----+----| |-----+-----+-----+-----+-----|
+ h| | | | | | |re- | | | | | |
+ t| | O | | | | |pair- | | | | |
+ | | r | | | | |ing | | | | | |
+ o| | d | B | B | | | | O | | | | |
+ f| | i | o | o | T | |hy- | r | | | | |
+ | | n | r | r | a | M |drau- d | B | B | | |
+ | | a | e | e | p | e |lic | i | o | o | T | |
+ i| | r | | | e | a | | n | r | r | a | M |
+ r| Section | y | 1 | 2 | r | n |pip-| a | e | e | p | e |
+ o| between |----+----+----+----+----|ing | r | | | e | a |
+ n| rings | H | H | H | H | H | | y | 1 | 2 | r | n |
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 1-68 |}Excavation partially {| |15-20| | |14-25|15-00|
+ | 69-95 |}completed previously. {| |19-20| | |18-58|19-18|
+ O| 96-141 |} {|0-03|20-27| | |20-46|20-28|
+ r| 142-191 |} {|0-12|19-47| | |19-43|19-47|
+ d| 192-203 |}Bolting time for light{|1-20|11-45|15-18|11-28|12-33|12-05|
+ i| 204-388 |}iron is included in {|0-05| 6-05| 6-13| 6-18| 6-20| 6-11|
+ n| 389-429 |}erection. {|0-38|16-35|15-56|18-23|16-46|16-47|
+ a| |} {| | | | | | |
+ r| 430-504 |} {|0-39| 5-23| 5-47| 5-30| 6-27| 5-29|
+ y| 505-629 |} {|0-23| 5-06| 5-23| 5-28| 5-11| 5-13|
+ | 630-692 |} {|0-08| 3-55| 4-11| 4-23| 4-24| 4-03|
+ | 204-692 |} {|0-18| 6-19| 6-30| 6-43| 6-20| 6-27|
+ | 69-692 |} {|0-15| 9-42| | |10-13| 9-47|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 693-766 |0-43|1-09|0-52|0-50|0-49|0-07| 4-08| 5-00| 4-29| 4-37| 4-21|
+ | 767-806 |0-38|0-24|0-43|0-38|0-42|0-02| 3-20| 3-02| 4-02| 3-41| 3-32|
+ | 807-900 |0-39|0-34|0-56|0-31|0-40|0-06| 3-11| 3-21| 3-38| 3-17| 3-18|
+ H| 901-933 |0-34|0-26|1-47| |0-43|0-05| 3-00| 2-58| 4-13| | 3-10|
+ e| 934-988 |0-28|0-34|0-34| |0-30|0-06| 2-29| 2-30| 2-42| | 2-32|
+ a| 989-1,043|0-33|0-24|0-51|0-35|0-35|0-04| 2-34| 2-18| 2-53| 2-59| 2-37|
+ v|1,044-1,053|0-23|0-38|0-30|0-55|0-36| | 3-22| 3-48| 3-15| 3-45| 3-33|
+ y|1,054-1,068|0-33|0-25|0-35| |0-32| | 2-14| 1-49| 2-21| | 2-12|
+ |1,069-1,110|0-32|0-40|0-48|0-46|0-37|0-05| 2-40| 2-54| 3-14| 3-37| 2-53|
+ | 693-1,110|0-37|0-39|0-52|0-40|0-40|0-05| 3-12| 3-21| 3-35| 3-33| 3-19|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ A| 204-1,110| [U]| | | | |0-12| 4-56| 5-06| 5-20| 5-06| 5-04|
+ l| 69-1,110| [U]| | | | |0-14| 7--0| | | 7-36| 7-15|
+ l| | | | | | | | | | | | |
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+
+ TABLE 25 SUMMARY PART 1
+
+ ===+===========+=======+==============+====+============+==+==+===+==+==|
+ | | | AVE. NO. |
+ W| | | OF MEN |
+ e| | DESCRIPTION | IN GANG |
+ i| |-------+--------------+----+------------+--+--+---+--+--|
+ g| | | |Ave.| | | | | | |
+ h| | | |air | | | | | | |
+ t| | | | | | | | | A| |
+ | | | |P | | | D| G | i| |
+ o| | | |r | | | r| r | r| |
+ f| | | |e | | S| i| o | | |
+ | | | |s | | h| l| u | T|T |
+ i| | | |s | | i| l| t | r|o |
+ r| Section | | |u | | e| i| i | a|t |
+ o| between |Length | |r |Method of | l| n| n | n|a |
+ n| rings |in feet| Material |e |Excavation | d| g| g | s|l |
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ O {| 1-68 | 170.0|Rock | 0 | [R] |20| 5| 5| 5|32|
+ r {| 69-191 | 307.5|Rock and earth|13 | [R] |22| 9| | 2|33|
+ d {| 192-388 | 492.5|Silt |18 |[R]Breasting|25| | | 3|28|
+ i {| | | | {|[S]7 doors | | | | | |
+ n {| 389-429 | 102.5|Silt piles and|22 |[R]Breasting|24| | | 4|28|
+ a {| | |rip-rap | {|[S]6 doors | | | | | |
+ r {| 430-692 | 657.5|Silt |22 |[S]3 doors |24| | | 6|30|
+ y {|-----------+-------+--------------+----+------------+--+--+---+--+--|
+ {| 204-692 |1,222.5| |21 | |25| | | 5|30|
+ {|-----------+-------+--------------+----+------------+--+--+---+--+--|
+ {| 69-692 |1,560.0| |17 | |23| 4| 0| 3|30|
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ Hvy| 693-1,110|1,045.0| |25 |[S]1 door |25| | | 8|33|
+ ---+-----------+-------+--------------+----+------------+--+--+---+--+--|
+ All| 69-1,110|2,605.0| |20 | |24| | | 5|31|
+ ===+===========+=======+==============+====+============+==+==+===+==+==|
+
+ TABLE 25 SUMMARY PART 2
+
+ ===+========+========+=======+=====+====+=====+==================+=======|
+ W | | | | UNAVOIDABLE DELAYS |
+ e | | | AVERAGE TIME | (NOT INCLUDED IN AVERAGE |
+ i o| | | PER RING. | TIME PER RING). |
+ g f| | |-------+-----+----+-----+------------------+-------|
+ h |Average | Time | | | | | | |
+ t i| No. of |mucking,|Shoving| | | | | |
+ r| cubic | per | and |Erec-| | | | |
+ o| yards | cubic |mucking|tion |Lost| | | Time |
+ n|per ring| yard | [T] | [U] |time|Total|Items |hrs min|
+ ---+--------+--------+-------+-----+----+-----+------------------+-------|
+ O {| 41 | 0-14 | 9-53 | 5-07| |15-00|First bulkhead |160 00|
+ r {| 54 | 0-19 | 17-20 | 2-26|0-05|19-51|Second bulkhead |157 45|
+ d {| 37 | 0-09 | 5-39 | 2-47|0-63| 9-29|Grouting |200 00|
+ i {| | | | | | | | |
+ n {| 40 | 0-17 | 12-42 | 3-27|0-38|16-47|Blowout | 69 45|
+ a {| | | | | | | | |
+ r {| 24 | 0-05 | 1-58 | 2-29|0-22| 4-49|Waiting-heavy iron| 64 00|
+ y {|--------+--------+-------+-----+----+-----+------------------+-------|
+ {| 30 | 0-07 | 3-27 | 2-42|0-18| 6-27|Total |715 30|
+ {|--------+--------+-------+-----+----+-----+------------------+-------|
+ {| 36 | 0-11 | 6-40 | 2-52|0-15| 9-47|Per ring | 0 39|
+ ---+--------+--------+-------+-----+----+-----+------------------+-------|
+ Hvy| 18 | 0-05 | 1-29 | 1-45|0-06| 3-19| | |
+ ---+--------+--------+-------+-----+----+-----+------------------+-------|
+ All| 29 | 0-09 | 4-36 | 2-25|0-14| 7-15| | |
+ ===+========+========+=======+=====+====+=====+==================+=======|
+
+[R] Excavating ahead of shield.
+
+[S] Shoving shield into silt with ... doors open.
+
+[T] Including time for jacks.
+
+[U] Including bolting time.
+
+TABLE 26.--SHIELD-DRIVEN TUNNEL WORK, WEEHAWKEN SHAFT, RIVER TUNNEL
+NORTH. Table showing the size of the gang, the amount of excavation, and
+the time per ring taken for the various operations involved in building
+tunnel through the several kinds of ground encountered; also the extent
+and nature of all the unavoidable delays.
+
+ TABLE 26 PART 1
+
+ =+===========+=======+=================+===+============+==+===+===+==+==|
+ W| | | AVE. NO. |
+ e| | | OF MEN |
+ i| | DESCRIPTION | IN GANG |
+ g| |-------+- ------------- +---+------------+--+---+---+--+--|
+ h| | | |Ave| | | | |A | |
+ t| | | |air| | |D |G |i | |
+ | | | | | | |r |r |r | |
+ o| | | |P | |S |i |o | | |
+ f| | | |r | |h |l |u |t |T |
+ | | | |e | |i |l |t |r |o |
+ | | | |s | |e |i |i |a |t |
+ i| | | |s | |l |n |n |n |l |
+ r| Section | | |u | |d |g |g |s |e |
+ o| between | Length| |r |Method of |--+---+---+--+--|
+ n| rings |in feet|Material |e |Excavation |A |B |C |D | |
+ -+-----------+-------+-----------------+---+------------+--+---+---+--+--|
+ | 1-24 | 60.0|Rock | 0 |[X] | 9|.04| 0 | 0|10|
+ | 25-55 | 77.5| " |20 |[X] |14|5 |0.5| 1|21|
+ | 56-72 | 42.5|Mixed sand and |10 |[X]Breasting|22|2 |.09| 2|26|
+ O| | |rock | | | | | | | |
+ r| 73-165 | 232.5|Sand and gravel |10 |[X] " |22|0 |0.1| 2|24|
+ d| 166-184 | 47.5|Sand and silt |20{|[X]Breasting|22|0 |.38| 3|25|
+ i| | |with piles | {|and cutting}| | | | | |
+ n| 185-253 | 172.5|Silt and piles |24{|piles }|23|0 |.71| 3|26|
+ a| 254-293 | 100.0|Silt |26 |[Y]8 doors |22|0 | 0 | 3|25|
+ r| 294-301 | 20.0| " |27 | |19|0 | 0 | 2|21|
+ y| 302-307 | 15.0| " |27 |[Y]8 doors |21|0 | 0 | 2|23|
+ | 308-342 | 87.5| " |28 | |19|0 | 0 | 2|21|
+ | 343-347 | 12.5| " |28 |[Y]8 doors |15|0 | 0 | 2|17|
+ | 348-459 | 280.0| " |28 | |20|0 | 0 | 3|28|
+ | 460-494 | 87.5| " |28 |[Y]8 doors |21|0 | 0 | 3|24|
+ | 495-513 | 47.5| " |28 | 8 " |23|0 | 0 | 4|27|
+ | 514-605 | 230.0| " |28 | 8 " |25|0 | 0 | 4|29|
+ | 606-624 | 47.5| " |28 | 8 " |24|0 | 0 | 4|28|
+ | 625-640 | 40.0| " |28 | 8 " |38|0 | 0 | 5|43|
+ | 25-640 |1,540.0| |20 | | | | | | |
+ | 185-640 |1,140.0| |26 | |23|0 |0.2| 3|26|
+ -+-----------+-------+-----------------+---+------------+--+---+---+--+--|
+ | 641-647 | 17.5|Silt |28 |[Y]8 doors |24|0 | 0 | 6|30|
+ | 648-751 | 260.0| " |28 |[Y]8 " |22|0 | 0 | 4|26|
+ | 752-795 | 110.0| " |28 |[Y]8 " |18|0 | 0 | 7|25|
+ | 796-825 | 75.0| " |28 |[Y]8 " |19|0 | 0 |10|28|
+ H| 826-854 | 72.5| " |28 |[Y]8 " |17|0 | 0 | 3|20|
+ e| 855-881 | 67.5| " |28 |[Y]8 " |23|0 | 0 | 9|32|
+ a| 882-982 | 252.5| " |28 |[Y]8 " |20|0 | 0 | 8|28|
+ v| 983-990 | 20.0| " |28 |[Y]8 " |21|0 | 0 | 7|28|
+ y| 991-1,049| 147.5| " |28 |[Y]8 " |23|0 | 0 | 7|30|
+ |1,050-1,074| 62.5| " |28 |[Y]8 " |24|0 | 0 | 9|33|
+ |1,075-1,110| 90.0| " |28 |[Y]8 " |25|0 | 0 |10|35|
+ | 641-1,110|1,175.0| |28 | |21|0 | 0 | 7|28|
+ -+-----------+-------+-----------------+---+------------+--+---+---+--+--|
+ A| 185-1,110|2,315.0| |28 | |22|0 |0.1| 5|27|
+ l| 25-1,110|2,715.0| |26 | |21|0.1|0.1| 3|24|
+ l| | | | | | | | | | |
+ =+===========+=======+=================+===+============+==+===+===+==+==|
+
+ TABLE 26 PART 2
+
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+ W| | | |Av. | | TIME FOR RING |
+ e| | | | | | ERECTION, |
+ i| | | |Time | | HRS. AND MIN. |
+ g| |----+-----| | |----+----+----+----+----|
+ h| |Av. |Time |per | | | | | | |
+ t| |No. |Muck-| |T | S | | | | |
+ | |of |ing, |ring,|i | t | | | | |
+ o| |cu. |per | |m | r | B | B | | |
+ f| |yd. |cu. |shov-|e J | a | o | o | T | |
+ | |per |yd. |ing |a | i | r | r | a | M |
+ | |ring| | |f c | g | e | e | p | e |
+ i| | | |and |o k | h | | | e | a |
+ r| Section | | | |r s | t | 1 | 2 | r | n |
+ o| between | | |Muck-+--------+----+----+----+----+----|
+ n| rings | E | |ing | F | G | G | G | G | G |
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 1-24 | 46 |0-06 | 4-32|Time |6-23| | | |6-23|
+ | 25-55 | 46 |0-51 |39-33|for |4-25| | |5-10|4-29|
+ O| 56-72 | 44 |0-21 |15-05|jacks |2-53| | |3-15|2-55|
+ O| | | | |for | | | | | |
+ r| 73-165 | 39 |0-11 | 6-56|light |2-27| | |2-21|2-26|
+ d| 166-184 | 42 |0-09 | 6-19|iron is |2-31| J | J |6-30|2-37|
+ i| | | | |included| | | | | |
+ n| 185-253 | 43 |0-09 | 6-13|in |1-57|2-44|2-52|2-00|2-15|
+ a| 254-293 | 6 |0-18 | 1-45|shoving |1-58|1-57|2-15|2-45|2-02|
+ r| 294-301 | 0 | | 1-08|and |0-58|1-45|1-50| |1-17|
+ y| 302-307 | 26 |0-09 | 4-03|mucking.|2-20|1-40|1-55|2-57|2-22|
+ | 308-342 | 0 | | 0-36| |2-00|1-34|2-42|1-58|2-02|
+ | 343-347 | 2 |0-36 | 1-11| |2-15|2-20| |2-43|2-33|
+ | 348-459 | 0 | | 0-33| |2-03|2-04|2-09|2-23|2-06|
+ | | | | | | | | | | |
+ | 460-494 | 9 |0-09 | 1-23| |2-49|2-30|2-50|1-50|2-38|
+ | 495-513 | 17 |0-05 | 1-28| |2-35|2-23|1-55|2-10|2-26|
+ | 514-605 | 26 |0-04 | 1-44| |2-12|2-34|2-29|2-15|2-19|
+ | 606-624 | 16 |0-04 | 1-07| |1-54|2-33|2-16|1-35|2-04|
+ | 625-640 | 24 |0-03 | 1-13| |2-14|2-55|2-35|2-46|2-28|
+ | 25-640 | | | | | | | | | |
+ | 185-640 | 16 |0-07 |1-58 | |2-07|2-19|2-26|2-15|2-13|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 641-647 | 19 |0-04 | 0-08| [V] |1-20|2-08|1-65|1-40|1-41|
+ | 648-751 | 14 |0-03 | 0-36| 0-12 |1-21|1-22|1-26|1-55|1-23|
+ | 752-795 | 10 |0-03 | 0-29| 0-14 |0-46|1-25|1-31|2-37|1-10|
+ | 796-825 | 5 |0-08 | 0-40| 0-11 |0-48|1-31|1-34|0-53|1-03|
+ H| 826-854 | 15 |0-03 | 0-48| 0-19 |0-54|1-12|1-02|1-23|1-01|
+ e| 855-881 | 7 |0-05 | 0-33| 0-16 |0-59|0-45|1-15|1-20|1-01|
+ a| 882-982 | 10 |0-02 | 0-20| 0-14 |0-49|1-02|1-01|0-50|0-54|
+ v| 983-990 | 17 |0-02 | 0-34| 0-14 |0-40|0-40|0-48| |0-44|
+ y| 991-1,049| 8 |0-03 | 0-21| 0-11 |0-40|0-48|0-39| |0-41|
+ |1,050-1,074| 7 |0-03 | 0-18| 0-10 |0-43|0-44|0-46|0-40|0-43|
+ |1,075-1,110| 16 |0-02 | 0-33| 0-12 |0-50|1-02|1-06|0-58|0-55|
+ | 641-1,110| 8 |0-04 | 0-30| 0-14 |0-56|1-08|1-12|1-29|1-02|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ A| 185-1,110| 12 |0-07 | 1-20| 0[V] |1-48|2-01|2-11|2-17|1-56|
+ l| 25-1,110|17.1|0-12 | 3-13| [V] | | | | |2-05|
+ l| | | | | | | | | | |
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+
+ TABLE 26 PART 3
+
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+ W| | BOLTING TIME, WHOLE |Time| |
+ e| | TIME ON BOLTS AFTER | | |
+ i| | RING IS COMPLETE. |lost| TOTAL TIME. |
+ g| |----+----+----+----+----| |-----+-----+-----+-----+-----|
+ h| | | | | | |re- | | | | | |
+ t| | S | | | | |pair- | | | | |
+ | | t | | | | |ing | | | | | |
+ o| | r | B | B | | | | S | | | | |
+ f| | a | o | o | T | |hy- | t | | | | |
+ | | i | r | r | a | M |drau- r | B | B | | |
+ | | g | e | e | p | e |lic | a | o | o | T | |
+ i| | h | | | e | a | | i | r | r | a | M |
+ r| Section | t | 1 | 2 | r | n |pip-| g | e | e | p | e |
+ o| between |----+----+----+----+----|ing | h | | | e | a |
+ n| rings | H | H | H | H | H | | t | 1 | 2 | r | n |
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 1-24 | Excavation partially | |10-55| | | |10-55|
+ | 25-55 |} completed previously.{| |43-58| | |44-43|44-02|
+ | 56-72 |} {|0-04|18-02| | |18-24|18-04|
+ O| 73-165 |} {|0-09| 9-32| | | 9-26| 9-31|
+ r| 166-184 |} {|0-07| 8-57| | |12-56| 9-03|
+ d| 185-253 |} {|0-15| 8-25| 9-12| 9-20| 8-28| 8-43|
+ i| |} {| | | | | | |
+ n| 254-293 |} Bolting time for {|0-14| 3-57| 3-56| 4-14| 4-44| 4-01|
+ a| 294-301 |} light iron is {| | 2-06| 2-53| 2-58| | 2-25|
+ r| 302-307 |} included in {| | 6-23| 5-43| 5-58| 7-00| 6-25|
+ y| 308-342 |} erection. {| | 2-36| 2-10| 3-18| 2-29| 2-38|
+ | 343-347 |} {|0-39| 4-05| 4-10| | 4-43| 4-23|
+ | 348-459 |} {|0-14| 2-50| 2-51| 2-56| 3-10| 2-53|
+ | |} {| | | | | | |
+ | 460-494 |} {|0-27| 4-39| 4-20| 4-40| 3-40| 4-28|
+ | 495-513 |} {| | 4-03| 3-51| 3-23| 3-38| 3-54|
+ | 514-605 |} {| | 3-56| 4-18| 4-13| 3-59| 4-03|
+ | 606-624 |} {| | 3-01| 3-40| 3-23| 2-42| 3-11|
+ | 625-640 |} {| | 3-27| 4-08| 3-48| 3-59| 3-41|
+ | 25-640 |} {| | | | | | |
+ | 185-640 |} {|0-09| 4-14| 4-26| 4-33| 4-22| 4-20|
+ -+-----------+------------------------+----+-----+-----+-----+-----+-----|
+ | 641-647 |0-40|0-35|1-25|0-55|0-47| | 3-08| 3-51| 4-28| 3-43| 3-36|
+ | 648-751 |0-31|0-29|0-38|0-30|0-32|0-12| 2-52| 2-51| 3-04| 3-25| 2-55|
+ | 752-795 |0-48|0-31|0-44|0-35|0-43|0-05| 2-22| 2-44| 3-03| 4-00| 2-41|
+ H| 796-825 |0-31|1-03|0-49|3-27|0-51| | 2-10| 3-25| 3-14| 5-11| 2-45|
+ e| 826-854 |0-22|0-37|0-38|0-20|0-27|0-06| 2-29| 3-02| 2-53| 2-56| 2-41|
+ a| 855-881 |0-22|0-21|0-45|0-40|0-26|0-45| 2-55| 2-40| 3-34| 3-34| 3-01|
+ v| 882-982 |0-41|0-36|0-36|0-15|0-39|0-12| 2-16| 2-24| 2-23| 1-51| 2-19|
+ y| 983-990 |1-15|0-15|0-28| |0-48| | 2-43| 1-43| 2-04| | 2-20|
+ | 990-1,046|0-41|0-34|0-55| |0-41| | 1-53| 1-54| 2-06| | 1-54|
+ |1,047-1,074|0-35|1-15|0-07|0-35|0-48|0-04| 1-50| 2-31| 2-25| 1-47| 2-03|
+ |1,075-1,110|0-35|0-46|0-58|2-10|0-41|0-21| 2-31| 2-54| 2-10| 4-14| 2-42|
+ | 641-1,110|0-36|0-36|0-44|0-54|6-38|0-11| 2-27| 2-27| 2-51| 3-18| 2-35|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ A| 185-1,110|[W] | | | | |0-10| 3-18| 3-31| 3-41| 3-47| 3-26|
+ l| 25-1,110|[W] | | | | |0-09| | | | | 5-27|
+ l| | | | | | | | | | | | |
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+
+ TABLE 26 SUMMARY PART 1
+
+ ===+===========+=======+==============+====+============+==+===+===+==+==|
+ | | | AVE. NO. |
+ W| | | OF MEN |
+ e| | DESCRIPTION | IN GANG |
+ i| |-------+--------------+----+------------+--+---+---+--+--|
+ g| | | |Ave.| | | | | | |
+ h| | | |air | | | | | | |
+ t| | | | | | | | | A| |
+ | | | |P | | | D | G | i| |
+ o| | | |r | | | r | r | r| |
+ f| | | |e | | S| i | o | | |
+ | | | |s | | h| l | u | t|T |
+ i| | | |s | | i| l | t | r|o |
+ r| Section | | |u | | e| i | i | a|t |
+ o| between |Length | |r |Method of | l| n | n | n|a |
+ n| rings |in feet| Material |e |Excavation | d| g | g | s|l |
+ ---+-----------+-------+--------------+----+------------+--+---+---+--+--|
+ O {| 1-24 | 60.0|Rock | 0 | [X] | 9|.04| 0 | 0|10|
+ r {| 25-55 | 77.5| " |20 | [X] |14|5 |0.5| 1|21|
+ d {| 56-72 | 42.5|Mixed sand and|10 |[X]Breasting|22|2 |.09| 2|26|
+ i {| | |rock | | | | | | | |
+ n {| 73-165 | 232.5|Sand & gravel |10 |[X]Breasting|22|0 |.1 | 2|24|
+ a {| 166-184 | 47.5|Sand and silt |20 {|[X]Breasting|22|0 |.38| 3|25|
+ r {| | |with piles | {|and cutting | | | | | |
+ y {| 185-253 | 172.5|Silt w/ piles |24 {|piles |23|0 |.71| 3|26|
+ {| 254-640 | 110.0|Silt |26 |[Y]Doors |22|0 | 0 | 3|25|
+ {|-----------+-------+--------------+----+------------+--+---+---+--+--|
+ {| 25-640 |1,540.0| |20 |[Y]Doors |21|0.3|.12| 3|24|
+ ---+-----------+-------+--------------+----+------------+--+---+---+--+--|
+ Hvy| 641-1,110|1,175.0| |28 | |21| 0 | 0 | 7|28|
+ ---+-----------+-------+--------------+----+------------+--+---+---+--+--|
+ All| 25-1,110|2,715.0| |26 | |21|0.1|0.1| 3|24|
+ ===+===========+=======+==============+====+============+==+===+===+==+==|
+
+ TABLE 26 SUMMARY PART 2
+
+ ===+========+========+=======+=======+====+=====+===============+========|
+ W | | | | UNAVOIDABLE DELAYS |
+ e | | | AVERAGE TIME |(NOT INCLUDED IN AVERAGE|
+ i o| | | PER RING. | TIME PER RING). |
+ g f| | |-------+-------+----+-----+---------------+--------|
+ h |Average | Time | | | | | | |
+ t i| No. of |mucking,|Shoving| | | | | |
+ r| cubic | per | and | Erec- | | | | |
+ o| yards | cubic |mucking| tion |Lost| | | Time |
+ n|per ring| yard | [V] | [W] |time|Total| Items |hrs min|
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ O {| 46 | 0-06 | 4-32 |6-23 |0-00|10-55|First bulkhead |132-00 |
+ r {| 46 | 0-51 |39-33 |4-29 |0-00|44-02|Second bulkhead|158-50 |
+ d {| 44 | 0-21 |15-05 |2-55 |0-04|18-04|Grouting |240-00 |
+ i {| | | | | | |Old cave-in |234-00 |
+ n {| 39 | 0-11 | 6-56 |2-26 |0-09| 9-31|shoving tube |128-00 |
+ a {| 42 | 0-09 | 6-19 |2-37 |0-07| 9-03|---------------+--------|
+ r {| | | | | | | Total |892-50 |
+ y {| 43 | 0-09 | 6-13 |2-15 |0-05| 8-43|---------------+--------|
+ {| 11 | 0-07 | 1-13 |2-20 |0-08| 3-41| per ring | 0-49 |
+ {|--------+--------+-------+-------+----+-----+---------------+--------|
+ {| 24 | 0-14 | 5-06 |2-24 |0-08| 7-38| | |
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ Hvy| 8 | 0-04 | 0-44 |1-40 |0-11| 2-35| | |
+ ---+--------+--------+-------+-------+----+-----+---------------+--------|
+ All| 17.1 | 0-12 | 3-13 |3-05 |0-09| 5-27| | |
+ ===+========+========+=======+=======+====+=====+===============+========|
+
+[V] Including time for jacks.
+
+[W] Including bolting time.
+
+[X] Excavating ahead of shield.
+
+[Y] Shoving shield into silt with ... doors open.
+
+TABLE 27.--SHIELD-DRIVEN TUNNEL WORK, WEEHAWKEN SHAFT, RIVER TUNNEL
+SOUTH. Table showing the size of the gang, the amount of excavation, and
+the time per ring taken for the various operations involved in building
+tunnel through the several kinds of ground encountered; also the extent
+and nature of all the unavoidable delays.
+
+ TABLE 27 PART 1
+
+ =+===========+=======+============+====+============+==+==+===+===+==|
+ W| | | AVE. NO. |
+ e| | | OF MEN |
+ i| | DESCRIPTION | IN GANG |
+ g| |-------+------------+----+------------+--+--+---+---+--|
+ h| | | |Ave | | | | |A | |
+ t| | | |air | | |D |G |i | |
+ | | | | | | |r |r |r | |
+ o| | | |P | |S |i |o | | |
+ f| | | |r | |h |l |u |t |T |
+ | | | |e | |i |l |t |r |o |
+ | | | |s | |e |i |i |a |t |
+ i| | | |s | |l |n |n |n |a |
+ r| Section | | |u | |d |g |g |s |l |
+ o| between | Length| |r |Method of |--+--+---+---| |
+ n| rings |in feet|Material |e |Excavation |A |B |C |D | |
+ -+-----------+-------+------------+----+------------+--+--+---+---+--|
+ | 1-27 | 67.5|Rock | 9 |[C] {|Excavation }|
+ | | | | | {|partially }|
+ | | | | | {|completed }|
+ | | | | | {|previously. }|
+ | 28-42 | 37.5| " |12 |[C] |13| 4|1 |1 |19|
+ | 43-58 | 40.0|Rock or |12 |[C] |19| 2|2 |2 |25|
+ | | | | | | | |
+ O| 59-153 | 237.5|Gravel and |16 |[C]Breasting|25| |1 |4 |30|
+ r| | |sand | | | | | | | |
+ d| 154-170 | 42.5|Sand and |18 | " |26| |1 |5 |32|
+ i| | |silt w/piles| | | | | | | |
+ n| 171-236 | 165.0|Silt with |22 |Top half |22| |1 |3 |26|
+ a| | |piles | |
+ r| 237-259 | 57.5|Silt |25 |[D]1 door |18| |1 |3 |22|
+ y| 260-302 | 107.5| " |27 |[D]1 door |15| | |2 |17|
+ | 303-350 | 120.0| " |27 |[D]8 doors |15| | |4 |19|
+ | 351-378 | 70.0| " |27.5|[D]8 " |18| | |6 |24|
+ | 379-424 | 115.0| " |27.5|[D]8 " |19| | |4 |23|
+ | 425-522 | 245.0| " |28 |[D]1 door |19| | |4 |23|
+ | 523-625 | 257.5| " |28 |[D]1 " |20| | |4 |24|
+ | 171-625 |1,137.5| |27 | |19| | |4 |23|
+ | 28-625 |1,495.0| |25 | |19|.8|0.8|3.4|24|
+ -+-----------+-------+------------+----+------------+--+--+---+---+--|
+ | 626-649 | 57.5|Silt |28 |[D]1 door |16| | | 3 |19|
+ | 650-733 | 210.0| " |28 |[D]8 doors |19| | | 4 |23|
+ | 734-753 | 50.0| " |28 |[D]8 " |24| | | 5 |29|
+ H| 754-844 | 227.5| " |28 |[D]8 " |26| | | 8 |34|
+ e| 845-859 | 37.5| " |28 |[D]8 " |27| | | 9 |36|
+ a| 860-899 | 100.0| " |28 |[D]8 " |24| | | 8 |33|
+ v| 900-935 | 90.0| " |28 |[D]1 door |25| | | 7 |32|
+ y| 936-963 | 70.5| " |28 |[D]1 " |25| | | 8 |33|
+ | 964-1,003| 100.0| " |28 |[D]1 " |25| | |10 |35|
+ |1,004-1,060| 142.5| " |28 |[D]1 " |26| | |10 |36|
+ |1,061-1,110| 125.0| " |28 |[D]1 " |37| | |10 |47|
+ |1,111-1,238| 320.0| " |28 |[D]1 " |30| | | 9 |39|
+ |1,239-1,312| 185.0| " |28 | |39| | | 9 |38|
+ | 626-1,312|1,717.5| " |28 | |35| | | 8 |33|
+ -+-----------+-------+------------+----+------------+--+--+---+---+--|
+ A| 171-1,312|2,855.0| |28 | |23| | | 6 |29|
+ l| 28-1,312|3,212.5| |26 | |21| | | 5 |26|
+ l| | | | | | | | | | |
+ =+===========+=======+============+====+============+==+==+===+===+==|
+
+ TABLE 27 PART 2
+
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+ W| | | |Av. | | TIME FOR RING |
+ e| | | | | | ERECTION, |
+ i| | | |Time | | HRS. AND MIN. |
+ g| |----+-----| | |----+----+----+----+----|
+ h| |Av. |Time |per | | | | | | |
+ t| |No. |Muck-| |T | O | | | | |
+ | |of |ing, |ring,|i | r | | | | |
+ o| |cu. |per | |m | d | B | B | | |
+ f| |yd. |cu. |shov-|e J | i | o | o | T | |
+ | |per |yd. |ing |a | n | r | r | a | M |
+ | |ring| | |f c | a | e | e | p | e |
+ i| | | |and |o k | r | | | e | a |
+ r| Section | | | |r s | y | 1 | 2 | r | n |
+ o| between | | |Muck-+--------+----+----+----+----+----|
+ n| rings | E | |ing | F | G | G | G | G | G |
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 1-27 |Excavation| | |8-30| | |3-45|8-08|
+ | | partially| | | | | | | |
+ | | completed| | | | | | | |
+ | |previously| | | | | | | |
+ | 28-42 |48.7|0-25 |20-33| |4-23| | |4-00|4-21|
+ | 43-58 |44.2|0-46 |33-44| |4-16| | |5-45|4-44|
+ | | | | | | | | | | |
+ O| 59-153 |39.0|0-12 | 8-06| |2-19| | |4-18|2-23|
+ r| | | | | | | | | | |
+ d| 154-170 |41.6|0-10 | 7-10| |2-00| J. | J. |1-48|1-59|
+ i| | | | | | | | | | |
+ n| 171-236 |42.6|0-10 | 7-23| |2-36|2-55|2-58|1-24|2-35|
+ a| | | | | | | | | | |
+ r| 237-259 |13.8|0-11 | 2-29| |3-01|2-05|1-28|2-00|2-32|
+ y| 260-302 | 0 | | 0-32| |2-34|2-35|3-38|4-28|3-05|
+ | 303-350 | 6.9|0-07 | 0-52| |2-59|2-28|2-37|1-44|2-41|
+ | 351-378 | 0 | | 0-33| |2-05|2-32|2-48|2-00|2-18|
+ | 379-424 | 6.9|0-07 | 0-48| |3-34|2-51|3-18|3-19|3-22|
+ | 425-522 | 6.7|0-06 | 0-45| |3-09|3-51|3-00|3-28|3-16|
+ | 523-625 | 0 | | 0-32| |1-36|1-37|1-47|1-51|1-39|
+ | 171-625 | 9.7|0-11 | 1-44| [A] |2-37|2-41|2-41|2-32|2-38|
+ | 28-625 |17.8|0-14 | 4-14| [A] | | | | |2-41|
+ -+-----------+----+-----+-----+--------+----+----+----+----+----|
+ | 626-649 |12.2|0-12 | 2-23| [A] |2-19|2-30|2-05|1-42|2-16|
+ | 650-733 |13.5| | 0-57| 0-13 |1-42|1-24|1-47|1-48|1-39|
+ | 734-753 | 8.3|0-05 | 0-41| 0-17 |1-06|1-55|0-38|1-20|1-12|
+ H| 754-844 |12.8|0-04 | 0-51| 0-16 |1-19|1-41|1-52|0-50|1-29|
+ e| 845-859 | 5.6|0-07 | 0-39| 0-19 |1-24|1-08|1-10| |1-20|
+ a| 860-899 |16.5|0-02 | 0-39| 0-13 |1-00|1-05|1-13| |1-04|
+ v| 900-935 |11.5|0-03 | 0-29| 0-14 |0-47|1-13|0-52|1-10|0-52|
+ y| 936-963 | 5.9|0-03 | 0-19| 0-15 |0-59|0-47|0-55| |0-56|
+ | 964-1,003| 8.1|0-03 | 0-27| 0-10 |0-51|0-52|1-05| |0-53|
+ |1,004-1,060| 8.7|0-03 | 0-30| 0-15 |1-01|1-09|1-05|0-45|1-03|
+ |1,061-1,110| 6.2|0-03 | 0-19| 0-10 |0-42|0-49|0-54|0-45|0-45|
+ |1,111-1,238|15.6|0-02 | 0-38| 0-16 |0-48|1-06|1-04|1-23|0-56|
+ |1,239-1,312|13.0|0-03 | 0-36| 0-18 |1-04|1-01|1-02|1-15|1-07|
+ | 626-1,312|10.6|0-04 | 0-42| 0-14 |1-06|1-15|1-16|1-18|1-10|
+ -+-----------+----+-----+-----+--------+--- |----+----+----+----|
+ A| 171-1,312|10.2|0-07 |1-15 | [A] |2-09|2-13|2-21|2-20|2-13|
+ l| 28-1,312|14.1|0-10 |2-28 | [A] | | | | |2-18|
+ l| | | | | | | | | | |
+ =+===========+====+=====+=====+========+====+====+====+====+====|
+
+ TABLE 27 PART 3
+
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+ W| | BOLTING TIME, WHOLE |Time| |
+ e| | TIME ON BOLTS AFTER | | |
+ i| | RING IS COMPLETE. |lost| TOTAL TIME. |
+ g| |----+----+----+----+----| |-----+-----+-----+-----+-----|
+ h| | | | | | |re- | | | | | |
+ t| | S | | | | |pair- | | | | |
+ | | t | | | | |ing | | | | | |
+ o| | r | B | B | | | | s | | | | |
+ f| | a | o | o | T | |hy- | t | | | | |
+ | | i | r | r | a | M |drau- r | B | B | | |
+ | | g | e | e | p | e |lic | a | o | o | T | |
+ i| | h | | | e | a | | i | r | r | a | M |
+ r| Section | t | 1 | 2 | r | n |pip-| g | e | e | p | e |
+ o| between |----+----+----+----+----|ing | h | | | e | a |
+ n| rings | H | H | H | H | H | | t | 1 | 2 | r | n |
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 1-27 |} {|0-14|21-11| | |16-26|20-49|
+ | |} {| | | | | | |
+ | |} {| | | | | | |
+ | |} {| | | | | | |
+ | 28-42 |} {|0-12|25-08| | |24-45|25-06|
+ | 43-58 |} {|1-15|39-15| | |40-44|39-43|
+ | |} {| | | | | | |
+ O| 59-153 |} {|0-30|10-55| | |12-54|10-59|
+ r| |{ {| | | | | | |
+ d| 154-170 |} {|0-00| 9-10| J. | J. | 8-58| 9-09|
+ i| |} {| | | | | |
+ n| 171-236 |} Bolting time for {|0-05|10-04|10-23|10-26| 8-52|10-03|
+ a| |} light iron is {| | | | | | |
+ r| 237-259 |} included in {|0-20| 5-50| 4-54| 4-17| 4-49| 5-21|
+ y| 260-302 |} erection. {|0-08| 3-14| 3-15| 4-18| 5-08| 3-45|
+ | 303-350 |} {|0-07| 3-58| 3-27| 3-36| 2-43| 3-40|
+ | 351-378 |} {|0-17| 2-55| 3-22| 3-38| 2-50| 3-08|
+ | 379-424 |} {|0-25| 4-47| 4-09| 4-31| 4-32| 4-35|
+ | 425-522 |} {|0-16| 4-10| 4-52| 4-01| 4-29| 4-17|
+ | 523-625 |} {|0-12| 2-20| 2-21| 2-31| 2-35| 2-23|
+ | 171-625 |} {|0-13| 4-34| 4-38| 4-38| 4-29| 4-35|
+ | 28-625 |} {|0-16| | | | | 7-11|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ | 626-649 |1-01|1-04|1-04|0-50|1-01|0-32| 6-15| 6-29| 6-04| 5-27| 6-12|
+ | 650-733 |1-15|0-52|0-55|0-42|1-07|0-32| 4-39| 3-58| 4-24| 4-12| 4-28|
+ | 734-753 |0-38|0-44|1-13|0-20|0-44|0-06| 2-48| 3-43| 2-55| 2-44| 3-00|
+ H| 754-844 |0-39|0-50|0-54|0-40|0-44|0-25| 3-30| 4-08| 4-18| 3-02| 3-45|
+ e| 845-859 |0-45|0-15|0-15| |0-37|0-48| 3-55| 3-09| 3-11| | 3-43|
+ a| 860-899 |0-59|0-32|0-49| |0-52|0-07| 2-58| 2-36| 3-01| | 2-55|
+ v| 900-935 |0-39|0-43|0-32|0-20|0-38|0-04| 2-18| 2-43| 2-11| 2-17| 2-17|
+ y| 936-963 |0-34|0-16|0-41| |0-32|0-37| 2-44| 2-14| 2-47| | 2-39|
+ | 964-1,003|0-32|0-45|0-37| |0-35|0-16| 2-16| 2-30| 2-35| | 2-21|
+ |1,004-1,060|0-54|0-37|0-49|0-40|0-49|0-24| 3-04| 2-55| 3-03| 2-34| 3-01|
+ |1,061-1,110|0-24|0-26|0-39|0-25|0-27|0-00| 1-35| 1-44| 2-02| 1-39| 1-41|
+ |1,111-1,238|0-36|0-34|0-57|1-12|0-41|0-02| 2-20| 2-36| 2-57| 3-31| 2-33|
+ |1,239-1,312|0-39|0-43|1-12|0-59|0-50|0-10| 2-47| 2-48| 3-18| 3-18| 3-01|
+ | 626-1,312|0-45|0-40|0-52|0-54|0-47|0-16| 3-03| 3-07| 3-20| 3-24| 3-09|
+ -+-----------+----+----+----+----+----+----+-----+-----+-----+-----+-----|
+ A| 171-1,312| [C]| | | | |0-15| 3-39| 3-43| 3-51| 3-50| 3-43|
+ l| 28-1,312| [C]| | | | |0-15| | | | | 5-01|
+ l| | | | | | | | | | | | |
+ =+===========+====+====+====+====+====+====+=====+=====+=====+=====+=====|
+
+ TABLE 27 SUMMARY PART 1
+
+ ===+===========+=======+==============+====+============+==+==+===+===+==|
+ | | | AVE. NO. |
+ W| | | OF MEN |
+ e| | DESCRIPTION | IN GANG |
+ i| |-------+--------------+----+------------+--+--+---+---+--|
+ g| | | |Ave.| | | | | | |
+ h| | | |air | | | | | | |
+ t| | | | | | | | | A | |
+ | | | |P | | | D| G | i | |
+ o| | | |r | | | r| r | r | |
+ f| | | |e | | S| i| o | | |
+ | | | |s | | h| l| u | T |T |
+ i| | | |s | | i| l| t | r |o |
+ r| Section | | |u | | e| i| i | a |t |
+ o| between |Length | |r |Method of | l| n| n | n |a |
+ n| rings |in feet| Material |e |Excavation | d| g| g | s |l |
+ ---+-----------+-------+--------------+----+------------+--+--+---+---+--|
+ {| 28-42 | 37.5|Rock |12 |[B]Breast |13| 4| 1| 1 |19|
+ O {| 43-58 | 40.0|Rock & gravel |12 | " |19| 2| 2| 2 |25|
+ r {| 59-153 | 237.5|Gravel & sand |16 | " |25| | 1| 4 |30|
+ d {| 154-170 | 42.5|Sand or silt, |18 | " |26| | 1| 5 |32|
+ i {| | | with piles | | | | | | | |
+ n {| 171-236 | 165.0|silt w/ piles |22 | " |22| | 1| 3 |26|
+ a {| 237-259 | 57.5|Silt |25 |[C]1 door |18| | 1| 3 |22|
+ r {| 260-625 | 915.0| " |27 | 1 " |18| | | 4 |22|
+ y {|-----------+-------+--------------+----+------------+--+--+---+---+--|
+ {| 28-625 |1,495.0| |25 | |19|.8|0.8|3.4|24|
+ ---+-----------+-------+--------------+----+------------+--+--+---+---+--|
+ Hvy| 626-1,312|1,717.5|Silt |28 | |25| | | 8 |33|
+ ---+-----------+-------+--------------+----+------------+--+--+---+---+--|
+ All| 28-1,312|3,212.5| |26 | |21| | | 5 |26|
+ ===+===========+=======+==============+====+============+==+==+===+===+==|
+
+ TABLE 27 SUMMARY PART 2
+
+ ===+========+========+=======+======+====+=====+===============+========|
+ W | | | | UNAVOIDABLE DELAYS |
+ e | | | AVERAGE TIME |(NOT INCLUDED IN AVERAGE|
+ i o| | | PER RING. | TIME PER RING). |
+ g f| | |-------+------+----+-----+---------------+--------|
+ h |Average | Time | | | | | | |
+ t i| No. of |mucking,|Shoving| | | | | |
+ r| cubic | per | and | Erec-| | | | |
+ o| yards | cubic |mucking| tion |Lost| | | Time |
+ n|per ring| yard | [Z] | [A] |time|Total| Items |hrs min|
+ ---+--------+--------+-------+------+----+-----+---------------+--------|
+ {| 48.7 | 0-25 | 20-33 | 4-21|0-12|25-06|First bulkhead | 80-00|
+ O {| 44.2 | 0-46 | 33-44 | 4-44|1-15|39-43|Second bulkhead| 156-00|
+ r {| 39.0 | 0-12 | 8-06 | 2-23|0-30|10-59|Grouting rock | 280-00|
+ d {| 41.6 | 0-10 | 7-10 | 1-59|0-0 | 9-09| sections| |
+ i {| | | | | | |Blow-outs | 222-00|
+ n {| 42.6 | 0-10 | 7-23 | 2-35|0-05|10-03|Shield repairs | 326-40|
+ a {| 13.8 | 0-11 | 2-29 | 2-32|0-20| 5-21|Horz. timbers | 69-30|
+ r {| 3.6 | 0-06 | 0-40 | 2-39|0-14| 3-33| Total |1,134-10|
+ y {|--------+--------+-------+------+----+-----+---------------+--------|
+ {| 17.8 | 0-14 | 4-14 | 2-41|0-16| 7-11|Per ring | 0-53|
+ ---+--------+--------+-------+------+----+-----+---------------+--------|
+ Hvy| 10.6 | 0-4 | 0-56 | 1-57|0-16| 3-09| | |
+ ---+--------+--------+-------+------+----+-----+---------------+--------|
+ All| 14.1 | 0-10 | 2-28 | 2-18|0-15| 5-01| | |
+ ===+========+========+=======+======+====+=====+===============+========|
+
+[Z] Including time for jacks.
+
+[A] Including bolting time.
+
+[B] Excavating ahead of shield.
+
+[C] Shoving shield into silt with ... doors open.
+
+The average time taken for each operation at all the working faces is
+given in Table 28. The work has been subdivided into the different kinds
+of ground encountered.
+
+The progress, as shown by the amount of work done each month by each
+shield, is given in Table 29.
+
+TABLE 28.--SHIELD-DRIVEN TUNNEL WORK.--TOTAL NUMBER OF RINGS ERECTED AND
+SHIFTS WORKED BY ALL FOUR SHIELDS IN CONTRACTS GY-WEST AND GJ, AND THE
+AVERAGE SIZE OF GANG, AMOUNT OF EXCAVATION AND TIME TAKEN PER RING FOR
+THE VARIOUS OPERATIONS INVOLVED IN BUILDING TUNNEL IN EACH OF THE
+SEVERAL KINDS OF GROUND ENCOUNTERED; ALSO THE EXTENT AND NATURE OF ALL
+THE UNAVOIDABLE DELAYS.
+
+ TABLE 28 PART 1
+
+ ===+===================+=====+========+======+==+====+====+====+====+====|
+ | | | | |A | AVE. NO. |
+ W| | | | |v | OF MEN |
+ e| | | | | | IN GANG |
+ i| | | | |a +----+----+----+----+----+
+ g| | | | |i | | | | A | |
+ h| | | | |r | | D | G | i | |
+ t| | | |Total | | | r | r | r | |
+ | | | | |p | S | i | o | | |
+ o| |Total| Total |number|r | h | l | u | t | T |
+ f| | | | |e | i | l | t | r | o |
+ | Description | No. | No. | of |s | e | i | i | a | t |
+ i| | | | |s | l | n | n | n | a |
+ r| of | of | of |8-hour|u | d | g | g | s | l |
+ o| | | | |r |----+----+----+----+----+
+ n| Material |rings| feet. |shifts|e |Unit|Unit|Unit|Unit|Unit|
+ ---+-------------------+-----+--------+------+--+----+----+----+----+----+
+ {|Rock. | 165| 412.5| 597 |16| 18 | 9 |0.25| 1 | 28 |
+ O {|Rock and earth and | 177| 442.5| 500 |14| 22 | 5 |0.3 | 2 | 30 |
+ r {| rock and gravel.| | | | | | | | | |
+ d {|Sand and gravel | 188| 470.0| 241 |13| 24 | |0.6 | 3 | 27 |
+ i {| (unobstructed), NJ| | | | | | | | | |
+ n {|Sand and silt (with| 171| 427.5| 199 |22| 23 | |1.0 | 3 | 27 |
+ a {| piles.)| | | | | | | | | |
+ r {|Silt under R. R. | 396| 990.0| 355 |19| 27 | | | 3 | 30 |
+ y {| tracks, NY| | | | | | | | | |
+ {|Rip-rap and silt | 77| 192.5| 193 |23| 26 | | | 4 | 30 |
+ | under bulkhead.| | | | | | | | | |
+ i {| |-----+--------+------+--+----+----+----+----+----|
+ r {|Total mixed and | | | | | | | | | |
+ o {| difficult ground.|1,174| 2,935.0|2,085 |17| 22 | 4 |0.3 | 3 | 29 |
+ n {|-------------------+-----+--------+------+--+----+----+----+----+----+
+ {|Silt--ordinary iron|1,302| 3,255.0| 676 |25| 22 | | | 4 | 26 |
+ ---+-------------------+-----+--------+------+--+----+----+----+----+----+
+ Hvy|Silt--heavy iron. |2,209| 5,522.5| 791 |26| 25 | | | 8 | 33 |
+ ---+-------------------+-----+--------+------+--+----+----+----+----+----+
+ |Silt--ord and heavy| | | | | | | | | |
+ |iron under river. |3,511| 8,777.5|1,467 |26| 24 | | | 6 | 30 |
+ |-------------------+-----+--------+------+--+----+----+----+----+----+
+ |Grand total. |4,685|11,712.5|3,552 |21| 23 | 2 |0.2 | 4 | 29 |
+ ===+===================+=====+========+======+==+====+====+====+====+====|
+
+ TABLE 28 PART 2
+
+ ====+====+=======+========+=======+=======+=============+========|
+ | | | |
+ | | | |
+ | | | |
+ | | | |
+ | | | |
+ | | | AVE. UNAVOIDABLE |
+ | | | DELAY PER |
+ | | AVERAGE TIME PER RING. | WORKING FACE. |
+ Cu. |Time|------------------------+-------+-------------+--------|
+ yd. |per |Shoving| | | | | Time |
+ per |cu. | and | | Lost | | Items |--------|
+ ring|yd. |mucking|Erecting| time | Total |not included |Ave unit|
+ ----+----+-------+--------+-------+-------| in previous |--------|
+ Unit|Unit|Hrs Min|Hrs Min |Hrs Min|Hrs Min| figures |Hrs Min |
+ | | K | L | M | | | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ 51 |0-27| 25 15| 3 41 | 0 02| 28 58|1st Bulkhead |136 00 |
+ 45 |0-26| 19 31| 2 55 | 0 11| 22 37| 2d " |147 54 |
+ | | | | | | | |
+ 39 |0-12| 7 31| 2 24 | 0 20| 10 15|Grouting |246 00 |
+ | | | | | | | |
+ 43 |0-09| 6 46| 2 24 | 0 09| 9 19|Blow-outs | 91 11 |
+ | | | | | | | |
+ 42 |0-06| 4 09| 2 51 | 0 10| 7 10|Miscellaneous|230 33 |
+ | | | | | | | |
+ 43 |0-21| 14 47| 3 41 | 1 34| 20 02|Total |851 38 |
+ | | | | | | | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ | | | | | | | |
+ 43 |0-18| 11 02| 2 54 | 0 16| 14 12| | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ 12 |0-07| 1 20| 2 35 | 0 14| 4 12| | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ 12 |0-05| 0 58| 1 44 | 0 10| 2 52| | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ | | | | | | | |
+ 12 |0-06| 1 09| 2 05 | 0 12| 3 26| | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+ 20 |0-11| 3 33| 2 15 | 0 13| 6 01| | |
+ ----+----+-------+--------+-------+-------+-------------+--------|
+
+ Average delay per ring--0 hrs. 44 min.
+ Average rings built by one shield = 1,146¼.
+
+ Average time per ring. 6 hr 01 min
+ Delays. 44 min
+ -----------
+ Total time per ring. 6 hr 45 min
+
+NOTE.--The "unavoidable delays" included in this table do not embrace
+the periods during which the work was at complete or partial standstill
+due to experiments and observations, shortage of iron due to change of
+design, and holidays.
+
+ K-Including time for jacks.
+
+ L-Including time spent by the whole gang on bolting; in
+ addition to this there was a small gang which spent its
+ whole time bolting.
+
+ M-Chiefly due to breakdowns of hydraulic lines and
+ erector.
+
+_Air Pressure._--The air pressure varied from 17 to 37 lb. Behind the
+river line it averaged 17 lb. and under the river 26 lb. Behind the
+river lines the pressure was generally kept about equal to the water
+head at the crown, except where at Weehawken, as previously described,
+this was impossible.
+
+In the silt the pressure was much lower than the hydrostatic head at the
+crown, but if it became necessary to make an excavation ahead of the
+shield, for example at the junction of the shields, the air pressure
+required was about equal to the weight of the overlying material,
+namely, the water and the silt, as the silt, which weighed from 97 to
+106 lb. per cu. ft. and averaged 100 lb. per cu. ft., acted like a
+fluid.
+
+ TABLE 29.--MONTHLY PROGRESS OF SHIELD-DRIVEN TUNNEL WORK.
+
+ =====+=============================+=============================+
+ | North Manhattan. | South Manhattan. |
+ +-----------------------------+----------------------+------+
+ | Number of | Station |Lin. | Number of | Station |Lin. |
+ | rings | of |ft. | rings | of |ft. |
+ | erected. | leading |for | erected. | leading |for |
+ +-----------+ ring. |month.+-----------+ ring. |month.|
+ |For | To | | |For |To | | |
+ Month|month|date | | |month|date | | |
+ -----+-----+-----+----------+------+-----+-----+----------+------+
+ 1905 | | | | | | | | |
+ May | 26 | 26|200 + 83.7| 63.7 | | | | |
+ June | 26 | 52|201 + 49.0| 65.3 | | | | |
+ July | 28 | 80|202 + 19.2| 70.2 | | | | |
+ Aug | 26 | 106|202 + 84.3| 65.1 | | | | |
+ Sept | 21 | 127|203 + 36.8| 52.5 | 31 | 31|200 + 96.4| 76.4 |
+ Oct | 25 | 152|203 + 99.4| 63.6 | 45 | 76|202 + 09.2|112.8 |
+ Nov | 31 | 183|204 + 76.9| 77.5 | 31 | 107|202 + 86.5| 77.3 |
+ Dec | 59 | 242|206 + 24.6|147.7 | 34 | 141|208 + 71.8| 85.3 |
+ 1906 | | | | | | | | |
+ Jan | 94 | 336|208 + 59.8|235.2 | 27 | 168|304 + 39.4| 67.6 |
+ Feb | 78 | 414|210 + 54.9|195.1 | 64 | 232|205 + 99.6|160.2 |
+ Mar | 56 | 470|211 + 95.2|140.3 | 96 | 328|208 + 39.9|240.3 |
+ April| 119 | 589|214 + 93.0|297.8 | 84 | 412|210 + 59.1|210.2 |
+ May | 129 | 718|218 + 15.7|322.7 | 70 | 482|212 + 25.3|165.2 |
+ June | 218 | 936|232 + 60.9|545.2 | 140 | 622|215 + 75.5|350.2 |
+ July | 155 |1,091|227 + 48.5|387.6 | 82 | 704|217 + 80.7|205.2 |
+ Aug | 145 |1,236|231 + 11.2|362.7 | 134 | 838|221 + 15.8|335.1 |
+ Sept | 89 |1,325|233 + 34.1|222.9 | 168 |1,006|225 + 35.8|420.0 |
+ Oct | | | | | 105 |1,111|227 + 98.6|262.8 |
+ Nov | | | | | 7 |1,118|228 + 16.8| 18.2 |
+ =====+=====+=====+==========+======+=====+=====+==========+======+
+
+ =====+=============================+============================+========
+ | North Weehawken. | South Weehawken. |
+ +-----------------------------+----------------------------+Average
+ | Number of | Station |Lin. | Number of | Station |Lin. |progress
+ | rings | of |ft. | rings | of |ft. |per
+ | erected. | leading |for | erected. | leading |for |shield
+ +-----------+ ring. |month.+-----------+ ring. |month|lin. ft.
+ |For | To | | |For |To | | |per
+ Month|month|date | | |month|date | | |month.
+ -----+-----+-----+----------+------+-----+-----+----------+-----+--------
+ 1905 | | | | | | | | |
+ May | | | | | | | | | 15.9
+ June | 24 | 24|260 + 76.6| 59.3 | 12 | 12|260 + 70.0| 30.0| 38.6
+ July | 12 | 36|260 + 46.6| 30.0 | 15 | 27|260 + 32.4| 37.6| 34.4
+ Aug | 15 | 51|260 + 09.1| 37.5 | 16 | 43|260 + 07.4| 25.0| 31.9
+ Sept | 1 | 52|260 + 06.6| 2.5 | 18 | 61|259 + 47.2| 60.2| 47.9
+ Oct | 10 | 62|259 + 81.5| 25.1 | 20 | 81|258 + 97.2| 50.0| 62.9
+ Nov | 29 | 91|259 + 09.0| 72.5 | 39 | 120|257 + 99.7| 97.5| 81.2
+ Dec | 46 | 137|257 + 94.0|115.0 | 77 | 197|256 + 07.1|192.6| 135.1
+ 1906 | | | | | | | | |
+ Jan | 77 | 214|256 + 01.4|192.6 | 73 | 270|254 + 24.6|182.5| 169.4
+ Feb | 133 | 347|252 + 68.6|332.8 | 165 | 435|250 + 11.7|412.9| 275.2
+ Mar | 142 | 489|249 + 13.3|355.3 | 111 | 546|247 + 34.0|277.7| 253.4
+ April| 32 | 521|248 + 33.3| 80.0 | 78 | 624|245 + 38.9|195.1| 195.7
+ May | 121 | 642|245 + 30.6|302.7 | 2 | 626|245 + 33.9| 5.0| 198.9
+ June | 162 | 804|241 + 25.3|405.3 | 157 | 788|241 + 41.1|392.8| 423.4
+ July | 113 | 917|238 + 42.4|282.9 | 118 | 901|238 + 45.9|295.2| 292.7
+ Aug | 138 |1,055|234 + 97.1|345.3 | 140 |1,041|234 + 95.8|850.1| 348.3
+ Sept | 55 |1,110|233 + 59.5|137.6 | 177 |1,218|230 + 52.8|443.0| 305.9
+ Oct | 1 |1,111|233 + 57.0| 2.5 | 94 |1,312|228 + 16.8|236.0| 125.3
+ Nov | 9 |1,120|233 + 34.1| 22.9 | | | | | 10.3
+ -----+-----+-----+----------+------+-----+-----+----------+-----+--------
+
+A ½-in. air line was taken direct from the working chamber to the
+recording gauges in the engine-room, which enabled the engine-room force
+to keep a constant watch on the air conditions below. To avoid undue
+rise of pressure, a safety valve was set on the air line at each lock,
+set to blow off if the air pressure rose above that desired. The
+compressor plant was ample, except, as before described, when passing
+the gravel section at Weehawken.
+
+Records were kept of the air supply, and it may be said here that the
+quantity of free air per man per hour was in general between 1,500 and
+5,000 cu. ft., though in the open gravel where the escape was great it
+was for a time as much as 10,000 cu. ft. For more than half the silt
+period it was kept between 3,000 and 4,000 cu. ft., but when it seemed
+proved beyond doubt that any quantity more than 2,000 cu. ft. had no
+beneficial effect on health, no attempt was made to deliver more, and on
+two separate occasions for two consecutive weeks it ran as low as 1,000
+cu. ft. without any increase in the number of cases of bends.
+
+The amount of CO_{2} in the air was also measured daily, as the
+specifications called for not more than 1 part of CO_{2} per 1,000 parts
+of air. The average ranged between 0.8 and 1.5 parts per 1,000, though
+in exceptional cases it fell as low as 0.3 and rose to 4.0. The air
+temperature in the tunnels usually ranged from 55° to 60° Fahr., which
+was the temperature also of the surrounding silt, though at times, in
+the earlier parts of the work when grouting extensively in long sections
+of the tunnel in rock, it varied from 85° to 110° Fahr.
+
+_Grouting._--Grout of one part of Portland cement to one part of sand by
+volume was forced outside the tunnel lining by air pressure through
+1½-in. tapped and plugged grout holes formed in each segment for this
+purpose, wherever the ground was not likely to squeeze in upon the metal
+lining as soon as this was erected. That is to say, it was used
+everywhere up to the river line; between river lines it was not used
+except at the New York bulkhead wall in order to fill voids in the
+rip-rap, and at the point of junction of the shields where the space
+between the metal lining and the shield skins outside it was grouted.
+Cow Bay sand was used, and it had to be screened to remove particles
+greater than 1/10 in. in diameter, which would choke the valves. For
+later grouting work, namely, in the top of the concrete lining inside
+the metal lining, Rockaway Beach sand was used. This is very fine, and
+did not need screening; it cost more, but the saving of screening and
+the non-blocking of valves, etc., resulted in a saving.
+
+The grout was mixed in a machine shown in Fig. 2, Plate XLI, which is a
+view of the grouting operation.
+
+The grout pipes were not screwed directly into the tapped hole in the
+segments, but a pipe containing a nipple and valve was screwed into the
+grout hole and the grout pipe screwed to the pipe. This prevented the
+waste of grout, enabled the valve to be closed and the grout pipe
+disconnected, and the pipe to be left in position until the grout had
+set. In the full rock section, 20 or 30 rings were put in without
+grouting; then the shield was stopped, the last two or three rings were
+detached and pulled ahead by the shield, a masonry stop-wall was built
+around the outside of the last ring left in, and the whole 20 or 30
+rings were grouted at one time. In the landward silt and gravel each
+ring had to be grouted as soon as the shield had left it, in order to
+avoid the flattening caused by the weight coming on the crown while the
+sides were as yet unsupported. The grout was prevented from reaching the
+tail of the shield by plugging up the space with empty cement bags,
+assisted by segmental boards held against the face of the leading ring
+by U-shaped clamps, fitting over the front circumferential flange of the
+ring and the boards, and tightened by wedges. The air pressure varied
+between 70 and 100 lb. per sq. in. above normal.
+
+The force consisted of one pipe-fitter and one or two laborers employed
+part of their time. When a considerable length was being grouted at a
+time, as in the full rock section, many laborers were employed for a
+short period.
+
+
+Transportation and Disposal.
+
+The transportation and disposal will be described under the following
+headings:
+
+ Receipt and Unloading of Materials,
+ Surface Transportation,
+ Tunnel Transportation,
+ Disposal.
+
+_Receipt and Unloading of Materials._--At the Manhattan Shaft the
+contractor laid a spur siding into the yard from the freight tracks of
+the New York Central Railroad, which immediately adjoins the yard on the
+west. There was also wharfage on the river front about 1,500 ft. away.
+
+At the Weehawken Shaft there were four sidings from the Erie Railroad
+and one from the West Shore Railroad. Access to the river was gained by
+a trestle direct from the yard, and Baldwin Avenue adjoined the yard.
+
+All the iron lining arrived by railroad. It was unloaded by derricks,
+and stacked so that it was convenient for use in the tunnel. The
+Manhattan derricks were a pair of steel ones with 39-ft. booms, worked
+by a 30-h.p., 250-volt, electric motor. There was also a stiff-leg
+derrick with 50-ft. boom, on a platform near the shaft, which was worked
+by a 40-h.p., 250-volt motor. At Weehawken there were two 45-ft. boom,
+stiff-leg derricks of 2 tons capacity, one worked by a 42-h.p.
+Lidgerwood boiler and engine, and the other by a 25-h.p., 250-volt,
+electric motor. These derricks were set on elevated trestles near the
+Erie Railroad sidings. There was a 50-ft. stiff-leg derrick with a
+70-h.p. Lidgerwood boiler and engine near the cement warehouse on the
+West Shore Railroad.
+
+The storage area for iron lining was 1,800 sq. ft. at Manhattan and
+63,000 sq. ft. at Weehawken; the maximum quantity of lining in storage
+at any one time was 150 rings at Manhattan and 1,200 rings at Weehawken.
+
+The cement, which was issued and sold by the Company to the contractor,
+was kept in cement warehouses; that at the New York side was at Eleventh
+Avenue and 38th Street, or some 1,200 ft. from the shaft, to which it
+was brought by team; that at Weehawken was adjacent to the shaft, with a
+2-ft. gauge track throughout it and directly connected with the shaft
+elevator.
+
+_Surface Transportation._--In the early days the excavation was handled
+in scale-boxes of 1 cu. yd. capacity which were hoisted up the shafts by
+a derrick, but, when the iron period began, two-cage elevators were put
+in at each shaft. They were worked by a single, friction-drum,
+Lidgerwood, steam hoisting engine of 40 h.p.
+
+All materials of construction were loaded on cars on the surface at the
+point where they were stored, and hauled on these to the elevators,
+sent down the shaft, and taken along the tunnels to the desired point
+without unloading.
+
+The narrow-gauge railway on the surface and in the tunnel was of 2-ft.
+gauge with 20-lb. rails. About 70 flat cars and 50 mining cars were used
+at each shaft. On the surface at Manhattan these were moved by hand, but
+at Weehawken, where distances were greater, two electric locomotives on
+the overhead trolley system were used.
+
+_Tunnel Transportation._--The mining cars shown in Fig. 19 were of 1¼
+cu. yd. capacity. The short wheel base and unbalanced loading caused a
+good many upsets, but they were compact, easily handled, and could be
+dumped from either side or end.
+
+[Illustration: MUCK CAR (AS USED IN RIVER TUNNELS) CAPACITY 5,000 LBS.
+OR 1¼ CU. YD. FIG. 19.]
+
+The flat cars shown in Fig. 20 were of 3 tons capacity, and could hold
+two tunnel segments. As the working face was down grade from the shafts,
+the in-bound cars were run by gravity. For out-bound cars a cable
+haulage system was used, consisting of double-cylinder, Lidgerwood,
+single friction-drum, hoisting engines (No. 32) of 6 h.p., with
+cylinders 5 in. in diameter and 6 in. stroke and drums 10 in. in
+diameter. These were handily moved from point to point, but, as there
+was no tail rope, several men had to be used to pull the cable back to
+the face. After the second air-lock bulkhead walls had been built, a
+continuous-cable system, worked electrically, was put in each tunnel
+between the first and second air-locks.
+
+The engine consisted of an electric motor driving a 3-ft. 6-in. drum
+hoist around which a ¾-in. steel wire cable passed three times. The
+cable was led around a sheave, down the tunnel on the right side of the
+in-bound track, and returned on the left side of the out-bound track. It
+was then carried around a set of sheaves, where a tension of 1,000 lb.
+was supplied by a suspended weight which acted on a sheave with a
+sliding axle on the tension carriage. The cable was supported throughout
+its length on 8-in. pulleys set in the floor at 50-ft. intervals. All
+the guide sheaves were 36 in. in diameter.
+
+[Illustration: FLAT CAR FOR TUNNEL SEGMENTS CAPACITY 6,000 LBS. FIG.
+20.]
+
+Each car was attached to the cable by a grip at its side. This was
+fastened and unfastened by hand, but was automatically released just
+before reaching the turn in the cable near each lock. This system could
+haul without difficulty an unbalanced load of 10 muck cars, spaced 100
+ft. apart, up a 2% grade. The cable operated over about 1,000 ft. of
+tunnel, the motor being placed at the top of the grade. The driving
+motor was of the semi-armored, 8-pole, series-wound type, rated at 25
+h.p., 635 rev. per min., and using direct current at 220 volts. The
+speed of handling the cars was limited by their having to pass through
+the air-locks on a single track. As many as 106 cars have been hauled
+each way in one 8-hour shift.
+
+_Disposal._--At Manhattan the tunnel muck was carried from the elevator
+over the upper level of the yard trestle and dumped into bins on the 33d
+Street side, whence it was teamed to the public dump at 30th Street and
+North River. At Weehawken the rock excavation was removed by the Erie
+Railroad on flat cars on which it was dumped by the tunnel contractor,
+but all the silt muck was teamed away to some marshy ground where
+dumping privileges were obtained.
+
+The typical forces employed on transportation were as follows:
+
+_Receipt and Unloading of Material: Surface Transportation and
+Disposal._
+
+At Manhattan Shaft, on 10-hour shifts:
+
+ 2 Engineers on derricks. @ $3.00 per day.
+ 2 Foremen. " 3.25 " "
+ 15 Laborers loading and unloading iron. " 1.75 " "
+ 7 Laborers on disposal. " 1.75 " "
+ 6 Teams. " 7.50 " "
+
+At Weehawken Shaft, on 10-hour shifts:
+
+ 3 Engineers on derricks and locomotives. @ $3.00 per day.
+ 16 Laborers loading and unloading iron. " 1.75 " "
+ 3 Foremen. " 3.50 " "
+ 11 Laborers on disposal. " 1.75 " "
+ 6 Teams on disposal. " 6.50 " "
+
+Tunnel Transportation (Including Shaft Elevator):
+
+Shaft elevators and to and from the first air-lock on 10-hour shift:
+
+ 2 Engineers. @ $3.00 per day.
+ 2 Signalmen. " 2.00 " "
+ 1 Foreman. " 3.00 " "
+ 12 Laborers. " 1.75 " "
+
+Between first lock and working face, on 8-hour shifts, the force varied:
+
+ From 1 to 3 (average 2) Hoist engineers @ $3.00 per day.
+ From 0 to 2 (average 1) Lockman " 2.75 " "
+ From 1 to 2 (average 2) Trackmen " 3.00 " "
+ From 2 to 7 (average 4) Cablemen
+ (pulling back cable) " 3.00 " "
+
+_Pumping._--The water was taken out of the invert by a 4-in. blow-pipe
+which was always kept up to a point near the shield and discharged into
+the sump near the shaft.
+
+When the air pressure was removed and the blow-pipe device,
+consequently, was unavailable, small Cameron pumps, driven by compressed
+air, and having a capacity of about 140 gal. per hour, were used, one
+being set up wherever it was necessary to keep the invert dry; for
+example, at points where caulking was in progress.
+
+_Lighting._--The tunnels were lighted by electricity, the current being
+supplied, at a pressure of 250 volts, from the dynamos in the
+contractor's power-house.
+
+Two 0000 wire cables were used as far as the second air-locks, about
+1,650 ft. from the power-house, on each side; and beyond that point, to
+the junction of the shields (about 1,750 ft.), 00 and 0 wires were used.
+These cables also carried the current for the cable haulage system. Two
+rows of 16-c.p. lamps, provided with reflectors, were used in each
+tunnel; one row was along the side just above the axis, with the lights
+at about 30-ft. intervals; the other along the crown, with the lamps
+halfway between the side lamps, also at 30-ft. intervals. At points
+where work was in progress three groups of 5 lights each were used. The
+tunnels as a whole were well lighted, and in consequence work of all
+kinds was much helped.
+
+_Period No. 2._--_Caulking and Grummeting._--_November, 1906, to June,
+1907._--After the metal lining had been built completely across the
+river in both tunnels, the work of making it water-tight was taken up.
+This consisted in caulking into the joints between the plates a mixture
+of sal-ammoniac and iron borings which set up into a hard rusty mass,
+and in taking out each bolt and placing around the shank under the
+washer at each end a grummet made of yarn soaked in red lead. These
+grummets were made by the contractor on the works, and consisted of
+three or four strands of twisted hemp yarn, known as "lath yarn," making
+up a rope-like cross-section about ¼ in. in diameter. Usually, one of
+these under each washer was enough, but in wet gravel, or where bolts
+were obliquely in the bolt-holes, two were used at each end. After
+pulling the grummets in, all the nuts were pulled up tight by wrenches
+about 3 ft. long, with two men on one wrench. Bolts were not passed as
+tight unless the nut resisted the weight of an average man on a
+2½-ft. wrench.
+
+Before putting in the caulking mixture, the joints were carefully
+scraped out with a special tool, cleaned with cotton waste, and washed
+with a stream of water. The usual mixture for sides and invert was about
+2 lb. of sal-ammoniac and 1 lb. of sulphur to 250 lb. of iron filings or
+borings. In the arch, 4 lb. of sal-ammoniac and 3 lb. of sulphur to 125
+lb. of filings was the mixture. A small hand-hammer was used to drive
+the caulking tool, but, in the sides and invert, air hammers were used
+with some advantage. The success of work of this kind depends entirely
+on the thoroughness with which the mixture is hammered in; and the
+inspection, which was of an exceedingly monotonous nature, called for
+the greatest care and watchfulness on the part of the Company's forces,
+especially in the pocket iron, where each bolt had to be removed, the
+caulking done at the bottom of the pockets put in, the bolts replaced;
+and the rest of the pockets filled. The results have been satisfactory,
+as the leakage under normal air and prior to placing the concrete
+averaged about 0.14 gal. per lin. ft. of tunnel per 24 hours, which is
+about 0.0035 gal. per lin. ft. of joint per 24 hours. With each linear
+foot of joint is included the leakage from 1.27 bolts. Afterward, when
+the concrete lining was in, the leakage was found to be about 0.05 to
+0.06 gal. per lin. ft. of tunnel per 24 hours, which compares favorably
+with the records of other lined tunnels. The typical gang employed on
+this work was as follows:
+
+_In Pocket Iron:_
+
+ 1 General foreman @ $5.00 per day.
+ 1 Mixer " 3.00 " "
+ 1 Nipper " 3.00 " "
+ 5 Caulkers " 3.00 " "
+ 10 Grummeters " 3.00 " "
+
+_In Pocketless Iron:_
+
+ 1 General foreman @ $5.00 per day.
+ 1 Mixer " 3.00 " "
+ 1 Nipper " 3.00 " "
+ 3 Caulkers " 3.00 " "
+ 12 Grummeters " 3.00 " "
+
+The average amount of caulking and grummeting done per shift with such a
+gang was (with pocketless grooves), 348 lin. ft. of joint and 445 bolts
+grummeted; and in pocket iron: 126 lin. ft. of joint and 160 bolts
+grummeted.
+
+The caulking and grummeting work was finished in June, 1907, this
+completing the second period.
+
+_Period No. 3._--_Experiments, Tests, and Observations._--_April, 1907,
+to April, 1908._--The third period, that of tests and observations in
+connection with the question of foundations, is dealt with in another
+paper. It occupied from April, 1907, to November, 1908. The results of
+the information then gathered was that it was not thought advisable to
+go on with the foundations.
+
+_Period No. 4._--_Capping Pile Bores, Sinking Sumps, and Building
+Cross-Passages._--_April, 1908, to November, 1908._--In order to reduce
+the leakage from the bore segments to the least possible amount before
+placing the concrete lining, it was decided to remove the plugs and
+replace them with flat cover-plates; these have been described before,
+together with the filling of Bore Segments No. 2 with mortar to reduce
+the leakage around the distance piece.
+
+During this period the turnbuckles to reinforce the broken plates were
+put in, and the sump sunk at the lowest point of the tunnel. These sumps
+have been described in a previous part of this paper; they were put down
+without trouble. As much as possible of the concrete lining was put in
+before the lining castings were taken into the tunnel, as the space
+inside was very restricted. The first lining casting was bolted to the
+flat flanges of the sump segment, the bolts holding the latter to the
+adjacent segments were removed, and the whole was forced down with two
+of the old shield jacks, taking a bearing on the tunnel. The two
+together exerted a pressure of about 150 tons. The plugs in the bottom
+of the sump segment were taken out, and pipes were put in, through which
+the silt squeezed up into the tunnel and relieved the pressure on the
+sump segment.
+
+If the silt did not flow freely, a water-jet was used. The sump was kept
+plumb by regulating the jacks. In this way the sump was sunk, adding
+lining sections one by one, and finally putting on the top segment,
+which was composed of three pieces.
+
+The time taken to sink one sump was about 4 days, working one 8-hour
+shift per day, and not counting the time taken to set up the jacks and
+bracing. The sinking of each section took from 4 to 6 hours. The air
+pressure was 25 lb. and the hydrostatic head 41 lb. per sq. in. The
+force was 1 assistant superintendent at $6.00 per day, 1 foreman at
+$4.50, and 6 laborers at $3.00 per day.
+
+_Cross-Passages._--It was during this period that the five
+cross-passages previously mentioned were built. In the case of those in
+the rock, careful excavation was needed so as to avoid breaking the iron
+lining. Drilling was done from both ends, the holes were closely spaced,
+and about 2 ft. 6 in. deep, and light charges of powder were used. The
+heading, 5 by 7 ft. in cross-section, was thus excavated in five
+lengths, with 24 holes to a length, and about 23 lin. ft. of hole per
+yard. About 5.3 lb. of powder per cu. yd. was used. The sides, top, and
+bottom were then drilled at a very sharp angle to the face and the
+excavation was trimmed to the right size. This widening out took about
+7½ ft. of hole per cu. yd., and 0.9 lb. of powder.
+
+In the passages in silt the excavation had to be 12 ft. wide and 13 ft.
+8 in. high to give enough room inside the timbers. The plates at one end
+of the passage were first removed. An air pressure of 17 lb. was
+carried, which was enough to keep the silt from squeezing in and yet
+left it soft enough to be chopped with a spade.
+
+A top heading, of full width and 6 ft. 8 in. high, was first taken out,
+and the roof was sheathed with 2-in. boards held by 10 by 10-in. head
+trees at 3-ft. centers, with 10 by 10-in. side trees. The lower 7 ft. of
+bench was then taken out, a tight floor of 6 by 6-in. cross-timber was
+put in, and also longer side trees, the head trees being temporarily
+held by two longitudinal 10 by 10-in. stringers blocked in place. The
+bulk of the space between the side trees was filled with 10 by 10-in.
+posts and blocking. The plates at the other end of the passage were then
+taken out from the other tunnel.
+
+After the excavation was out, the outer reinforced concrete lining was
+built. Rough forms were used, as the interior surfaces of the passages
+were to be rendered with a water-proofing cement. A few grout pipes
+were built in, and all voids outside the concrete were grouted. Grouting
+was also done through the regular grout holes of the metal lining around
+the openings.
+
+In the case of the most westerly of the cross-passages at Weehawken,
+which was in badly seamed rock carrying much water, a steel
+inter-lining, rather smaller than the concrete, was put in. The space
+between the concrete and the steel was left open, so that water coming
+through the concrete lining was stopped by the steel plate. This water
+was led back to the shield chamber in a special drain laid in the bench
+of the river tunnel and behind the ducts. From the shield chamber the
+water ran with the rest of the drainage from the Weehawken Land Tunnels
+to the Weehawken Shaft sump.
+
+[Illustration: TYPICAL CROSS-SECTIONS SHOWING SUCCESSIVE STAGES IN
+PLACING CONCRETE IN RIVER TUNNELS FIG. 21.]
+
+_Period No. 5._--_Placing the Concrete Lining._--_November, 1908, to
+June, 1909._--During the fifth period the concrete lining was put in.
+This lining was placed in stages, as follows: First, the invert; second,
+the duct bench; third, the arch; fourth, the ducts; and fifth, the face
+of the bench. This division can be seen by reference to Fig. 21.
+
+All the work was started on the landward ends and carried toward the
+middle of the river from both sides. Except where the Weehawken force
+passed the lowest point of the tunnel, which is at Station 241 or nearly
+900 ft. to the west of the middle of the river, all the work was down
+grade.
+
+Before any concrete was placed, the surface of the iron was cleaned with
+scrapers and wire brushes, and washed with water. Any leaks in the
+caulking and grummeting (finished by June, 1907, and therefore all more
+than 12 months old) were repaired. All the grout hole plugs were
+examined, and the plugs in any leaking ones were taken out, smeared
+with red lead, and replaced. The leakage in the caulking was due to the
+fact that the tunnel had been settling slightly during the whole 12
+months of pile tests, and, therefore, had opened some of the joints.
+After the caulking had been repaired and the surface thoroughly cleaned,
+the flanges were covered with neat cement (put on dry or poured on in
+the form of thick grout) just before the concrete was placed.
+
+_Invert Concrete._--The form used for the landward type of concrete,
+that is, the one with a middle drain, consisted of a frame made of a
+pair of trussed steel rails on each side of the tunnel and connected at
+intervals with 6 by 6-in. cross-timbers; two "wing forms" were hung from
+this frame by adjustable arms. These wings formed the curved sides of
+the invert, the lip, and the form for the middle drain. The whole form
+was supported on three wheels, two on the rear end running on a rail
+laid on the finished concrete, and the third in front attached to the
+frame by a carriage and running on a rail temporarily laid on the iron
+lining. The form was braced from the iron lining by 6 by 6-in. blocks.
+
+For the soft-ground type of invert, namely, the one without the middle
+drain, a form of the same general type was used, except that the form
+for the middle drain was removed. After the form had been in use for
+some time, "key pieces" (made of strips of wood about 1 ft. 3 in. in
+length and 3 by 3 in. in cross-section) were nailed circumferentially on
+the under side of the wings at 2-ft. intervals. This was done because,
+at the time, it was not known whether ballasted tracks or some form of
+rigid concrete track construction would be adopted, and, if the latter,
+it was desirable not to have the surface smooth.
+
+The concrete was received in cars at the rear end of the form and dumped
+on a temporary platform. It was then loaded into wheel-barrows on the
+runways, as shown in Fig. 22. The concrete was thrown from the barrows
+into the invert, where it was spaded and tamped.
+
+In cases where there was steel-rod reinforcement, the concrete was first
+brought up to the level of the underside of these rods, which came
+between the wings; the rods were laid in place, and then more concrete
+was placed over the rods and brought up to the level of the bottom of
+the wings. Where there was no reinforcement, the concrete was brought up
+in one lift.
+
+[Illustration: CONCRETE FORM STANDARD IN RIVER TUNNELS FIG. 22.]
+
+After this was finished, the concrete behind the wings was placed,
+thoroughly spaded and tamped, and, where there were longitudinal
+reinforcing rods, these were put in at their proper level. Where there
+were circumferential rods, the 16-ft. rods had already been put in when
+the lower part of the concrete was placed. As the invert was being
+finished off, the 8-ft. rods were embedded and tied in position.
+
+The longitudinal rods were held in place at the leading end of each
+length of arch by the wooden bulkhead, through which holes were drilled
+in the proper position. At the rear end they were tied to the rods
+projecting from the previous length. The quantity of water used in
+mixing the invert concrete needed very nice adjustment; if too wet, the
+middle would bulge and rise when the weight of the sides came on it;
+and, if too dry, it would not pack properly between the flanges of the
+iron lining. The difficulties as to this were often increased by the
+flow of accumulated leakage water from the tunnel behind on the concrete
+while it was being put in. To prevent this, a temporary dam of sand bags
+was always built across the last length of finished invert concrete
+before beginning a new length. A sump hole, about 4 by 1 ft. and 1 ft.
+deep, was left every 800 ft. along the tunnel, and a small Cameron pump
+was put there to pump out the water.
+
+The invert forms were left in place about 12 hours after the pour was
+finished. The average time taken to fill a length of 30 feet was 7
+hours, the form was then left 12 hours, and it took 2 hours to set it up
+anew. The total time for one length, therefore, was 21 hours, equal to
+34 ft. per 24 hours. At one place, a 45-ft. form was used, and this gave
+an average speed of 45 ft. per 24 hours.
+
+An attempt was made to build the invert concrete without forms (seeing
+that a rough finish was desired, as previously explained, to form a key
+for possible sub-track concrete), but it proved a failure.
+
+The typical working force (excluding transport) was as follows:
+
+ 1 Foreman @ $3.25 per shift.
+ 2 Spaders " 2.00 " "
+ 9 Laborers " 1.75 " "
+
+The average time taken to lay a 30-ft. length of invert was 7 hours; the
+two spaders remained one hour extra, smoothing off the surface.
+
+For setting the form, the force was:
+
+ 1 Foreman @ $4.50 per shift.
+ 5 Carpenters " 3.25 " "
+ 6 Carpenters' helpers " 2.25 " "
+
+The average time taken to erect a form was 2 hours, 1 carpenter and 1
+helper remaining until the concrete was finished.
+
+_Duct Bench Concrete._--The duct bench (as described previously) is the
+portion of the concrete on which the ducts are laid. The exact height of
+the steps was found by trial, so as to bring the top of the ducts into
+the proper position with regard to the top and the face of the bench.
+
+Both kinds of duct bench forms were of the same general type. A drawing
+of one of them is shown on Plate XLII. The form consisted of a skeleton
+framework running on wheels on a track at the level of the temporary
+transportation tracks. The vertical faces of the steps were formed by
+boards supported from the uprights by adjustable arms. The horizontal
+surfaces were formed by leveling off the concrete with a shovel at the
+top of the vertical boards. Where the sheets of expanded metal used for
+bonding came at a step, the lower edge of the boards forming the back of
+the step was placed 1 in. above the one forming the front of it; but,
+when the expanded metal came in the middle of a step, a slot 1 in. wide
+was left at that point to accommodate it.
+
+A platform was formed on the top of the framework for the form, and on
+this a car forming a sort of traveling stage was run. There was ample
+room to maintain traffic on a single track through the form. A
+photograph of the form is shown in Fig. 1, Plate XLIII.
+
+The concrete, for the most part, was received at the form in ¾-cu. yd.
+dumping buckets. The buckets were lifted by the rope from a small
+hoisting engine. This rope passed over a pulley attached to the crown of
+the tunnel and dumped into the traveling stage on the top of the form.
+In this the concrete was moved along to the point where it was to be
+deposited, and there it was thrown out by shovels into the form below.
+For a portion of the period, while the duct bench concrete was being
+laid, it was not necessary to maintain a track for traffic through the
+form and, during that period, the concrete for the lower step was placed
+from below the form, the concrete being first dumped on a temporary
+stage at the lower track level.
+
+Owing to the horizontal faces of the steps being uncovered, there was a
+tendency for the concrete there to rise when concrete was placed in the
+steps above. For this part of the work, also, it was necessary to see
+that the concrete was not mixed too wet, for, when that was the case,
+the concrete in the upper steps was very apt to flow out at the top of
+the lower one. At the same time, there was the standing objection to the
+mixture being too dry, namely, the responsibility of getting a
+sufficient amount of spading and tamping done. Particulars of the exact
+quantity of water used are given later in describing "Mixing." Fig. 2,
+Plate XLIII, illustrates the process of laying.
+
+In the section of the tunnel in which there were circumferential
+reinforcement rods in the duct bench, the rods were in place before the
+laying commenced, as they had been placed with the invert concrete. The
+circumferential reinforcing rods in the arch came down into the upper
+part of the duct bench concrete; these rods were put in position and
+tied to the iron lining in the crown at the same time as the duct bench
+concrete was being finished off. Openings for the manholes were left in
+the duct bench at the regular stationing.
+
+The average time taken to fill a length of 35 ft. was about 6 hours; the
+form was then left in position for about 8 hours--usually enough to let
+the concrete set properly--and then moved ahead; it then took about 3
+hours to set it up again ready to continue work. The total time for a
+length, therefore, was about 17 hours, equal to an average progress of
+about 49 ft. per day. The average force engaged in duct bench concrete
+(not including transport) was:
+
+ 1 Foreman @ $3.25 per day.
+ 2 Spaders " 2.00 " "
+ 9 Laborers " 1.75 " "
+
+_Arch Concrete._--By far the greater part of the arch work was put in
+with traveling centers before the face of the bench was built, in which
+case the whole of the arch was built at once. A short length of arch at
+each end of the tunnel was built after the face of the bench, in which
+case the haunches or lower 5 ft. were laid first and the upper part of
+the arch later.
+
+The first traveling centers were used on the New York side, and were 50
+ft. long. The laggings were of 4-in. yellow pine, built up in panels 10
+ft. long and 16 in. wide for the sides, and solely longitudinal lagging
+5 ft. long for the key.
+
+It was pretty certain that the results to be obtained from forms of such
+a length would not be satisfactory, and this was pointed out to the
+contractor, who, however, obtained permission to use them on trial.
+Grout pipes were built in, as it was not likely that the concrete could
+be packed tightly into the upper part of the lining.
+
+[Illustration: PLATE XLIII. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 1.]
+
+[Illustration: PLATE XLIII. TRANS. AM. SOC. CIV. ENGRS. VOL. LXVIII, No.
+1155. HEWETT AND BROWN ON PENNSYLVANIA R. R. TUNNELS: NORTH RIVER
+TUNNELS. FIG. 2.]
+
+After about 300 lin. ft. of arch had been built with these forms, a test
+hole was cut out and large voids were found, and, to confirm this,
+another hole was cut, and similar conditions observed.
+
+The results were so unsatisfactory that orders were given that the use
+of longitudinal key lagging should be discontinued, and cross or block
+lagging used instead. These block laggings were 6 in. in length (in the
+direction of the tunnel) and 2 ft. in width; at the same time, the
+system of grout pipes was changed. This will be described later under
+"Grouting." It was soon found that with block lagging a better job could
+be made of packing the concrete up into the keys, but the time taken to
+"key up" a 50-ft. length was so great that the rest of the arch had set
+by the time the key was finished. Despite a lot of practice, this was
+the case, even in the unreinforced type. When the reinforcing rods were
+met, the time for keying up became still greater, and therefore the
+contractor was directed to shorten the forms to 20-ft. lengths. A
+typical working force for a 50-ft. length was:
+
+ 1 Foreman @ $3.25 per day.
+ 4 Spaders " 2.00 " "
+ 12 Laborers " 1.75 " "
+
+Details of the 20-ft. forms are shown on Plate XLIV. The lower 4 ft. of
+lagging was built on swinging arms, which could be loosened to allow the
+centers to be dropped and moved ahead. The rest of the lagging was built
+up in panels 10 ft. long and 1 ft. 4 in. high. The ribs rested on a
+longitudinal timber on each side; these were blocked up from the top
+step of the duct bench concrete. When the form was set, or when it was
+released, it was moved ahead on rollers placed under it.
+
+The concrete was received at the form in ¾-cu. yd. dumping buckets;
+from the flat cars on which they were run, these were hoisted to the
+level of the lower platform of the arch form. At this level the concrete
+was dumped on a traveling car or stage, and moved in that to the point
+on the form where it was to be placed. For the lower part of the arch,
+the concrete was thrown directly into the form from this traveling
+stage, but, for the upper part, it was first thrown on the upper
+platform of the arch. The hoisting was done by a small Lidgerwood
+compressed-air hoister, and set up on an overhead platform across the
+tunnel. The pulley over which the cable from the hoister passed was
+attached to the iron lining near one end of the form, and the traveling
+stage ran back from the arch form on a trailer, shown on Plate XLIV.
+When it was impossible to hang a pulley--owing to the concrete arch
+having been built at the point where the trailer stood--an =A=-frame was
+built on the trailer, and the pulley was attached to that.
+
+In laying the lower part of the arch, about 1 ft. of lagging (including
+the swinging arms) was first set, the other panels being pulled up
+toward the top of the arch. When that was filled, the next panel above
+was lowered into place, and the work continued. As the concrete rose
+toward the key, it was packed up to a radial surface, so that the arch
+would not be unduly weakened if the sides set before the key was placed.
+All the time, great care was taken to see that the concrete was
+carefully packed into the segments of the metal lining. The quantity of
+water used in the concrete was carefully regulated, more being used in
+the lower than in the upper parts of the arch.
+
+In places where there were no reinforcing rods, the width of the
+concrete key was the length of the block lagging, namely, 2 ft. Where
+there was circumferential reinforcement, the key had to be more than 5
+ft. wide, in order to take the 5-ft. closure rods used in the key. This
+naturally increased the time of keying very much. On the places where
+the 5-ft. longitudinal laggings were used, it was impossible to fill the
+flanges of the metal lining much higher than their undersides.
+
+As the concrete used in the key had to be much drier than that used
+elsewhere, it was not easy to get a good surface. This trouble was
+overcome by putting a thin layer of mortar on the laggings just before
+the concrete was put in.
+
+The overhead conductor pockets were a great hindrance to the placing of
+the key concrete, especially where the iron was below true grade.
+Whenever an especially troublesome one was met, a special grout pipe was
+put in to fill up unavoidable holes by grouting after the concrete had
+set. All the circumferential reinforcing rods were bent in the tunnel by
+bending them around a curved form of less diameter than the required
+bend. This generally left them all right in the middle of their length,
+but with their end portions too straight; in such cases the ends were
+bent again. All rods were compared with a template before being passed
+for use.
+
+The arch forms were left up for 48 hours after keying was finished.
+Levels taken after striking the forms showed that no appreciable
+settlement occurred. An average gang for a 20-ft. length of arch was:
+
+ 1 Foreman @ $3.25 per shift.
+ 2 Spaders " 2.00 " "
+ 10 Laborers " 1.75 " "
+
+Table 30 shows the progress attained under various conditions.
+
+Whenever the face of the bench concrete was constructed before the arch,
+the latter was built in two separate portions, that is, the bottom 5
+ft., or "haunches" of the arch, as they were termed, were built on each
+side and the rest of the arch later. This involved the use of two
+separate sets of forms, namely, for the haunch and for the arch. Not
+very much arch was built in this way, and, as the methods were in
+principle precisely the same as those used when all the arch was built
+in one operation, no detailed description is needed.
+
+No provision was made in the contract for grouting the concrete arch,
+but it soon became evident that by ordinary methods the top part of the
+concrete could not be packed solid against the iron segments, especially
+in the keys. As it was imperative to have the arch perfectly solid, it
+was determined to fill these unavoidable gaps with a 1:1 Portland cement
+grout, at the same time making every effort to reduce the spaces to a
+minimum. This made it necessary to build grout pipes into the concrete
+as it was put in.
+
+The first type of grout pipe arrangement is shown as Type _A_, in Fig.
+23. This was used with the longitudinal key laggings; when this method
+was found to be no good, and cross-laggings were used, the system shown
+as Type _B_, in Fig. 23, was adopted, in which vents were provided to
+let out the air during grouting. The expense of these pipes was high,
+and the contractor obtained permission to use sheet-iron tubes, which,
+however, were found to be unsuitable, so that the screwed pipes were
+used again. The contractor next obtained permission to try dispensing
+altogether with the vent pipes, and so Type _C_, in Fig. 23 was evolved.
+This, of course, was found to be worse than any of the other systems, as
+the imprisoned air made it impossible to force grout in. Several other
+modifications were made, and are shown in Fig. 23.
+
+It was then decided to devise as perfect a system as possible, without
+allowing the question of cost to be the ruling factor, and to use that
+system throughout. In this system, shown as Type _S_, in Fig. 23, most
+of the vent pipes were contained in the concrete, and their size was
+independent of the thickness of the arch, so that they were easily
+fixed in position and not subject to disturbance while placing the
+concrete. This system was used for about 80% of the total length of the
+tunnel, and proved entirely satisfactory. The machine used for grouting
+was the same as that used for grouting outside the metal lining.
+
+TABLE 30.--AVERAGE TIME TAKEN FOR VARIOUS OPERATIONS CONNECTED WITH
+BUILDING CONCRETE ARCHES IN SUBAQUEOUS TUNNELS.
+
+ ==========+=============+========+================+=========+=========+
+ Average |Type of |Length |Time, in hours, |Time, |Time, |
+ time |reinforcement|of |moving and |in hours,|in hours,|
+ in hours, | |section,|erecting forms. |placing |placing |
+ form stood| |in | |concrete |concrete |
+ after | |feet. | |in arch. |in key. |
+ filing. | | | | | |
+ | | | | | |
+ ----------+-------------+--------+----------------+---------+---------+
+ 70 | { A | } 50 | 20 | 15 | 15.40 |
+ | {day work | } | ______/\______ | | |
+ | | |/ \| | |
+ | { A | } |Moving Erecting| | |
+ | {day work | } 20 | 2 3 | 8.30 | 2.40 |
+ | | | | | |
+ 53 | { B | } | | | |
+ | {day work | } 20 | 2 3 | 10.40 | 11.20 |
+ | | | | | |
+ 58 | { C | } | | | |
+ | {day work | } 20 | 2 3 | 11.00 | 7.20 |
+ | | | | | |
+ 58 | { D | } | | | |
+ | {day work | } 20 | 2 3 | 9.30 | 4.35 |
+ | | | | | |
+ 53 | { D | } | | | |
+ | {day work | } 20 | 2 3 | 6.15 | 2.05 |
+ | | | | | |
+ 53 | {Sub-Type | } 20 | 2 3 | 6.00 | 3.00 |
+ | No. 1 | } | | | |
+ | piece work | } | | | |
+ ==========+=============+========+================+=========+=========+
+
+ ==========+=========+===========+===========+============
+ Average |Time, |Total Time |Total time |Remarks.
+ time |in hours,|in hours, |in hours, |
+ in hours, |placing |for moving,|per linear |
+ form stood|concrete |erecting, |foot, |
+ after |in key |and filling|for moving,|
+ filing. |and arch | |erecting, |
+ | | |and filling|
+ ----------+---------+-----------+-----------+------------
+ 70 | 30.40 | 50.40 | 1.01 |
+ | | | |
+ | | | |
+ | | | |
+ | 11.10 | 16.10 | 0.50 |
+ | | | |
+ 53 | | | |Includes
+ | 22.10 | 27.00 | 1.35 |placing rods
+ | | | |
+ 58 | | | |
+ | 18.20 | 23.20 | 1.16 | do.
+ | | | |
+ 58 | | | |
+ | 14.25 | 19.25 | 0.91 | do.
+ | | | |
+ 53 | | | |
+ | 8.20 | 13.20 | 0.05 | do.
+ | | | |
+ 53 | 9.00 | 14.00 | 0.70 | do.
+ | | | |
+ | | | |
+ ==========+=========+===========+===========+============
+
+[Illustration: FIG. 23.]
+
+The only compressed air available was the high-pressure supply, at about
+90 lb.; a reducing valve, to lower this pressure to 30 lb. was used
+between the air line and the grouting machine. This was thought to be
+about as high a pressure as the green concrete arch would stand, and,
+even as it was, at one point a section about 2 ft. by 1 ft. was blown
+out.
+
+A rough traveling stage resting on the bottom step of the duct bench
+concrete was used as a working platform. In the earlier stages of the
+work the grouting was carried on in a rather haphazard manner, but, when
+the last system of grout and vent pipes was adopted; the work was
+undertaken systematically, and was carried out as follows:
+
+Two 20-ft. lengths of arch were grouted at one time, and, in order to
+prevent the grout from flowing along the arch and blocking the pipes in
+the next lengths, a bulkhead of plaster was made at the end of every
+second length to confine the grout.
+
+After a section had been grouted, test holes were drilled every 50 ft.
+along the crown to see that all the voids were filled; if not, holes
+were drilled in the arch, both for grouting and for vents, and the
+faulty section was re-grouted. An average of ¾ bbl. of cement and an
+equal quantity of sand was used per linear foot of tunnel. The average
+amount put in by one machine per shift was 15 bbl., and therefore the
+average length of tunnel grouted per machine per shift was 20 ft. The
+typical working force was:
+
+ 1 Foreman @ $3.75 per shift
+ 1 Laborer running grout machine " 2.00 " "
+ 2 Laborers handling cement and sand. " 1.75 " "
+ 1 Laborer tending valve and grout pipes " 1.75 " "
+
+After the grouting was finished, the arches were rubbed over with wire
+brushes to take off discoloration, and rough places at the junctions of
+adjoining lengths or left by the block laggings were bush-hammered.
+
+_Face of Bench Concrete._--The form used for this portion of the work is
+shown on Plate XLV. It consisted of a central framework traveling on
+wheels, and, from the framework, two vertical forms were suspended, one
+on each side, and equal in height to the whole height of the bench.
+Adjusting screws were fitted at intervals both at top and bottom, and
+thus the position of the face forms could be adjusted accurately. The
+face forms were built very carefully of 3-in. tongued and grooved yellow
+pine, and one 50-ft. form was used for 3,000 ft. of tunnel without
+having the face renewed. Great care was taken to set these forms true to
+line and grade, as the appearance of the tunnel would have been ruined
+by any irregularity. Joints between successive lengths were finished
+with a =V=-groove.
+
+The concrete was received at the form in dumping buckets; these were
+hoisted to the top of the form by a Lidgerwood hoister fixed to a
+trailer. The concrete was placed in the form by shoveling it from the
+traveling stage down chutes fitted to its side. The quantity of water to
+be used in the mixture needed careful regulation. The first few batches
+in the bottom had to be very wet, and were made with less stone than the
+upper portion, in order that the concrete would pack solidly around the
+niche box forms and other awkward corners.
+
+The forms for the ladders and refuge niches were fastened to the face of
+the bench forms by bolts which could be loosened before the main form
+was moved ahead, and in this way the ladder and niche forms were left in
+position for some time after the main form was removed.
+
+At first the forms were kept in place for 36 hours after finishing a
+length, but, after a little experience, 24 hours was found to be enough.
+In the summer, when the rise of temperature quickened the set, the time
+was brought down to 18 hours. The average time taken for a 50-ft. length
+was:
+
+ Laying concrete 4½ hours.
+ Interval for setting 18 "
+ Moving forms ahead and resetting 5 "
+ -------
+ Total 27½ hours.
+
+The typical working gang was:
+
+_Laying Concrete._
+
+ 1 Foreman @ $3.25 per shift.
+ 2 Spaders " 2.00 " "
+ 8 Laborers " 1.75 " "
+
+_Moving and Setting Forms._
+
+ 1 Foreman @ $4.00 per shift.
+ 10 Laborers " 1.75 " "
+
+After the forms were removed, any rough places at the lower edge, where
+the concrete joins the "lip," were bush-hammered; no other cleaning work
+was done.
+
+_Duct Laying and Rodding._--The design and location of the ducts have
+already been described. It will have been seen that the duct-bench
+concrete was laid in steps, on which the ducts were laid, hence the
+maintenance of the grade and line in the ducts was an easy matter. The
+only complication was the expanded metal bonds, which were bent up out
+of the way of the arch forms and straightened out again after the arch
+forms had passed. The materials, such as ducts, sand, and cement, were
+brought into the tunnel by the regular transportation gang. The mortar
+was mixed in a wooden trough about 10 ft. long, 2 ft. 6 in. wide and 8
+in. deep.
+
+After the single-way ducts had been laid, all the joints were plastered
+with mortar, in order to prevent any foreign substance from entering the
+ducts. This was not necessary with the multiple duct, as the joints were
+wrapped with cotton duck. The ducts were laid on a laying mandrel, and,
+as soon as possible after the concrete was laid around a set of ducts,
+they were "rodded" with a rodding mandrel. Not many obstructions were
+met, and these were usually some stray laying mandrel which had been
+left in by mistake, or collections of mortar where the plastering of the
+single-way joints had been defective.
+
+In the 657,000 duct ft. of conduit in the river tunnels only eight
+serious obstructions were met. That the work was of exceptionally high
+quality is shown by the fact that a heavy 3-in. lead cable has been
+passed through from manhole to manhole (450 ft.) in 6 min., and the
+company, engaged to lay the cables in these ducts, broke all its
+previous records for laying, not only for tunnel work, but also in the
+open.
+
+Fig. 1, Plate XXXV, shows a collection of the tools and arrangements
+used in laying and rodding ducts. The typical working force was:
+
+_Laying Multiple Ducts._
+
+ 1 Foreman @ $3.50 per shift.
+ 9 Laborers " 1.75 " "
+
+_Laying Single-Way Ducts._
+
+ 1 Foreman @ $3.50 per shift.
+ 8 Laborers " 1.75 " "
+
+_Rodding Multiple Ducts._
+
+ 1 Foreman @ $3.50 per shift.
+ 5 Laborers " 1.75 " "
+
+_Rodding Single-Way Ducts._
+
+ 1 Foreman @ $3.50 per shift.
+ 5 Laborers " 1.75 " "
+
+The average progress per 10-hour shift with such gangs was:
+
+ Laying multiple ducts 4,000 duct ft.
+ Laying single-way ducts 1,745 " "
+ Rodding multiple ducts 4,040 " "
+ Rodding single-way ducts 2,532 " "
+
+No detailed description need be given of the concreting of the
+cross-passages, pump chambers, sumps, and other small details, the
+design of which has been previously shown. The concrete was finished on
+June 1st, 1909.
+
+_Period No. 6._--_Final Cleaning Up._--_June, 1909, to November,
+1909._--As soon as all the concrete was finished, the work of cleaning
+up the invert was begun. A large quantity of débris littered the
+tunnels, and it was economical to remove it as quickly as possible. The
+remaining forms were first removed, and hoisting engines, supported on
+cross-timber laid across the benches, were set up in the middle of the
+tunnel at about 500-ft. intervals.
+
+Work was carried on day and night, and about 169 ft. of single tunnel
+was cleared per 10-hour shift. Work was begun on May 28th, and finished
+on July 15th, 1909. For part of the time it was carried on at two points
+in each tunnel, working toward the two shafts, but when the work in the
+Weehawken Shaft, which was being done at the same time, blocked egress
+from that point, all material was sent out by the Manhattan Shaft.
+
+The total quantity of material removed was 5,350 cu. yd., or about 0.44
+cu. yd. per lin. ft. of tunnel. The average force per shift was:
+
+_In Tunnel._
+
+ 3 Foremen @ $3.25 per shift
+ 1 Hoist engineer " 3.00 " "
+ 1 Signalman " 2.00 " "
+ 38 Laborers " 1.75 " "
+
+_On the Surface._
+
+ 1 Foreman @ $3.25 per shift
+ 1 Hoist engineer " 3.00 " "
+ 1 Signalman " 2.00 " "
+ 12 Laborers " 1.75 " "
+
+After the cleaning out had been done, the contractor's main work was
+finished. However, quite a considerable force was employed, up to
+November, 1909, in doing various incidental jobs, such as the
+installation of permanent ventilation conduits and nozzles at the
+intercepting arch near the Manhattan Shaft, the erection of a head-house
+over the Manhattan Shaft, and collecting and putting in order all the
+miscellaneous portable plant, which was either sold or returned to
+store, sorting all waste materials, such as lumber, piping, and scraps
+of all kinds, and, in general, restoring the sites of the working yards
+to their original condition.
+
+
+Concrete Mixing.
+
+The plant used in mixing the concrete for the land tunnels was pulled
+down and re-erected before the concrete work in the river tunnels was
+begun. At the New York shaft two new bins for sand and stone were built,
+bringing the total capacity up to 950 cu. yd. Two No. 6 Ransome mixers,
+driven electrically by 30-h.p. General Electric motors, using current
+from the contractor's generators, were set up on a special platform in
+the intercepting arch.
+
+At Manhattan the sand and stone were received from the bins in chutes at
+a small hopper built on the permanent upper platform of the intercepting
+arch. Bottom-dumping cars, divided by a partition into two portions,
+arranged to hold the proper quantities of sand and stone for a 4-bag
+batch of concrete, were run on a track on this upper platform, filled
+with the proper quantities of sand and stone, and then run back and
+dumped into the hoppers of the mixer. After mixing, the batch was run
+down chutes into the tunnel cars standing on the track below. The water
+was brought in pipes from the public supply. It was measured in barrels
+by a graduated scale within the barrels. The water was not put into the
+mixer until the sand and stone had all run out of the mixer hopper. The
+mixture was revolved for about 1½ min., or about 20 complete
+revolutions.
+
+At Weehawken Shaft the mixing plant was entirely rebuilt. Four large
+bins, two for sand and two for stone, were built in the shaft. Together,
+they held 430 cu. yd. of stone and 400 cu. yd. of sand. The sand and
+stone were dumped directly into the bins from the cars on the trestle
+which ran from the wharf to the shaft. The materials were run through
+chutes directly from the bins to the hoppers of the mixers, where they
+were measured. Two No. 6 Ransome mixers, electrically driven, were used
+here, as at New York, and, as there, the water was led into measuring
+tanks before being let into the mixer.
+
+The quantity of water used in the various parts of the concrete
+cross-section, for a 4-bag batch consisting of 1 bbl. (380 lb.) of
+cement, 8.75 cu. ft. of sand, and 17.5 cu. ft. of stone, is given in
+Table 31.
+
+TABLE 31.--QUANTITY OF WATER PER 4-BAG BATCH OF CONCRETE, IN U.S.
+GALLONS.
+
+ ==========================+==========+==========+==========
+ Portion of cross-section. | Maximum. | Minimum. | Average.
+ --------------------------+----------+----------+----------
+ Invert | 40 | 20 | 26
+ Duct bench | 36 | 21 | 27
+ Arch (excluding key) | 37 | 19 | 25
+ Key of arch | 27 | 15 | 20
+ Face of bench | 31 | 22 | 27
+ ==========================+==========+==========+==========
+
+The maximum quantities were used when the stone was dry and contained
+more than the usual proportion of fine material, the minimum quantity
+when the sand was wet after rain.
+
+The resulting volumes of one batch, for various kinds of stone, are
+given in Table 32.
+
+TABLE 32.--VOLUME OF CONCRETE PER BATCH, WITH VARIOUS KINDS OF STONE.
+
+ ========+===========+================+===========+==================|
+ | | Resulting | |
+ | DESCRIPTION OF STONE. |volume per | |
+ Mixture.|-----------+----------------| barrel of | Remarks. |
+ | | |cement, in | |
+ | Passed | Retained on | cubic | |
+ | screen. | screen. | yards. | |
+ --------+-----------+----------------+-----------+------------------|
+ 1:2½:5 | 1½-in. | 3/8-in. | 0.815 | Measured in air |
+ 1:2½:5 | 2½-in. |Run of crusher. | 0.827 | " " " |
+ 1:2½:5 | -- |General average.| 0.808[D]|Measured from plan|
+ 1:2½:5 | 2-in. | 1½-in. | 0.768[E]| " " " |
+ ========+===========+================+===========+==================|
+
+[D] Average for whole of River Tunnel section.
+
+[E] Average from 7,400 cu. yd. in Land Tunnel section.
+
+The sand used was practically the same for the whole of the river tunnel
+section, and was supposed to be equal to "Cow Bay" sand. The result of
+the mechanical analysis of the sand is shown on Plate XLVI. The stone
+was all trap rock. For the early part of the work it consisted of stone
+which would pass a 2-in. ring and be retained on a 1½-in. ring, in
+fact, the same as used for the land tunnels. This was found to be too
+coarse, and for a time it was mixed with an equal quantity of fine
+gravel or fine crushed stone. As soon as it could be arranged,
+run-of-crusher stone was used, everything larger than 2½ in. being
+excluded. About three-quarters of the river tunnel concrete was put in
+with run-of-crusher stone. The force was:
+
+_At Manhattan._
+
+ 1 Foreman @ $3.00 per shift
+ 4 Men on sand and stone cars " 1.75 " "
+ 4 Men handling cement " 1.75 " "
+ 2 Men dumping mixers " 1.75 " "
+
+_At Weehawken._
+
+ 1 Foreman @ $3.00 per shift
+ 2 Men hauling cement " 1.75 " "
+ 2 Men dumping mixers " 1.75 " "
+
+The average quantity of concrete mixed per 10-hour shift was about 117
+batches, or about 90 cu. yd. The maximum output of one of the mixers was
+about 168 batches, or 129 cu. yd. per 10-hour shift.
+
+
+Transportation.
+
+_Surface Transportation._--At Manhattan the stone and sand were received
+in scows at the wharf on the river front. For the first part of the
+work, the wharf at 32d Street and North River was used, and while that
+was in use the material was unloaded from the scows into scale-boxes by
+a grab-bucket running on an overhead cable, and then teamed to the
+shaft. For the latter part of the work, the wharf used was at 38th
+Street and North River, where facilities for unloading were given to the
+contractor by the Pennsylvania Railroad Company which was the permanent
+lessee of the piers. The material was unloaded into scale-boxes by a
+grab-bucket operated by a derrick, and teamed to the shaft. When the
+scale-boxes arrived at the shaft they were lifted from the trucks by
+derricks and dumped into the bins.
+
+At Weehawken all the stone and sand, with the exception of the stone
+crushed on the work, was received by water at the North slip. Here it
+was unloaded by a 2-cu. yd. grab-bucket and dumped into 3-cu. yd.
+side-tipping cars, which were hauled by a small steam locomotive over
+the trestle to the shaft, where they were dumped directly into the bins.
+
+Before beginning the concrete lining, the 2-ft. gauge railway, which had
+been used for the surface transportation during the driving of the
+iron-lined tunnels, was taken up and replaced by a 3-ft. gauge track
+consisting largely of 30-lb. rails. The cars were 3-cu. yd.
+side-dumping, with automatic swinging sides. Two steam locomotives which
+were being stored at Weehawken (part of the plant from another
+contract), were used for hauling the cars in place of the electric ones
+used with the 2-ft. gauge railway.
+
+_Tunnel Transport._--The track used in the tunnel was of 2-ft. gauge,
+laid with the 20-lb. rails previously used in driving the iron-lined
+tunnels. The mining cars (previously mentioned in describing the driving
+of the iron-lined tunnels) were used for transporting the invert
+concrete, although, for most of the work, dumping buckets carried on
+flat cars were used. Several haulage systems were considered for this
+work, but not one of them was thought to be flexible enough to be used
+with the constantly changing conditions, and it was eventually decided
+to move all the cars by hand, because, practically all the work being
+down grade, the full cars could be run down by gravity and the empty
+ones pushed back by hand. Two men were allotted to each car, and were
+able to keep the traffic moving in a manner that would have been perhaps
+impossible with any system of mechanical haulage. This system was
+apparently justified by the results, for the whole cost of the tunnel
+transport, over an average haul of about 2,000 ft., was only about 50
+cents per cu. yd., which will be found to compare favorably with
+mechanical haulage on similar work elsewhere, provided full allowance is
+made for the use of the plant and power.
+
+_Force Employed._--The average force employed on transport, both on the
+surface and in the tunnel, is shown in Table 33.
+
+
+Costs.
+
+During the work, careful records of the actual cost to the contractor of
+carrying out this work were kept by the Company's forces; these costs
+include all direct charges, such as labor and materials, and all
+indirect charges such as head office, plant depreciation, insurance,
+etc., but do not include the cost of any financing, of which the Company
+had no information.
+
+TABLE 33.--AVERAGE FORCE PER SHIFT FOR TRANSPORTATION IN TWO TUNNELS.
+
+ ========+==================+=====+==========+============+===========+
+ Location|Grade |Rate | WORK IN PROGRESS |
+ | | |----------+------------+-----------+
+ | | | Two |Two arches, |Four arches|
+ | | | inverts |two inverts,| and one |
+ | | | and two |and two duct| face of |
+ | | | duct | benches | bench |
+ | | | benches | | |
+ --------+------------------+-----+----------+------------+-----------+
+ {|Foreman |$3.00| 2 | 2 | 2 |
+ Tunnel {|Laborer | 1.75| 24 | 28 | 70 |
+ {|Switchmen | 2.00| | 2 | 2 |
+ {|Hoisting engineers| 3.00| 2 | 4 | 5 |
+ {|Foreman | 3.00| 1 | 1 | 2 |
+ Surface{|Laborers | 1.75| 8 | 8 | 15 |
+ {|Teams | 6.50| 1 | 1 | 2 |
+ ========+==================+=====+==========+============+===========+
+
+
+Field Engineering Staff.
+
+The field staff may be considered as divisible into five main divisions:
+
+ (_A_).--Construction, including alignment,
+
+ (_B_).--Cost records,
+
+ (_C_).--Testing of cement and other materials of construction,
+
+ (_D_).--Photography,
+
+ (_E_).--Despatch-boat service.
+
+(_A_).--_Construction_ (_Inspection and Alignment_) _Staff._--A
+comparatively large staff was maintained by the Company, and to this two
+causes contributed. In the first place, the contractor maintained no
+field engineering staff, because, early in the proceedings, it was
+arranged that the Company would carry out all this work, and thus avoid
+the overlapping, confusion, and lack of definite responsibility which
+often ensues when two engineering forces are working over the same
+ground. Even had the contractor maintained an engineering force, it
+would have been necessary for the Company to check most of the
+contractor's work.
+
+In the second place, this work gave rise to a number of special surveys,
+tests, borings, and observations of various kinds, most of which were
+kept up as a part of the regular routine work, and this necessitated a
+staff. Also, for a whole year, active progressive work was at a
+standstill while the pile tests were going on.
+
+(_B_).--_Cost Records Staff._--A distinct feature was made of keeping as
+accurately as possible detailed records of the actual cost to the
+contractor of carrying out the work. A small staff of clerks, retained
+solely for this purpose, tabulated and recorded the information
+furnished by the members of the construction staff. About $12,000,
+altogether, was spent in salaries in this department, and it may be
+considered an extremely wise investment, for, not only is the
+information thus obtained of great value and interest in itself, but it
+also puts the Company in an excellent position should any claim or
+discussion arise with the contractor.
+
+(_C_).--_Cement-Testing Department._--As the Company furnished the
+cement to the contractor, it became incumbent to make careful tests of
+the quality. A cement-testing laboratory was established at the
+Manhattan Shaft offices, under the charge of a cement inspector who was
+furnished with assistants for sampling, shipping, and testing cement.
+All materials used on the work, such as bricks, sand, stone,
+water-proofing, etc., were tested here, with the exception of metals,
+which were under the charge of a metal inspector reporting directly to
+the head office. This department cost about $10,000 for salaries and
+$3,000 for apparatus and supplies, or about $13,000, in all.
+
+There were 800,000 bbl. of cement tested, and samples from 2,100,000
+brick. A large amount of useful information has resulted from the work
+of this laboratory.
+
+(_D_).--_Photography._--It was desired to keep a complete photographic
+record of the progress of the work, and therefore a photographer was
+appointed, with office room at the Manhattan Shaft. The photographer
+took all the progress photographs on the work of the North River
+Division, made photographic reductions of all drawings and plans, made
+lantern slides of all negatives of a more important nature, and, in
+addition, during the period of compressed air, analyzed the samples of
+compressed air, brought into the office for the purpose, for the amount
+of CO_{2} present. About $8,000 was spent on this department.
+
+(_E_).--_Despatch-Boat Service._--To provide access to the New Jersey
+side, a despatch boat was purchased. This boat was at first (June, 1904)
+chartered, and in May, 1905, was bought outright, and ran on regular
+schedules, day and night. It continued in the service until April,
+1909, when it was given up, as the tunnels were so far completed that
+they provided easy access to New Jersey. The cost of the boat
+(second-hand) was about $3,000. It was then thoroughly overhauled and
+the cabin remodeled. The monthly cost, when working a 12-hour shift, was
+$270 for manning, $65 for supplies, and $64 for coal. On two 12-hour
+shifts, the monthly cost was $533 for manning, $100 for supplies, and
+$96 for coal. About 100,000 passengers were carried during the boat's
+period of service, and the total cost was about $37,500.
+
+For the major part of the period embraced by this paper, B. H. M.
+Hewett, M. Am. Soc. C. E., served as General Resident Engineer, in
+charge of the Field Work as a whole.
+
+W. L. Brown, M. Am. Soc. C. E., was at first Resident Engineer of the
+work constructed from the Manhattan Shaft, while H. F. D. Burke, M. Am.
+Soc. C. E., was Resident Engineer of the work constructed from the
+Weehawken Shaft. After the meeting of the shields, Mr. Burke left to
+take up another appointment, and from that time Mr. Brown acted as
+Resident Engineer.
+
+It may be said, without reflecting in any way on the manufacturers, that
+the high standard of all the metal materials also testified to the
+efficient inspection conducted under the direction of Mr. J. C.
+Naegeley.
+
+It is impossible to close this brief account of these tunnels without
+recording the invaluable services at all times rendered by the members
+of the Company's field staff. Where all worked with one common aim it
+might seem invidious to single out names, but special credit is due to
+the following Assistant Engineers: Messrs. H. E. Boardman, Assoc. M. Am.
+Soc. C. E., W. H. Lyon, H. U. Hitchcock, E. R. Peckens, H. J. Wild,
+Assoc. M. Am. Soc. C. E., J. F. Sullivan, Assoc. M. Am. Soc. C. E., and
+R. T. Robinson, Assoc. M. Am. Soc. C. E. Mr. C. E. Price was in charge
+of the cement tests throughout the entire period, and brought to his
+work not only ability but enthusiasm. Mr. H. D. Bastow was in charge of
+the photographic work, and Mr. A. L. Heyer of the cost account records,
+in which he was ably seconded by Mr. A. P. Gehling, who, after Mr.
+Heyer's departure, finished the records and brought them into their
+final shape. The organization of the Company's field engineering staff
+is shown graphically by Fig. 24.
+
+FIELD ORGANIZATION OF THE O'ROURKE ENGINEERING CONSTRUCTION COMPANY FOR
+THE BUILDING OF THE PENNSYLVANIA RAILROAD TUNNELS INTO NEW YORK
+CITY--NORTH RIVER DIVISION. SECTIONS GY EAST, GY WEST SUPPLEMENTARY, GY
+WEST, AND CO.
+
+
+ GENERAL SUPERINTENDENT.
+ |
+ +------------------------+-------+--+
+ | | |
+ (General, Surface and Office) (Excavation |
+ ---------------+------------- of Land |
+ | Tunnels) |
+ ASSISTANT GENERAL SUPERINTENDENT | |
+ | GENERAL |
+ | ROCK SUPT |
+ +------------+------------+ | |
+ | | | Tunnel |
+ FIELD SURFACE DESPATCH Supts |
+ OFFICE BOAT Tunnel |
+ Foreman |
+ Civil Head Captain Foremen |
+ Engineer Carpenter Engineer Timbermen |
+ Inspectors Foreman Deck Hands Timbermen |
+ Bookkeepers Carpenter Timbermen's |
+ Paymaster Carpenters Helpers |
+ Head Carpenters' Foremen |
+ Storekeeper Helpers Drillers |
+ Storekeepers Blacksmiths Drillers |
+ Timekeepers Blacksmiths' Foremen |
+ Telephone Helpers Muckers |
+ Operators Foreman Pipe Fitters |
+ Office Boys Laborers Pipe Fitters' |
+ Messengers Laborers Helpers |
+ Janitors Disposal Electricians |
+ Trimmers Hoist |
+ Teamsters Engineers |
+ Signalmen |
+ Muckers |
+ Nippers |
+ Water Boys |
+ |
+ |
+ -------------+--------+-------------------------+--------+----------+
+ | | | |
+ (Shield Tunnel Driving) (Masonry (Power (Medical
+ | Lining-Rock Plant) Supervision)
+ GENERAL TUNNEL SUPERINTENDENT and River | |
+ | Tunnels) MASTER CHIEF MED
+ ASSISTANT SUPERINTENDENTS | MECHANIC OFFICER
+ | | | | | | |
+ +--------+------------+---------+ | Foreman |
+ EXCAVATION | | GENERAL | Electrician |
+ | IRON LINING CAULKING AND | | Electricians |
+ General | GRUMMETING | | Engineers |
+ Foremen Foremen | Pipefitters | Foreman Resident
+ Foremen Erector Foremen Pipefitters' | Machinist Doctor
+ Drillers Runners Caulkers Helpers | Machinists
+ Drillers Ironmen Grummeters Electricians | Machinists'
+ Powdermen Boltmen Electricians'| Helpers
+ Foremen Helpers | Firemen
+ Timbermen Trackmen | Oilers
+ Timbermen Lockmen | Pumpmen
+ Foremen Transport | Hoist Engineers
+ Muckers Foreman | Signalmen
+ Muckers Transport |
+ Shieldmen Laborers |
+ Laborers Watchmen |
+ Nippers |
+ Water Boys |
+ GENERAL CONCRETE SUPERINTENDENT
+ |
+ TUNNEL SUPERINTENDENTS
+ |
+ +-----------+------------+----------------++-----------+
+ | | | | |
+ CONCRETE BRICKWORK DUCTS WATER-PROOFING GENERAL
+
+ Foremen Foremen Foremen Foremen Pipefitters
+ Carpenters Bricklayers Duct-layers Waterproofers Pipefitters'
+ Carpenters' Bricklayers' Helpers
+ Helpers Laborers Electricians
+ Mixer Carpenters Electricians'
+ Foremen Carpenters' Helpers
+ Mixer Helpers Transport
+ Laborers Foremen
+ Concrete Transport
+ Laborers Laborers
+ Watchmen
+
+ FIG. 24.
+
+_Contractor's Organization._--The contracting firm which did the work
+described in this paper was the O'Rourke Engineering Construction
+Company, of New York City. The President of this Company was John F.
+O'Rourke, M. Am. Soc. C. E., the Vice-President was F. J. Gubelman,
+Assoc. M. Am. Soc. C. E. The General Superintendent was Mr. George B.
+Fry, assisted by J. F. Sullivan, Assoc. M. Am. Soc. C. E. The duties of
+General Tunnel Superintendent fell to Mr. Patrick Fitzgerald. The
+generally pleasant relations existing between the Company and the
+contractor's forces did much to facilitate its execution.
+
+The organization of the Contractor's field staff is shown on Fig. 25.
+
+PENNSYLVANIA TUNNEL AND TERMINAL RAILROAD COMPANY. NORTH RIVER DIVISION.
+
+SECTIONS GY EAST, GY WEST SUPPLEMENTARY, GY WEST, GJ, AND I, _I. E._,
+FROM 10TH AVENUE, MANHATTAN, TO THE WEEHAWKEN SHAFT, FIELD ENGINEERING
+STAFF ORGANIZATION.
+
+ GENERAL RESIDENT ENGINEER
+ |
+ +-----------------+------------+------------+---------+----+
+ | | | | | |
+ (Material Testing) (Photography) | (Cost Records) |(Office)
+ Cement Inspector Photographer | Recording Clerk | Clerks
+ Asst Cement | Asst Recording |Messengers
+ Inspectors | Clerks |
+ (Construction) |
+ | (Despatch Boat)
+ +----------------+ Captain
+ | Engineers
+ RESIDENT ENGINEERS Deckhands
+ (Two during driving of Shield-driven Messengers
+ Tunnels, and one subsequently.)
+ |
+ +---------------------+---+------------------+
+ | | |
+ (Inspection) (Alignment) (Office)
+ Assistant Engineers Assistant Engineers Draftsmen
+ Chief Tunnel Chiefs of Parties Field Office
+ Inspector Instrumentmen Clerks
+ Tunnel Inspectors Rodmen Cement
+ Surface Inspectors Chainmen Warehousemen
+ Clerks Laborers Janitors
+
+ FIG. 25
+
+In conclusion, the writers cannot forego the pleasure of expressing
+their deep obligation to Samuel Rea, M. Am. Soc. C. E., as representing
+the Management of the Company, to the Chief Engineer, Charles M. Jacobs,
+M. Am. Soc. C. E., and to James Forgie, M. Am. Soc. C. E., Chief
+Assistant Engineer, for their permission to write this paper, and also
+to all the members of the field office staff for their great and
+unfailing assistance in its preparation.
+
+
+
+
+
+End of the Project Gutenberg EBook of Transactions of the American Society
+of Civil Engineers, Vol. LXVIII, Sept. 1910, by B. H. M. Hewett and W. L. Brown
+
+*** END OF THE PROJECT GUTENBERG EBOOK 42149 ***