summaryrefslogtreecommitdiff
path: root/18408-8.txt
diff options
context:
space:
mode:
Diffstat (limited to '18408-8.txt')
-rw-r--r--18408-8.txt2596
1 files changed, 2596 insertions, 0 deletions
diff --git a/18408-8.txt b/18408-8.txt
new file mode 100644
index 0000000..02d7058
--- /dev/null
+++ b/18408-8.txt
@@ -0,0 +1,2596 @@
+The Project Gutenberg EBook of Transactions of the American Society of
+Civil Engineers, vol. LXVIII, Sept. 1910, by George C. Clarke
+
+This eBook is for the use of anyone anywhere at no cost and with
+almost no restrictions whatsoever. You may copy it, give it away or
+re-use it under the terms of the Project Gutenberg License included
+with this eBook or online at www.gutenberg.org
+
+
+Title: Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910
+ The Site of the Terminal Station. Paper No. 1157
+
+Author: George C. Clarke
+
+Release Date: May 17, 2006 [EBook #18408]
+
+Language: English
+
+Character set encoding: ISO-8859-1
+
+*** START OF THIS PROJECT GUTENBERG EBOOK SOCIETY OF CIVIL ENGINEERS ***
+
+
+
+
+Produced by Louise Hope, Juliet Sutherland and the Online
+Distributed Proofreading Team at http://www.pgdp.net
+
+
+
+
+
+ AMERICAN SOCIETY OF CIVIL ENGINEERS
+ Instituted 1852
+
+ TRANSACTIONS
+
+ Paper No. 1157
+
+ THE NEW YORK TUNNEL EXTENSION OF THE
+ PENNSYLVANIA RAILROAD.
+ THE SITE OF THE TERMINAL STATION.[1]
+
+ By GEORGE C. CLARKE, M. Am. Soc. C. E.
+
+
+The purpose of this paper is to describe the preliminary work for and
+the preparation of that portion of the site for the Terminal Station
+in Manhattan, of the New York Tunnel Extension of the Pennsylvania
+Railroad, which was constructed under the direction of the Chief
+Engineer of the East River Division, including the disposal of material
+excavated from all parts of the Terminal construction and the tunnels on
+the East River Division.
+
+As outlined in the paper by Brigadier-General Charles W. Raymond, M. Am.
+Soc. C. E., Chairman of the Board of Engineers, the track yard of the
+station, Plate LIII, extends from the east line of Tenth Avenue eastward
+to points in 32d and 33d Streets, respectively, 292 and 502 ft. east of
+the west line of Seventh Avenue. The width of the available area at
+track level at Tenth Avenue is 213 ft., continuing at this width to
+within 182 ft. of the west line of Ninth Avenue, where, by an offset
+toward the south, it is increased to 355 ft. This width is held to a
+point 5 ft. east of the east line of Ninth Avenue, where, by an offset
+toward the north, it is increased to 509 ft., which width continues to
+the west line of Seventh Avenue, where it divides into two fan-shaped
+areas. The north area has a width of about 170 ft. and the south one,
+160 ft., at the house line, each area tapering gradually to the width
+of the standard three-track tunnel at the east ends, noted above in 33d
+and 32d Streets. Additional track room for four tail-tracks is gained by
+the construction of two double-track tunnels under Ninth Avenue at 33d
+Street, their center lines being parallel to the street and 45.5 and
+84.5 ft. distant, respectively, from the north house line. An additional
+width of 24.5 ft. is occupied on the north from 277.5 ft. to 543.5 ft.
+west of the west line of Seventh Avenue, where the buildings on the
+north side of 33d Street have been torn down and the enclosing wall set
+back in anticipation of a future outlet to 34th Street; and on the
+south, from 459 ft. to 597 ft. west of the west line of Seventh Avenue a
+rectangular offset of 124 ft. encloses the area occupied by the Service
+Building. The total area above outlined is the space occupied at track
+level, and amounts to 28 acres, of which the portion west of the east
+house line of Ninth Avenue and south of a line 107.3 ft. south of the
+south line of 33d Street is a part of the North River Division, and was
+constructed under the direction of the engineers of that Division; the
+fan-shaped areas east of the west house line of Seventh Avenue were
+constructed under the direction of the Chief Engineer of Electric
+Traction and Terminal Station Construction.
+
+ [Illustration:
+ Plate LIII.
+ Pennsylvania Station, New York City: Plan Showing Area at Track Level]
+
+In June, 1903, when the writer's connection with the work began, the
+preliminary surveys had been completed and the location and extent of
+the Terminal track area had been fixed, in so far as the city blocks to
+be occupied were concerned. This contemplated area, however, did not
+include the portion between Ninth and Tenth Avenues, that being added
+subsequently. The elevation of the track level had also been fixed by
+the requirement in the agreement with the City that no part of the
+permanent structure should approach within 19 ft. of the surface under
+any avenue or under any street except within the Terminal area. The
+nearest approach of the tracks to the surface is at a point 320 ft. east
+of Eighth Avenue, where the top of the rail is 40 ft. below the 31st
+Street curb line.
+
+
+WASH-BORINGS.
+
+The general plan of enclosing the area in retaining walls having been
+adopted, wash-borings were taken, for the purpose of determining the
+best location for the walls, the depth of rock, and the nature of the
+material overlying it. These borings were made along both curb lines of
+Seventh Avenue, the east curb line of Ninth Avenue, the north curb line
+of 33d Street, and the south curb line of 31st Street. The borings, as a
+rule, were taken at intervals of approximately 100 ft., some deviation
+in these intervals being made in order to prevent injury to water, gas,
+and sewer connections, and, if the elevation of the surface of the rock,
+as determined by one of these borings, corresponded fairly well with
+the borings on either side of it, no intermediate borings were taken.
+When a discrepancy appeared, a boring was taken midway between the
+two non-corresponding ones, and if the information obtained from the
+intermediate boring failed to account for the discrepancy, others were
+taken at the quarter points of the original 100-ft. interval.
+
+The dotted lines on Fig. 1 show the profiles of the surface of the rock
+underlying 31st and 33d Streets, on the line of the borings, constructed
+from the elevations obtained by them; the solid lines show the profiles
+of the actual surface of the rock as found when uncovered. It will be
+noted that, except in three cases, Borings 313, 328, and 333, the two
+profiles correspond very closely at the points where the borings were
+made, but they differ widely between those points, a variation of 5 ft.
+being common; there is a variation of 14 ft. between Borings 324 and
+327, and between Nos. 337 and 340; and of 12 ft. between Nos. 333 and
+335, and between Nos. 312 and 313, while an extreme variation of 17 ft.
+is shown between Nos. 303 and 305. At each of the points where the
+variation is great the interval between borings is the full 100 ft., and
+it is quite apparent that, if a definite idea is to be obtained of the
+elevation of the surface of the rock in Manhattan, borings must be taken
+at shorter intervals.
+
+The necessary width of trench for the construction of the retaining
+walls was determined by the elevation of the rock, as shown by the
+borings, and only in the case of the dip between Borings 303 and 305
+did the variation lead to any difficulty. The trench at that point had
+to be widened after rock was reached. This depression corresponded very
+closely in location to that of one arm of the creek shown on General
+Viele's map of 1865,[2] the bed of that stream, or one in approximately
+the same location, being clearly marked across the excavation by
+smoothly-worn rock and well-rounded boulders. The original stream,
+however, seemed to have turned in a westerly direction under 31st Street
+to Eighth Avenue instead of crossing, as shown on General Viele's map.
+
+ [Illustration:
+ Fig. 1.
+ PROFILE OF ROCK SURFACES IN THIRTY-FIRST AND THIRTY-THIRD STREETS,
+ BETWEEN SEVENTH AND NINTH AVENUES]
+
+
+SEWERS.
+
+The arrangement of the sewers in the streets in the vicinity of the
+Terminal Site, previous to the beginning of the construction, and the
+drainage area tributary to those sewers, is shown by Fig. 2. The main
+sewer for this district was in Eighth Avenue, and was a 6-ft. circular
+brick conduit within the Terminal area. The sewers leading to it from
+the west, in 31st, 32d, and 33d Streets, were elliptical, 3 by 2 ft.,
+and egg-shaped, 4 ft. by 2 ft. 8 in., although in no case did they drain
+more than one block, and they were on a heavy grade. Draining into
+Eighth Avenue from the east, the one on 31st Street was 4 ft. by 2 ft.
+8 in., egg-shaped, and drained a length of two blocks, and those on 32d
+and 33d Streets were circular, 4 ft. in diameter, and drained the
+territory for three blocks, or as far east as Fifth Avenue. There were
+no sewers in Seventh Avenue within the Terminal area, except small
+vitrified pipes, each less than 200 ft. in length.
+
+It was desirable that the size and number of the sewers in the streets
+and avenues surrounding the Terminal should be reduced to a minimum, on
+account of the difficulty of caring for them during construction and
+also to reduce the probability of sewage leaking into the underground
+portion of the work after its completion. With this in view, the plan
+was adopted of building an intercepting sewer down Seventh Avenue from
+north of 33d Street to the 30th Street sewer, which, being a 4-ft.
+circular conduit, was sufficiently large to carry all the sewage coming
+from east of Seventh Avenue and south of 34th Street. It was decided to
+build this sewer of cast iron where it crossed the proposed construction
+work, and also to replace with cast iron the brick sewers on 31st, 32d,
+and 33d Streets from Seventh Avenue to a point east of the west end of
+the standard tunnel section, and also the sewer on Eighth Avenue from
+the north side of 33d Street to the south side of 31st Street. This
+arrangement permitted: first, the removal of the sewer in 32d Street
+between Seventh and Eighth Avenues, which was necessary, as that street
+was to be excavated; second, the reduction of the sewer in Eighth Avenue
+from a 6-ft. to a 5-ft. circular conduit; and, third, assuming that the
+sewage and drainage from the Terminal would be pumped directly to the
+sewers in the avenues, the reduction of the sewers in 31st and 33d
+Streets, from Seventh to Ninth Avenue, to 15-in. vitrified pipes, except
+west of the Service Building in 31st Street, to accommodate which
+section, a larger sewer was required. The sewer in 32d Street, from
+Ninth to Eighth Avenue, of course, could be dispensed with in any
+arrangement, as all the area tributary to it was to be excavated.
+
+ [Illustration:
+ Fig. 2.
+ PLAN SHOWING LAYOUT OF SEWER IN CATCHMENT AREA ABOUT TERMINAL STATION]
+
+
+GAS AND WATER MAINS.
+
+A rearrangement of the gas pipes in the three streets crossing the
+Terminal site was necessary. These pipes were of two classes: trunk
+mains and service mains. Fortunately, there were but two trunk mains
+in the three streets, one a 20-in. in 31st Street from east of Seventh
+Avenue to Ninth Avenue, the other a 16-in. in 32d Street from east of
+Seventh Avenue to Eighth Avenue. The 20-in. main was relaid from Seventh
+Avenue and 31st Street down Seventh Avenue to 30th Street and through
+that street to Ninth Avenue. The 16-in. main was relaid from Seventh
+Avenue and 32d Street north to 34th Street and through that street to
+Eighth Avenue. The service mains in 32d Street were no longer required,
+and were taken up and not replaced. The houses on 31st and 33d Streets
+were provided with service by two 6-in. wrought-iron mains back of the
+retaining walls in each street, that location being chosen to avoid
+damage by gas drip to the water-proofing of the street bridges. As the
+permanent structures under the avenues were not to approach the surface
+nearer than 19 ft., only slight rearrangements, sufficient to permit the
+new sewers and water lines to be laid, were necessary.
+
+There were no large water mains to be cared for, in fact, those in the
+streets were too small for ample fire protection, being only 6 in. in
+diameter. The main in 32d Street was taken up and not replaced, and
+those on 31st and 33d Streets were replaced by 12-in. pipes laid back
+of the retaining walls. No changes were necessary in the mains in the
+avenues, but, before approving the rearrangement for the streets, the
+Department of Water Supply, Gas and Electricity added a 48-in. main in
+Eighth Avenue to be laid as a part of this construction, the pipe being
+supplied by the City.
+
+
+LOCATION AND DESIGN OF RETAINING WALLS.
+
+The plans, from the earliest stages, contemplated founding the
+retaining wall on the surface of the rock, where of suitable quality,
+and afterward excavating the rock in front of the toe of the wall
+to sub-grade. This plan was definitely adopted soon after the borings
+were completed, on account of the great danger of blasting out large
+quantities of rock in timbered trenches close to buildings founded on
+soft material, and also to avoid the additional cost and delay that
+would have been caused by carrying the walls to sub-grade. The retaining
+walls in Seventh Avenue, south of the viaduct, and in Ninth Avenue,
+north of the viaduct, were not governed by the same conditions as in the
+streets. The dip and quality of the rock at both points required that
+the walls be carried to sub-grade, and they are, in fact, face walls;
+the Ninth Avenue wall, in particular, having little thrust to sustain,
+is very light.
+
+The results aimed at in the design and location of the retaining walls
+in 31st and 33d Streets were:
+
+ _First._--A perfectly stable wall under all conditions that might
+ reasonably be expected;
+
+ _Second._--As much room as possible at the elevation of the top of
+ rail;
+
+ _Third._--The least necessary interference with adjoining property
+ during construction; and,
+
+ _Fourth._--The most economical wall that would fulfill the other
+ conditions.
+
+As stated in the paper by Alfred Noble, Past-President, Am. Soc. C. E.,
+the third stipulation required the relinquishing of a portion of the
+space under these streets granted by the City, but it was finally
+decided not to approach the south house line of 31st Street with the
+back of the walls nearer than 9 ft., while on 33d Street the extreme
+position of the back was fixed at the north line, as there were no
+buildings, except those belonging to the Railroad Company, on the house
+line at the low points in the rock.
+
+The assumptions made in designing the wall were as follows:
+
+ _First._--Weight of concrete, 140 lb. per cu. ft.
+
+ _Second._--Weight of material from the surface of the ground to a
+ depth of 12 ft. (which was shown by tests made in bore-holes to be
+ the elevation of the ground-water surface), 100 lb. per cu. ft.;
+ and angle of repose, 30 degrees. The distance of 12 ft. below
+ the surface was the depth of the inverts of the sewers, which
+ undoubtedly drained the ground above them, thus accounting for the
+ standing of the ground-water in planes practically parallel with
+ the surface.
+
+ _Third._--Weight of buildings back of wall neglected, as that of the
+ present type will about equal the cellars filled with material at
+ 100 lb. per cu. ft., and if large buildings are erected in the
+ future they will undoubtedly be carried to rock.
+
+ _Fourth._--Reaction from superstructure, live and dead load, 20,000
+ lb. per lin. ft. of wall.
+
+ _Fifth._--Weight of materials below the 12-ft. line, 124 lb. per
+ cu. ft., ascertained as follows: The material was considered as
+ weighing 165 lb. per cu. ft. in the solid, and having 40% of voids
+ filled with water at 62.5 lb. per cu. ft., the resulting weight
+ being (165 × 60/100) + (62.5 × 40/100) = 124 lb. per cu. ft.
+
+Various angles of repose were used for this material in the
+investigation, and it was finally decided that 30° was the greatest
+angle that could be expected, whereas the worst condition that could be
+anticipated was that the sand and water would act separately and give a
+pressure as follows:
+
+Hydraulic pressure from liquid weighing 62.5 lb. per cu. ft. plus
+pressure from sand with angle of repose at 30° and weight as follows:
+
+Weight of 1 cu. ft. in air = 165 × 60/100 = 99 lb.
+
+Weight of water displaced by 1 cu. ft. = 60/100 × 62.5 lb. = 37.5 lb.
+
+Weight in water, therefore = 61.5 lb. per cu. ft.
+
+These combined weights, of course, are equal to the weight of the
+combined material in the previous assumption.
+
+ _Sixth._--The usual requirement that the resultant of both horizontal
+ and vertical forces should, at all points, fall within the middle
+ third of the wall, or, in other words, that there should be no
+ tension in the concrete.
+
+ [Illustration:
+ Plate LIV.
+ Diagram Showing Widths of Base of Retaining Wall Required
+ for Different Batters and Pressures, Pennsylvania Station]
+
+With these assumptions, investigation was made of walls with various
+batters and differently designed backs. This investigation developed the
+fact that the reaction from the superstructure was so great that, for
+economy, both in first cost and space occupied, the batter must be
+sufficient to cause that reaction to fall within or very close to the
+middle third. Nothing could have been gained by having that reaction
+fall back of the front of the middle third, as the wall was required
+to be stable against the full pressure before the superstructure was
+erected, and in case it should ever be removed; or, to state the matter
+more clearly, the reaction from the superstructure was so great in
+comparison to the weight of the wall, that, if it fell in front of the
+resultant of all the other forces, the width of base required would be
+greatly increased to make the wall stable after the superstructure was
+erected; whereas, if the reaction from the superstructure fell back of
+the resultant of all the other forces, the width of base could not be
+correspondingly decreased without danger of the wall being overturned
+before the superstructure was erected. The least batter that would
+answer those conditions was found to be 2 in. per ft.
+
+For convenience in designing, and economy in constructing, the
+steelwork, the faces of the bridge seat and of the backwall were laid
+parallel to the center line of the Terminal, and in elevation on line
+parallel to the top of the curb and as near to it as the economical
+depth of steel would permit, without bringing the finished construction
+above the plane fixed in the ordinance. As there is a variation of 13
+ft. in the elevation of the top of the curb of 31st Street above the top
+of rail and a variation of 18 ft. in 33d Street, a uniform batter, with
+the top parallel to the center line, would produce a toe varying in
+distance from it and from the other constructions. It was decided,
+therefore, for the sake of appearance, to make the face of the wall
+(or wall produced) at the top of rail parallel to the center line,
+and to vary the batter accordingly, using the 2-in. batter previously
+mentioned as the minimum. This gave a maximum batter of 3 in. per ft. The
+variation is so gradual that it is unnoticeable, and is not sufficient
+to introduce any complications in construction.
+
+The wall was designed with a stepped back, primarily to allow the
+water-proofing and brick protection to be held in position more readily.
+The first step was put at 13 ft. below the surface of the ground. This
+gave a vertical back above that point for a 3-in. battered face, and a
+slightly battered back for sections having a less batter in front. Below
+that point a step was added for each 5 ft. of depth to the elevation
+of the top of rail, or to the foundation of the wall if above that
+elevation. As the horizontal distance of the heel of the wall, at its
+greatest width, from its face at the top of rail would determine the
+effective room to be occupied by the wall, it was determined to make the
+back vertical below the top of rail and gain the necessary increase in
+width below that point by making a heavy batter on the face.
+
+The type of wall having been thus determined, calculations were made
+of the width of base required for each ¼-in. batter from 2 to 3 in.,
+inclusive, first for a depth of 13 ft. below the top of the curb and
+then for each 5 ft. below that elevation, to a depth corresponding to
+the distance between the top of the curb and the top of the rail at the
+point of greatest variation. These widths of wall were determined for
+the two pressures previously decided on, and curves were then plotted
+showing the thickness of wall required for each batter calculated and
+for each pressure. They are shown on Plate LIV. The curves in broken
+lines represent the widths required for saturated material, and the
+curves in dotted lines for hydraulic pressure. Mean curves were then
+drawn between each broken and its corresponding dotted curve. These are
+shown in solid lines, and represent the widths of wall which were used
+in the construction. Typical sections of the wall and pipes back of it
+are shown on Fig. 3.
+
+The extreme positions of the back of the wall on the two streets having
+been determined, as previously stated, the width of base required at
+those points fixed the toe of the wall at the top of rail as 254.5 ft.
+south of the center line of the Terminal in 31st Street, and 258.5 ft.
+north of the center line in 33d Street.
+
+ [Illustration:
+ Fig. 3.
+ TYPICAL SECTIONS OF RETAINING WALL IN THIRTY-FIRST STREET]
+
+
+CONTRACTS.
+
+The construction was done under the following contracts:
+
+_1._--The principal contract, dated June 21st, 1904, was with the New
+York Contracting and Trucking Company, later assigned by that company
+to the New York Contracting Company-Pennsylvania Terminal, for the
+performance of the following works:
+
+ (_a_).--The excavation for and construction of a retaining wall in
+ Seventh Avenue, 31st Street, Ninth Avenue, and 33d Street.
+
+ (_b_).--Excavation over the area enclosed by the retaining wall.
+
+ (_c_).--The building of sewers and the laying of water and gas pipes.
+
+ (_d_).--The building of a timber trestle to support the surface of
+ Eighth Avenue between the south side of 31st Street and the north
+ side of 33d Street, and also the surface of 31st and 33d Streets
+ between Seventh and Ninth Avenues. This refers to the trestles left
+ in place on the completion of the work.
+
+ (_e_).--The building of a trestle and bridging from a point near the
+ west side of Tenth Avenue on the south side of 32d Street, westward
+ to the outer end of Pier No. 62, at the foot of 32d Street.
+
+_2._--The second contract, dated February 10th, 1905, was with the New
+York Contracting Company-Pennsylvania Terminal, for the excavation for
+and construction of retaining walls for the Manhattan Terminal Power
+Station, and the excavation of the area thus enclosed.
+
+_3._--The third contract, dated October 2d, 1907, was with the New York
+Contracting Company-Pennsylvania Terminal, for the construction of two
+twin tunnels under Ninth Avenue, and other work incidental thereto.
+
+Sewers and gas mains laid outside the area covered by the foregoing
+contracts were constructed under the following agreements:
+
+An agreement, dated August 9th, 1904, between the New York Contracting
+Company-Pennsylvania Terminal, and the New Amsterdam Gas Company, for a
+20-in. gas main from Seventh Avenue and 31st Street to 30th Street, and
+thence to Ninth Avenue, the New Amsterdam Gas Company being remunerated
+for the cost by the Tunnel Company.
+
+A contract, dated August 24th, 1904, with the New York Contracting
+Company-Pennsylvania Terminal, for the construction of sewers in Seventh
+Avenue and in 32d and 33d Streets east of Seventh Avenue.
+
+A contract, dated November 24th, 1908, with the New York Contracting
+Company-Pennsylvania Terminal, for the construction of a 16-in. gas main
+from Seventh Avenue and 32d Street to 34th Street, and thence to Eighth
+Avenue.
+
+All these contracts required that the excavated material be delivered on
+board scows to be furnished by the company at the pier at the foot of
+32d Street, North River. These scows were furnished and the material
+was disposed of from that point by Henry Steers, Incorporated, under a
+contract, dated August 9th, 1904, which called for the transportation to
+and placing of all material so delivered in the Pennsylvania Railroad
+Company's freight terminal at Greenville, N.Y.
+
+The disposal of the excavated material was one of the principal features
+of the work, and, under the above contract, material from those portions
+of the Terminal site east of Seventh Avenue and west of Ninth Avenue,
+and from all substructures work, was disposed of, as well as from the
+constructions herein described. The problem differed from that presented
+by the usual foundation excavations in New York City in magnitude only,
+and the methods were not unusual, but were adaptations of the usual ones
+to exceptionally large work.
+
+
+PIERS AND TRESTLE FOR DISPOSAL.
+
+The most rapid and economical handling of all excavated material to
+scows was made possible by the Tunnel Company procuring from the New
+York Central and Hudson River Railroad Company the pier at the foot of
+32d Street, North River, known in the earlier stages of the work as Pier
+No. 62, but subsequently changed to Pier No. 72, and thus referred to in
+this paper. This pier was occupied by a freight-shed used by the New
+York Central Railroad Company, under a long-term lease from the City,
+and that Company had to make numerous changes in their tracks and
+adjoining piers before No. 72 could be turned over; the contract for
+the excavation, therefore, required the contractor to procure any piers
+needed previous to and in addition to it. Under this clause of the
+agreement, the contractor procured one-half of the pier at 35th Street,
+North River, which was used for the disposal of all material excavated
+previous to May 22d, 1905, on which date Pier No. 72 was first put in
+service.
+
+As the type of plant the contractor would elect to use could not be
+determined, previous to the letting of the contract, a general plan for
+Pier No. 72 and the trestle approach, suitable for either trains or
+wagons, was attached to the contract, and the details were worked out
+afterward. The method adopted was by train, and a two-track approach to
+the pier was provided. Beginning on the east side of Ninth Avenue, at
+the south line of 32d Street, at an elevation of 20 ft. below the
+surface, crossing under Ninth Avenue and to the center line of 32d
+Street, it rose on a 1.5% grade in open cut to the surface of 32d Street
+at a point 500 ft. west of Tenth Avenue, from which point it rose above
+the surface of the street on a timber trestle to Tenth Avenue, which was
+crossed overhead. West of Tenth Avenue the line changed by a reverse
+curve to the south sidewalk of 32d Street, and continued on a timber
+trestle, practically level, to the New York Central Yard tracks near
+Eleventh Avenue. These tracks and Eleventh Avenue were crossed overhead
+on a through-truss, steel bridge, and a column-and-girder construction
+on which the two tracks separated to a distance of 29 ft, between center
+lines, so as to bring them directly over the posts of special timber
+bents which spanned the two house tracks of the New York Central
+south-bound freight shed, which the trestle here paralleled. This
+position was held to a point 25 ft. west of the east house line of
+Twelfth Avenue, where, by a system of cross-overs and turn-outs, access
+was had from either track to six tracks on the pier. Four of these were
+on upper decks, two on the north and two on the south edge of the pier,
+at an elevation of 41 ft. above mean high tide, to carry earth and small
+rock to chutes from which it was dumped into barges. The other two
+tracks proceeded by a 5.3% grade down the center of the pier to the
+lower deck where, at a distance of 540 ft. from the bulkhead, and beyond
+the upper deck construction, they diverged into six, two on the north
+and two on the south edge of the pier for standing tracks to serve
+derricks, and two down the center for shifting purposes. A siding to the
+north of the two running tracks just west of the bottom of the incline
+served a bank of eight electric telphers. The arrangement of the pier is
+shown by Fig. 4.
+
+The trestle east of the steel structure at Eleventh Avenue had simple
+four-post bents, as shown by Bent "_A_," on Fig. 5, all posts being
+vertical, to save room at the street level; the outside posts and the
+caps and sills were of 12 by 12-in. timber; the intermediate posts were
+of 8 by 12-in. timber; and single or double decks of 3 by 8-in. bracing
+were used, depending on the height of the bents. These bents were framed
+on the ground in position and raised by hand. West of Tenth Avenue, the
+sills of the bents rested on four 12 by 12-in. longitudinal timbers,
+each spanning two bays and breaking joints, for convenience in
+supporting the trestle while the tunnels were constructed in open cut
+beneath. These bents were placed 12 ft. on centers, with one 8 by 16-in.
+stringer under each rail, and one 6 by 16-in. jack-stringer supporting
+the overhang of the floor on either side.
+
+The bents along the New York Central freight shed had but two posts of
+12 by 14-in. yellow pine varying from 26 ft, to 31 ft. 9 in. from center
+to center; they had double caps of 12 by 14-in. yellow pine on edge, no
+bottom sills or bracing, and the vibration and wind pressure were taken
+care of by the top bracing and anchorage, as shown by Bent "_G_," on
+Fig. 6.
+
+ [Illustration:
+ Fig. 4.
+ PLANT FOR DISPOSAL OF EXCAVATED MATERIALS PIER NO. 72 N.R.]
+
+The method of erection was as follows: An excavation was made on the
+line of each post, 4 ft. deep and from 4 to 5 ft. square, depending on
+whether it was for a single or reinforced post; 6 in. of concrete was
+placed in the bottom, and on this were laid, at right angles to the
+center of the trench, three 8 by 12-in. timbers varying in length with
+the excavation from 3 to 4 ft. To these timbers was drifted one 12 by
+12-in. timber of the same length as those in the bottom row, but at
+right angles to them. Elevations were then taken on top of the 12 by
+12-in. timber, and the bent was framed complete and of correct height.
+The framing was done south of the line of the trestle and west of the
+freight-house. The framed bents were picked up by a small two-boom
+traveler carrying two double-drum, electric, hoisting engines, and run
+forward into position. A hole had previously been made in the metal
+gutter and canopy of the freight-house, by an experienced roofer, and
+in the freight platform underneath, and, as soon as the bent had been
+dropped into position, it was firmly drifted to the foot-blocks,
+previously described, and the excavation made for them was filled with
+concrete well rammed about the blocks and rounded off 6 in. above the
+surface of the ground. Secure flashings, in two sections, were then made
+about the posts to cover the holes made in the gutter and roof, the
+bottom sections being firmly soldered to the roof or gutter, and the top
+sections, which lapped over the bottom and cleared them 2 in. in all
+directions, were firmly nailed to the posts and the joints leaded. This
+arrangement allowed the bents to move slightly, and at the same time
+made the roof and gutter water-tight. These bents were placed 16 ft. on
+centers to correspond with the spacing of the doors of the freight shed.
+
+Under the cross-overs near Eleventh Avenue, where the tracks had to
+be supported in different positions on the caps, and could no longer
+be kept over the posts, the caps were trussed and the posts were
+reinforced, as shown on Bents "_J_," "_H_," and "_K_," Fig. 5.
+
+ [Illustration:
+ Fig. 5.
+ DETAIL OF BENTS FOR MATERIAL TRESTLE]
+
+The trusses for the through bridge over the tracks were erected on
+Sunday, April 16th. The two trusses, one 122 ft. and the other 165 ft. 8
+in. from center to center of end posts, had been assembled and riveted,
+lying flat on cribwork a few feet above the ground, south of the
+permanent position and between the New York Central tracks and Eleventh
+Avenue. On the date stated, the contractor, having been given permission
+to block the Central's tracks from 5 a.m. to 9 p.m., erected a large
+steel gin pole just south of the correct position of the center of the
+north truss, which was then dragged, from the place where it had been
+assembled, across the railroad tracks until the center of the bottom
+chord was vertically under its true position, the truss still lying flat
+and about at right angles to the center line of the bridge. Chains were
+made fast to the top chord at the middle panel of the truss, which was
+then turned up to a vertical plane, raised to its permanent position,
+and guyed. The gin pole was then shifted and the operation repeated with
+the longer truss, after which, half of the floor beams and a part of the
+top laterals were bolted in position and the guys were removed, the
+bridge being thus erected without the use of falsework of any kind.
+During the lifting there was no sag in either truss that could be
+noticed by the eye. Fig. 1, Plate LV, shows the bridge erected, with
+the exception of the tight timber fence.
+
+Pier No. 72 is directly over the North River Tunnels. When it was turned
+over by the New York Central Railroad Company, the contractor for the
+construction of those tunnels tore down the shed and removed the deck
+and such piles as were in the path of the tubes. This left standing the
+four northernmost, the four southernmost and two centers rows of piles
+for the entire length of the pier. An additional row of piles was then
+driven on either side of the two center rows, and battered so that at
+the elevation of the tunnels they would be close to the center rows
+and leave as much clear space as possible. The pier, therefore, was
+constructed of three independent lines of four-post bents, which,
+however, rested on sills which were continuous throughout the width of
+the pier, as shown by Figs. 2 and 3, Plate LV.
+
+ [Illustration:
+ Fig. 6.
+ DETAIL OF BENTS FOR MATERIAL TRESTLE.]
+
+The bents for the upper floors of the pier were double-decked, with
+12 by 12-in. posts, sills, intermediate and top caps, and 3 by 8-in.
+longitudinal and cross-bracing. The bents for the incline were similar,
+except that those below 16 ft. in height were of single-deck
+construction. The spacing of the bents varied from 9 ft. 6 in. to 12
+ft., except the three outer bays, which had a span of 23 ft., all to
+agree with the position of the pile bents. The double-deck construction
+extended for the full length of the original pier. A single-deck
+extension, of full width and 180 ft. in length, was subsequently built
+for the accommodation of four derricks for handling building material
+and large rock. The piles for this extension were driven in three sets
+of four rows each, similar to those in the old portion of the pier,
+except that the bents were driven with a uniform spacing of 15 ft.
+between centers. The three sets of bents were topped separately with
+12 by 12-in. caps and 12 by 12-in. dock stringers; they were braced with
+both cross and longitudinal low-water bracing, and were tied together by
+a continuous 12 by 12-in. timber over the dock stringers and 12 by
+12-in. packing pieces from stringer to stringer, each of these ties
+being supported in the center of the span over the tunnels by two 2-in.
+hog rods, Section "_A-A_," Fig. 4.
+
+The south side of the upper deck of the pier carried three sets of nine
+hoppers, each set covering 90 ft., a little less than the full length
+between bulkheads of the largest deck scows, with 70 ft. clear between
+sets, to allow for the length of a scow outside of the bulkhead and to
+permit the free movement of boats. Each hopper occupied the full space
+between two bents, and, as the caps were topped by strips of timber of
+triangular section, with a width of 12 in. on the base and a height of
+6 in., protected by a 6 by 6-in. steel angle, each set of hoppers
+presented 90 lin. ft. of continuous dumping room. The bottoms of the
+hoppers, set at an angle of 45°, were formed by 12 by 12-in. timbers
+laid longitudinally, running continuously throughout each set, and
+covered by 3-in. planking. The partitions were formed with 4-in. planks
+securely spiked to uprights from the floor of the hoppers to the caps;
+these partitions narrowed toward the front and bottom so as to fit
+inside the chutes. Each hopper was lined on the bottom and sides with
+½-in. steel plates, and the bottoms were subsequently armored with 2 by
+1-in. square bars laid 3 in. on centers and bolted through the 12 by
+12-in. flooring of the hoppers. The chutes, extending from the bottom of
+the hoppers, were 20 ft. long and 7 ft. wide, in the clear; they were
+formed entirely of steel plates, channels, and angles, and were
+supported from the upper deck of the pier by chains; their lower ends
+were 17 ft. above mean high tide and 14 ft. 6 in. from the string piece
+of the pier. The hoppers and chutes are shown by Fig. 1, Plate LVI.
+
+ [Illustration:
+ Plate LV.
+ Material Trestle Over N.Y.C. & H.R.R.R. Co.'s Tracks;
+ and Construction of Pier No. 72, North River
+ Fig. 1.--Material Trestle Over N.Y.C. & H.R.R.R. Co.'s Tracks.
+ Fig. 2.--Material Trestle Under Construction on Pier No. 72,
+ North River, Showing Clear Water Over Tunnel Location.
+ Fig. 3.--Pier No. 72, North River, Showing Incline as Reconstructed
+ For Locomotives.]
+
+A length of 150 ft. of the north side of the pier was for the use of the
+contractor for the North River tunnels; it was equipped with a set of
+nine chutes similar to those for the south side; they were used but
+little, and were finally removed to make room for a cableway for
+unloading sand and crushed stone.
+
+At the foot of the incline there was a bank of eight telphers running
+on rails securely bolted to the tops of 20-in. I-beams, which were hung
+from stringers resting on the upper caps. The beams were erected in
+pairs, each pair being securely braced together and to the trestle posts
+to prevent swaying. Each telpher occupied the space between two bents,
+about 10 ft., so that the entire bank commanded a length of 80 ft.,
+which was approximately the length of a rock scow between bulkheads. All
+supports for the telphers were provided as a part of the trestle, but
+the machines themselves were a part of the contractor's plant.
+
+Four derricks were erected on the extension, two on the north and two on
+the south edge of the pier, supported on bents at a sufficient elevation
+above the floor to clear a locomotive.
+
+After most of the earth had been excavated, the out-bound set of hoppers
+on the south side of the pier was removed, and two derricks were erected
+in their place and used for unloading sand, crushed stone, and other
+building material.
+
+
+PLANT.
+
+As the use of the 35th Street pier for the disposal of material required
+that the mode of transportation should be by dump-wagons drawn by
+horses, the plant in use by the contractor during that period
+necessarily differed in many respects from what it was later, when Pier
+No. 72 was available. Therefore, the nature of the plant during each
+period will be stated. The plant for each period will be divided into
+five classes:
+
+ 1.--Central Plant:
+ (_a_) Power-Generating Plant.
+ (_b_) Repair Shops.
+ 2.--Retaining-Wall Plant.
+ 3.--Pit-Excavating Plant.
+ 4.--Transportation Plant.
+ 5.--Dock Plant.
+
+Horse-and-Truck Period: July 11th, 1904, to May 22d, 1905.
+
+_1._--_Central Plant._
+
+(_a_).--_Power-Generating Plant._--The contractor's first central
+generating plant was established in a 35 by 85-ft. steel-framed building
+covered with corrugated iron, the long side being parallel to Ninth
+Avenue and 15 ft. from the east house line, and the north end 43 ft.
+south of the south house line of 32d Street. The foundations for the
+building and machinery were of concrete, resting on bed-rock, the floor
+being 20 ft. below the level of the Ninth Avenue curb. The south end of
+the building was the boiler-room and the north end the compressor-room,
+the two being separated by a partition. Coal was delivered into a large
+bin, between the boiler-house and Ninth Avenue, its top being level with
+the street surface, and its base level with the boiler-room floor.
+
+At the end of the horse-and-truck period the plant consisted of:
+
+ Two Rand, straight-line compressors, 24 by 30 in., having a capacity
+ of 1,400 cu. ft. of free air per min. when operating at 86 rev. per
+ min. and compressing to 80 lb. above atmospheric pressure.
+
+ One 10 by 6 by 10-in., Worthington, steam, plunger pump.
+
+ Three horizontal boilers of the locomotive type, each of 125 h.p.
+
+(_b_).--_Repair Shops._--The repair shops, which included blacksmith,
+machine and carpenter shops, were located on the first floor of a 40 by
+70-ft. two-story frame structure, which was in the pit on the north side
+of 31st Street, 48 ft. east of Ninth Avenue. The second floor was on the
+street level, and was used as a storehouse for hand-tools and small
+plant.
+
+The blacksmith shop contained: Four forges with hand blowers, four
+anvils, and hand-tools.
+
+The machine shop contained: One drill press, one shaper (14-in. stroke),
+one 18-in. swing lathe, and one 6-in. bed lathe.
+
+The carpenter shop contained: One circular saw, one wood lathe, and
+hand-tools.
+
+The plant in both machine and carpenter shops was operated by one
+7½-h.p. General Electric motor, the current for which was obtained from
+the Edison Electric Heat, Light, and Power Company.
+
+ [Illustration:
+ Plate LVI.
+ Material Trestle Showing First Chutes in Operation;
+ and Views of East and West Pits at Terminal Site
+ Fig. 1.--Material Trestle, Showing First Chutes in Operation.
+ Fig. 2.--East Pit, Steam Shovel Loading Excavated Material on Car.
+ Fig. 3.--West Pit, Showing Condition on June 28th, 1905.]
+
+_2._--_Retaining-Wall Plant._
+
+ Three cableways, with 35-ft. towers of 12 by 12-in. yellow pine timber
+ capable of spanning 350 ft., and operated by 7 by 10-in. double-drum
+ Lambert hoisting engines mounted with 25-h.p. Lambert upright
+ boilers.
+
+ Five stiff-leg derricks, with masts from 35 to 50 ft. long and booms
+ from 45 to 60 ft. long, operated by 7 by 10-in. Lambert double-drum
+ and swinging gear engines, mounted with 25-h.p. upright Lambert
+ boilers.
+
+ Six Cameron pumps, varying in size from 7 by 6 by 13 in. to 10 by 8
+ by 16 in. The first dimension referring to the diameter of the steam
+ cylinder, the second to that of the water, and the third to the
+ stroke.
+
+ Five Rand sheeting drivers.
+
+ Two Ransome ¾-cu. yd. concrete mixers, mounted on frame, with
+ kerosene driving engine.
+
+ Drills drawn from pit plant as required.
+
+_3._--Pit-Excavating Plant.
+
+ One guy derrick, 50-ft. mast and 45-ft. boom, operated by a Lambert
+ two-drum and swing-gear hoisting engine, with Lambert 25-h.p.
+ upright boiler.
+
+ Three stiff-leg derricks, similar to those used on the retaining wall
+ work.
+
+ Three Bucyrus, 70-ton steam shovels with 3½-cu. yd. dippers.
+
+ One traveling derrick, built with an A-frame of 12 by 12-in. timbers,
+ 15-ft. mast, and 25-ft. boom; the traveler carried an engine and
+ boiler similar to those used on the stiff-leg derricks, and was
+ used on the Seventh and Eighth Avenue sewers, as well as in the pit.
+
+ Ten Rand-Ingersoll rock drills, Nos. 1, 3¼, and 4.
+
+ One Reliance stone crusher (nominal capacity 17 tons of crushed stone
+ per hour) belt-driven by 50-h.p. engine.
+
+_4._--_Transportation Plant._
+
+ During the whole of the first period the transportation plant
+ consisted of two-horse trucks and snatch teams as needed. The number
+ varied greatly from 25 at the beginning and end of the period to an
+ average of 135 from August 1st to December 1st, 1904, about 10% of
+ the total number of teams being used as snatch teams.
+
+_5._--_Dock Plant._
+
+ The only machinery used on the dock during the horse-and-truck period
+ was one stiff-leg derrick similar in size and operation to those
+ described under the head of retaining-wall plant.
+
+The plant described above does not represent that which was used during
+the whole of the horse-and-truck period, but what had accumulated at the
+end of it. The power-generating plant might almost have been omitted
+from this period, as the first compressor did not begin running until
+February, 1905. Previous to that time, the power for drilling, pumping,
+driving, sheeting, etc., was steam furnished by the boilers which
+subsequently drove the compressors, these being brought on the ground
+and fired as occasion required.
+
+
+Train-Disposal Period, Beginning May 22d, 1905.
+
+At the beginning of this period there had been excavated 242,800 cu. yd.
+of earth and 22,800 cu. yd. of rock, of the total excavation of 803,500
+cu. yd. of earth and 804,000 cu. yd. of rock included in the principal
+contract, leaving to be excavated under that contract 560,000 cu. yd. of
+earth and 781,200 cu. yd. of rock, and an additional contract had been
+let to the New York Contracting Company for the terminal power station,
+which increased the earth by 16,500 and the rock by 15,500 cu. yd.
+During the year following, contracts for the east and west portions and
+the sub-structures were let, which brought the total to be excavated,
+after the beginning of the train-disposal period, up to 681,000 cu. yd.
+of earth and 1,494,000 cu. yd. of rock.
+
+The central plant, transportation plant, and dock plant were used
+indiscriminately on all these contracts, and, as no separation can be
+made which will hold good for any appreciable length of time, the plant
+in those classes will be stated in total. The retaining-wall and pit
+plant here given include that used on the principal contract and
+terminal power station only. The power-generating plant given under
+the horse-and-truck period was doubled at the beginning of the
+train-disposal period, but it was still insufficient for the work then
+under contract, and the additional contracts necessitated a greater
+increase. The location had also to be changed to permit the excavation
+of the rock under Ninth Avenue. The old stone church fronting on 34th
+Street, between Seventh and Eighth Avenues, a building 68 ft. wide and
+92 ft. long, made a roomy and very acceptable compressor-house. The
+wooden floors and galleries were removed, and good concrete foundations
+were put in, on which to set the plant; the walls, which were cracked in
+several places, were trussed apart and prevented from moving outward by
+cables passed about the pilasters between the windows.
+
+The boilers were erected south of the church, an ash-pit being first
+built, the full width of it, with the floor on a level with the
+basement. The rear wall of the church formed the north wall of the
+ash-pit, and the south wall and the ends were built of concrete. The
+boilers were set with the fire-doors toward the rear wall of the
+building, and 7 ft. distant from it, and above this fire-room and the
+boilers there was erected a coal-bin of 500 tons capacity. The rear wall
+of the compressor-house formed the north wall of the bin, the section
+of which was an isosceles right-angled triangle. Coal was delivered by
+dumping wagons into a large vault constructed under the sidewalk on 34th
+Street, and was taken from there to the bin by a belt conveyor.
+
+The plant for the second period was as follows:
+
+_1._--_Central Plant._
+
+(_a_).--_Power-Generating Plant._--The plant in the engine-room
+consisted of:
+
+ Three Rand straight-line compressors from the original power plant at
+ Ninth Avenue and 32d Street.
+
+ One Ingersoll straight-line compressor from the old power-house.
+
+ One Rand duplex Corliss, 40 by 48-in. air-compressor, with both air
+ and steam cylinders cross-compounded, and a capacity of 5,600 cu.
+ ft. of free air per min. compressed to 80 lb. at 70 rev. per min.
+
+ Three Rand duplex, 30 by 30-in., compressors, connected with 525-h.p.,
+ 6,600-volt, General Electric motors, with a capacity of 3,000 cu.
+ ft. of free air per min. compressed to 80 lb. at 125 rev. per min.
+
+ Two 10 by 6 by 10-in. Worthington steam plunger pumps.
+
+ One 7½-h.p. General Electric motor for driving the Robbins belt coal
+ conveyor.
+
+ One forced-draft fan (built by the Buffalo Forge and Blower Company),
+ driven by an 8 by 10-in. Buffalo engine.
+
+In the boiler-room there were three 500-h.p. Sterling water-tube
+boilers.
+
+(_b_).--Repair Shops.--The repair shops remained in their old location
+until sufficient room had been excavated to sub-grade in the lot east
+of Eighth Avenue, and then they were moved to the old Ninth Avenue
+power-house which had been erected at that point. The contents of the
+blacksmith shop remained the same as for the first period. The equipment
+of the machine shop was increased by one 18-ton trip-hammer operated by
+air and one bolt-cutting machine, size 1 in. to 1½ in. The carpenter
+shop remained the same except that the electric motor was replaced by a
+25-h.p. single-cylinder air motor; there was added to the repair shop a
+drill shop containing: Four forges with compressed air blowers, four
+anvils, two Ajax 20-ft. drill sharpeners, and one oil blower forge.
+
+_2._--_Retaining-Wall Plant._
+
+The retaining-wall plant was identical with that described for the first
+period, with the addition of two Ransome 1-cu. yd., concrete mixers,
+with vertical engines mounted on the same frame, using compressed air.
+
+_3._--_Pit-Excavating Plant._
+
+The pit-excavating plant included that listed for the first period and,
+in addition, the following:
+
+ One Vulcan, 30-ton, steam shovel, with 1-cu. yd. dipper and a vertical
+ boiler.
+
+ One Ohio, 30-ton, steam shovel, with 1-cu. yd. dipper and a vertical
+ boiler.
+
+ Four guy derricks (50 to 80-ft. masts and 45 to 60-ft. booms),
+ operated by Lambert 7 by 10-in. engines, with two drums and swinging
+ gear, mounted with 25-h.p. vertical boilers, but driven by
+ compressed air.
+
+ Seventy Ingersoll-Rand rock drills, Nos. 1, 3¼, and 4.
+
+ Two Rand quarry bars, cutting 10 ft. in length at one set-up, and
+ mounted with No. 4 drill using a Z-bit.
+
+_4._--_Transportation Plant._
+
+ Twenty-one H. K. Porter locomotives, 10 by 16-in., and 36-in. gauge.
+
+ Three Davenport locomotives, 9 by 16-in., and 36-in. gauge.
+
+ One hundred and forty Western dump-cars, each of 4 cu. yd. capacity.
+
+ One hundred and sixty-five flat cars, with iron skips, each of 4 cu.
+ yd. capacity.
+
+_5._--_Dock Plant._
+
+ Four stiff-leg derricks on extension, having 35-ft. masts and 40-ft.
+ booms, and each operated by a 60-h.p. Lambert, three-drum, electric,
+ hoisting engine.
+
+ One stiff-leg derrick, on the south side of the pier on the upper
+ deck, with a 28-ft. mast operated by a three-drum Lambert engine
+ and a 25-h.p. vertical boiler.
+
+ One stiff-leg derrick, on the north side of the dock on the upper
+ deck, used exclusively for bringing in brick, electric conduit,
+ pipe, and other building material, operated when first erected by a
+ three-drum, steam-driven, Lambert, hoisting engine. This engine was
+ later changed to the derrick on the south side of the dock, and a
+ motor-driven Lambert engine from that derrick was substituted.
+
+ Eight electric telphers.
+
+Ninth Avenue Twin-Tunnels Plant.
+
+ One stiff-leg derrick, previously used in retaining-wall work.
+
+ One Smith concrete mixer, 1 cu. yd. capacity, driven by attached air
+ engine.
+
+ Two cableways taken from the retaining-wall plant and used for mucking
+ out the tunnels after the center pier had been built; driven by air
+ supplied to the original engine.
+
+ One Robbins belt conveyor, driven by a 30-h.p. engine run by air.
+
+ Three 1-cu. yd. Hopple dump-cars.
+
+
+CONSTRUCTION.
+
+Ground was broken for work under the principal contract on July 9th,
+1904, on which date the contractor began cutting asphalt for Trench No.
+1 in 31st Street, and also began making a roadway from Ninth Avenue into
+the pit just south of 32d Street.
+
+_Excavation for Retaining Walls._--Two essentially different methods
+were used in excavating for and building the retaining walls; one,
+construction in trench, the other, construction on bench. In general,
+the trench method was used wherever the rock on which the wall was to be
+founded was 12 ft. or more below the surface of the street; or, what is
+perhaps a more exact statement, as it includes the determining factor,
+where the buildings adjoining the wall location were not founded on
+rock.
+
+In the trench method the base of the wall was staked out on the surface
+of the ground, the required width being determined by the elevation of
+the rock, as shown by the borings. The contractor then added as much
+width as he desired for sheeting and working space, and excavated to a
+depth of about 5 ft. before setting any timber. In some cases the depth
+of 5 ft. was excavated before the cableway or derrick for the excavation
+was erected, the wagons being driven directly into the excavation and
+loaded by hand, but, usually, the cableway was first erected, and
+buckets were used from the start. After the first 5 ft. had been
+excavated, two sets of rangers and struts were set, the first in the
+bottom of the excavation and the second at the level of the street
+surface, supported by posts resting on the bottom rangers. The sheeting
+was then set, and all voids back of it were filled with clean earth and
+well tamped. The toe of the sheeting was kept level with the bottom of
+the excavation until the ground-water was reached, after which it was
+kept from 3 to 5 ft. ahead of the digging.
+
+The sheeting used was 3-in., in variable widths; it was always tongued
+and grooved on the side of the trench next to the buildings and in the
+deeper excavations on both sides of the trench, and was driven by wooden
+mauls above the ground-water level, but steam sheeting-drivers were used
+below that elevation. Struts, rangers, and posts were generally 12 by
+12-in.
+
+Some exceedingly bad material was encountered in the deeper excavations,
+beds of quicksand being passed through, varying in thickness from 1 to
+18 ft., the latter, in 31st Street between Seventh and Eighth Avenues,
+in the deepest excavation made. After encountering the fine sand in that
+trench, no headway was made until a tight wooden cylinder was sunk
+through the sand by excavating the material inside of it and heavily
+weighting the shell with pig iron. When this cylinder had reached the
+gravel, which lay below the sand, it was used as a sump, and the water
+level was kept below the bottom of the excavation, which permitted good
+progress. Sand continued to flow under the sheeting to such an extent,
+however, that the front walls of four adjoining buildings were badly
+cracked and had to be taken down and rebuilt. All the stoops along this
+trench settled, and had to be repaired.
+
+The bench method of excavating for the retaining wall was very simple,
+and was used only where the rock lay near the surface and the adjoining
+buildings were founded on it, the overlying material being in such case
+dry, and consequently firm, little or no shoring was required. The
+method was to extend the pit excavation to a width of 2 or 3 ft. beyond
+the proposed back of the retaining wall, and to carry that width down to
+the depth required for its base, below which the excavation was narrowed
+to 1 ft. inside of the face of the wall and continued either before it
+was built or subsequently.
+
+_Retaining-Wall Construction._--The concrete walls were built in
+sections 50 ft. in length, except where that spacing would bring an
+expansion joint under a girder pocket or just on line with a tier of
+struts, in which cases the section was shortened as required. Trenches
+were never allowed to remain open at the full depth, the concreting
+being started as soon after the necessary length of rock had been
+uncovered as the forms and preliminary work for a section could be
+prepared. Each section was a monolith, except in a few cases where
+very heavy rains made it impossible to hold the laborers.
+
+The various operations in building the concrete wall are shown on
+Fig. 7. Guide-planks, "_a a_," Section "_A-A_," were securely spiked
+to alternate tiers of struts for the length of the section, the face
+of each guide-plank being set on line with the intended face of the
+concrete wall, and 2-in. tongued-and-grooved spruce plank were laid
+along the guide-plank to the height of the bottom strut and securely
+braced from the front sheeting. A 4-in. brick wall was built
+simultaneously on line with the back of the wall to the height of
+the first step. Where the bottom strut was below that elevation, the
+brickwork was left low at that immediate point and built up when the
+strut was removed. The brick wall was then water-proofed on the side
+toward the concrete, and loose laps of the water-proofing were allowed
+to hang over the brickwork and at least 8 in. down the back. A 6-in.
+vitrified pipe drain was then laid along the surface of the rock just
+outside of the brick wall, the joints in the pipe being caulked with
+oakum saturated in cement, and pointed with cement mortar above a line
+1 in. below the horizontal diameter, the remainder of each joint being
+left open. Cross-drains were laid from tees in the back drain to the
+face of the wall at all low points in the rock and at least for every
+25 ft. of wall length, the joints of these discharge pipes being caulked
+and cemented throughout. The surface of the rock was then washed and
+scraped clean, and was covered with about 1 in. of mortar, after which
+the section was ready for concrete.
+
+The building of monolithic sections in trenches required that the thrust
+from one set of struts be taken by the concrete before the set above
+could be removed, and necessarily caused slow progress, the rate at
+which concrete was deposited being just sufficient to prevent one layer
+from setting before the next layer above could be placed.
+
+The concrete used was mixed in the proportions of 1 part of cement to
+3 parts of sand and 6 parts of stone, in 2-bag batches, in ¾-yd. and
+1-yd. Ransome portable mixers mounted with air-driven engines on the same
+frame. These mixers were placed at the surface, and were charged with
+barrows, the correct quantities of sand and stone for each batch being
+measured in rectangular boxes previous to loading the barrows. The
+concrete was discharged from the mixer into a hopper which divided into
+two chutes, only one of which was used at a time, the concrete being
+shoveled from the bottom of the chutes to its final position. Facing
+mortar, 2 in. thick, was deposited simultaneously with the concrete, and
+was kept separate from it by a steel diaphragm until both were in place,
+when the diaphragm was removed and the two were spaded together. The
+bottoms of the guide-planks were cut off just above the concrete as it
+progressed, and, as soon as the wall had reached a strut at one end of
+the section, that strut was removed, the form was built up to the next
+strut, at front and back, and braced to the sheeting, so that, by the
+time the entire length of the section had been carried up to the level
+of the first line of struts, forms were ready at one end for the
+succeeding layers. The layers of concrete never exceeded 8 in. in
+height, and at times there were slight delays in the concreting while
+the carpenters made ready the next lift of forms, but such delays were
+rarely long enough to permit the concrete to take its initial set.
+
+ [Illustration:
+ Fig. 7.
+ SKETCH SHOWING FORMS FOR, AND METHOD OF, CONCRETING RETAINING WALLS
+ IN TRENCH.]
+
+After a section of concrete had firmly set, both back and front forms
+were removed, and the thrust from the sides of the trench was
+transferred directly to the finished wall. The face of the wall was
+rubbed with a cement brick to remove the marks of the plank, and was
+then coated with a wash of thin cement grout. The water-proofing and
+brick armor were then continued up the back of the wall, the spaces
+between the lines of braces being first water-proofed and bricked, and
+the braces transferred to the finished surface, after which the omitted
+panels were completed. The water-proofing consisted of three layers of
+Hydrex felt, of a brand known as Pennsylvania Special, and four layers
+of coal-tar pitch. The pitch contained not less than 25% of carbon,
+softened at 60° Fahr., and melted at a point between 96° and 106° Fahr.
+The melting point was determined by placing 1 gramme of pitch on a lead
+disk over a hole, 5/16-in. in diameter, and immersed in water which was
+heated at the rate of 1° per min.; the temperature of the water at the
+time the pitch ran through the hole was considered as the melting point.
+
+In order to prevent the water-proofing from being torn at the joint
+between sections when they contract from changes in temperature, a
+vertical strip of felt, 6 in. wide, was pitched over each joint, lapping
+3 in. on each concrete section. The back of this strip was not pitched,
+but was covered with pulverized soapstone, so that the water-proofing
+sheet was free from the wall for a distance of 3 in. on either side of
+each joint.
+
+Concreting was continued during the severest weather, one section being
+placed when the thermometer was 5° above zero. When the thermometer was
+below the freezing point both sand and stone were heated by wood fires
+in large pipes under the supply piles; the temperature of the mix was
+taken frequently, and was kept above 40 degrees. Numerous tests made
+while the work was in progress showed that, while the temperature fell
+slightly soon after the concrete was deposited, it was always from 2° to
+5° higher at the end of 2 hours. The face and back of the concrete were
+prevented from freezing by a liberal packing of salt hay just outside
+the forms.
+
+A vertical hog trough, 24 in. wide and 9 in. deep, was placed in one
+end of each section, for its full height below the bridge seat, into
+which the next section keyed, and, when the temperature at the time
+of concreting was below 50° Fahr., a compression joint was formed by
+placing a strip of heavy deadening felt, 2 ft. wide, on the end of the
+completed section next to the face and covering the remainder of the
+end with two ply of the felt and pitch water-proofing; the one ply of
+deadening felt near the face was about the same thickness as the two ply
+of water-proofing, and was used to prevent the pitch from being squeezed
+out of the joint to the face of the wall.
+
+The excavation for the retaining walls in 31st and 33d Streets were in
+all cases made of sufficient width to receive the sewers, which were
+laid as soon as the back-fill, carefully rammed and puddled, had reached
+the proper elevations; the back-filling was then completed, and the gas
+and water mains were afterward laid in separate trenches.
+
+ [Illustration:
+ Fig. 8.
+ SKETCH SHOWING FORMS AND BRACING FOR NINTH AVENUE WALL]
+
+The sections of concrete built in trench varied in height from 13 to
+59 ft. from the base to the top of the back wall. With the exception of
+the Seventh Avenue wall, 50 ft. in height, and the Ninth Avenue wall,
+62 ft. in height, none of those sections constructed by the bench
+method was more than 14 ft. The forms and bracing for these walls were
+substantially the same, except that the low walls were built in lengths
+of approximately 50 ft., while the forms for the Seventh and Ninth
+Avenue walls were only 20 ft. long.
+
+The forms and bracing for the Ninth Avenue walls are shown on Fig. 8.
+These forms were built in one piece and moved ahead from section to
+section, and they were firmly braced from the bottom with raker braces
+to a point 36 ft. above the base, the upper part being held in place by
+¾-in. bolts passed through the forms and anchored by cables to bolts
+grouted into the rock behind.
+
+After the forms had been set and braced, an 8-in. brick wall was laid
+up the face of the rock, containing a vertical line of three-cell hollow
+tile block every 5 ft. of length, and laid to conform as nearly as
+possible to the face of the rock, all voids being filled with broken
+stone. Water-proofing, similar to that described for the walls in the
+trench, was then applied to the brick and tile wall for the full height,
+and firmly braced to the front forms, the braces being removed as the
+concrete reached them. The concrete was mixed at the street level and
+deposited through chutes, as described previously.
+
+Tables 1, 2, and 3 show the quantity of cement used in each section of
+retaining wall, and give figures by which the quantities of other
+materials may be determined.
+
+_Pit Excavation._--The pit excavation during the horse-and-truck period
+was largely preparatory work done to get the excavation in good shape
+for handling spoil trains after Pier No. 72 and the trestle approach
+were finished. This required an open cut from Ninth to Seventh Avenues
+at a sufficient depth below the sewers and other substructures in the
+avenues to clear a locomotive, and wide enough for both running and
+loading tracks, also the building of the cast-iron sewer in Eighth
+Avenue across the entire excavation, with enough of the temporary
+bridging to support it. The building of the trestle in Eighth Avenue
+was essentially a part of the pit excavation, as the progress of one
+depended greatly on that of the other.
+
+Excavation was commenced on July 12th, 1904, for the crossing under
+Ninth Avenue, and in the pit east of Ninth Avenue along 32d Street. The
+line chosen for the opening cut was down the center of the pit, as it
+was not safe to excavate near the bounding streets until after the
+completion of the enclosing retaining wall. The excavation was started
+by hand, but three 70-ton Bucyrus steam shovels were put to work as soon
+as they could be delivered, the first on July 25th and the third on
+September 12th. The excavated material was loaded by the shovels on
+end-dump wagons, each having a capacity of 2 cu. yd., and was conveyed
+in them to the dumping board at 35th Street. The average number of teams
+was 135, 10% being snatch teams to pull the wagons out of the pit and to
+assist them up the runway at the dumping board. The teams averaged only
+seven trips per day of 10 hours, considerable delay being caused by the
+trains of the New York Central Railroad at Eleventh Avenue. The number
+of teams was not sufficient, therefore, to keep the three shovels busy
+when they were all in good digging, but the dumping board was taxed to
+accommodate that number, and little would have been gained by increasing
+it. The digging was very good during this period, practically no rock
+being encountered, and the building foundations were too light to
+present any obstacle to such powerful shovels. The capacity of their
+dippers was 3½ cu. yd., so that one dipperful meant one truck loaded and
+running over. The output from August to November, inclusive, averaged
+40,000 cu. yd. per month; one shift only was worked per day, and
+although the quantity was not large for three such powerful shovels, it
+was large to truck through the streets, and required that one team pass
+a given point every 18 sec. At the end of November the opening up of
+the pit had been accomplished, considerable rock had been stripped
+near Ninth Avenue, and the streets had become so icy that the cost of
+transportation was practically doubled; work in the pit, therefore, was
+much curtailed, and amounted to continuous work for one shovel from that
+time until the end of the period, May 22d, 1905, when Pier No. 72 was
+put in service and transportation by train began. Figs. 2 and 3, Plate
+LVI, show the condition of the pit east and west of Eighth Avenue,
+respectively, on that date.
+
+ [Illustration:
+ Fig. 9.
+ SKETCH SHOWING TYPICAL BENT OF TRESTLE SUPPORTING EIGHTH AVENUE]
+
+The work of excavating for and building the temporary street bridge,
+a typical bent and bracing for which are shown on Fig. 9, and the
+cast-iron sewer and water mains in Eighth Avenue, was commenced on
+September 3d, 1904. The trestle was a double-decked structure of yellow
+pine, with 10 by 10-in. posts and sills, 10 by 14-in. intermediate and
+top caps, and 2 by 10-in. longitudinal and cross-braces. The trestle was
+further stiffened longitudinally by four lines of 8 by 10-in. struts,
+butted between the intermediate caps, and held in position by 2 by 8-in.
+splice-plates resting on top of them. The intermediate caps were at an
+elevation of 15 ft. below the surface of the street, and above that line
+the longitudinal bracing was continuous, while below it the bents were
+braced in pairs, the bracing being omitted from every second bay. Below
+the intermediate cap the bents were uniform for the entire width of the
+trestle, but the top cap was not continuous, being 5 ft. below the
+surface under the trolley tracks, and only 18 in., the depth of
+stringers and planking, beyond. The stringers under the trolley tracks
+were 8 by 16-in. yellow pine, spaced three to a track, and those for the
+driveway were 6 by 14-in., spaced 1 ft. 6 in. on centers, the planking
+being 4-in. yellow pine.
+
+The first step in the construction was to excavate a trench 15 ft. wide
+on the west side of the street, the east side of the trench being 4 ft.
+west of the westernmost trolley rail. While this work was in progress,
+all vehicular traffic was turned to that part of the avenue east of the
+westerly trolley rail. The trench was sheeted and timbered, and carried
+to a depth sufficient to receive the intermediate cap. That portion of
+the bent from the bottom of the intermediate cap to the bottom of the
+top cap was then erected for the width of the trench, after which the
+60-in. cast-iron sewer and the 48-in. water main were laid in position
+and caulked. The top cap, stringers, and planking were then laid, for
+the full width of the trestle west of the trolley tracks. This work was
+finished and the sewage turned into the new sewer in April, 1905.
+
+As the planking was laid west of the trolley tracks, traffic was turned
+to that side of the street, and the material east of the tracks was
+excavated to its natural slope. Trenches were then dug under the tracks
+on the line of the bents, and the caps were set in position on blocking.
+The material between these trenches was then removed, the tracks being
+supported meanwhile by blocking at least every 6 ft., and the stringers
+and planking were shoved into place. Excavation was next made between
+the caps to a depth of about 5 ft. below them, needle-beams being placed
+under the caps, one or two at a time, and supported on posts erected in
+these excavations; the material on line of the bents was excavated to
+the depth of the intermediate caps, which were then set, together
+with the posts and bracing for the upper deck of the structure. This
+operation was repeated for the lower deck, about 10 ft. being gained for
+each change of posts, and three shifts, therefore, were required.
+
+At the beginning of the train-transportation period, May 22d, 1905, two
+shifts of 10 hours each were inaugurated, and the earth was handled at
+the rate of from 85,000 to 90,000 cu. yd. per month; but, by the end of
+August, when a little more than 60% of the total earth had been disposed
+of, the rock began to interfere very greatly with the progress. The
+strike of the rock was almost directly north and south, and its surface
+formed broken ridges running in that direction, with deep valleys
+between. The dip was almost vertical near Ninth Avenue, and about 70°
+toward the west near Seventh Avenue. This condition made it necessary to
+turn the shovels parallel to the ridges in order to strip the rock for
+drilling; and, as the ridges were very broken, the shovels continued to
+bump into them on all occasions, making it necessary to move back and
+start other cuts or stand and wait for the rock to be drilled and
+blasted. One small Vulcan steam shovel, with vertical boiler and ¾-cu.
+yd. dipper, had been brought on the work to be used in stripping rock,
+and was moved from place to place so much more easily than the large
+ones that an Ohio shovel of the same general type was purchased in
+October, and thereafter the stripping was done largely by the two small
+shovels and by hand, the large shovels being used almost exclusively in
+handling rock.
+
+The drilling necessary to remove the rock was very large in amount and
+also per yard excavated. In order not to damage the retaining walls and
+the rock underlying them, holes spaced at 5-in. centers were drilled
+1 ft. away from the face of the walls and on the same batter. These
+breaking holes alone amounted to a total of 210,000 lin. ft., or 1 ft.
+of hole for each 3½ cu. yd. of rock excavated; and the regulations of
+the Bureau of Combustibles, which prevented springing, caused the
+blasting holes to be placed very close together and required a total of
+about 420,000 lin. ft., making 630,000 ft. If to this is added the block
+holes, for some of the rock broke very large, it will show at least
+1 ft. of drill hole for each cubic yard of rock excavated, about ten
+times the average on general railroad work.
+
+ [Transcriber's Note:
+ The three numbered Tables were originally printed at full width, with
+ columns (1)-(13) displayed in a single row.]
+
+TABLE 1a.--Record of Retaining-Wall Sections, Terminal Station.
+
+West Thirty-first Street from Seventh Avenue to Ninth Avenue.
+
+ (1) Section No.
+ (2) Stations.
+ (3) Contents of section, in cubic yards.
+ (4) Barrels of cement used for facing.
+ (5) Cubic yards of facing mortar equivalent.
+ (6) Barrels of cement used for bed mortar.
+ (7) Cubic yards of bed mortar equivalent.
+ (8) Cubic yards of embedded stone.
+
+ (1) (2) (3) (4) (5) (6) (7) (8)
+ _____________________________________________________________________
+ | 1 {165 + 05.8} | | | | | | |
+ | {165 + 66.0} | 617.48 | 17.50 | 5.95 | ... | ... | ... |
+ | 2 {165 + 66.0} | | | | | | |
+ | {165 + 95.4} | 233.96 | 10.25 | 3.49 | ... | ... | ... |
+ | 3 {165 + 95.4} | | | | | | |
+ | {166 + 41.2} | 355.20 | 24.50 | 8.34 | ... | ... | ... |
+ | 4 {171 + 03.4} | | | | | | |
+ | {171 + 53.4} | 309.29 | 67.50 | 23.00 | ... | ... | ... |
+ | 5 {177 + 44.0} | | | | | | |
+ | {177 + 94.0} | 109.62 | 30.25 | 10.30 | ... | ... | ... |
+ | 6 {171 + 53.4} | | | | | | |
+ | {171 + 83.0} | 246.35 | 27.75 | 9.44 | ... | ... | ... |
+ | 7 {166 + 41.2} | | | | | | |
+ | {166 + 79.0} | 644.12 | 77.50 | 26.37 | ... | ... | ... |
+ | 8 {171 + 83.0} | | | | | | |
+ | {172 + 12.0} | 394.43 | 63.75 | 21.69 | ... | ... | ... |
+ | 9 {166 + 79.0} | | | | | | |
+ | {167 + 20.5} | 974.58 |103.75 | 35.30 | 2.50 | 0.85 | 7.96 |
+ | 10 {170 + 16.6} | | | | | | |
+ | {170 + 58.6} | 767.34 | 92.50 | 31.48 | 2.75 | 0.94 | ... |
+ | 11 {170 + 58.6} | | | | | | |
+ | {171 + 03.4} | 599.17 | 77.00 | 26.20 | 10.25 | 3.49 | ... |
+ | 12 {167 + 20.5} | | | | | | |
+ | {167 + 43.9} | 535.28 | 50.50 | 17.18 | 2.00 | 0.68 | 4.00 |
+ | 13 {175 + 18.5} | | | | | | |
+ | {175 + 61.8} | 553.04 | 62.00 | 21.10 | 5.25 | 1.79 | ... |
+ | 14 {177 + 02.9} | | | | | | |
+ | {177 + 44.0} | 305.12 | 49.25 | 16.76 | 4.50 | 1.53 | ... |
+ | 15 {175 + 61.8} | | | | | | |
+ | {176 + 91.7} | 429.88 | 50.00 | 17.01 | 1.50 | 0.51 | ... |
+ | 16 {176 + 62.5} | | | | | | |
+ | {177 + 02.9} | 675.64 | 77.50 | 26.37 | 6.25 | 2.13 | ... |
+ | 17 {174 + 04.5} | | | | | | |
+ | {174 + 29.6} | 162.98 | 29.00 | 9.87 | 3.50 | 1.19 | ... |
+ | 18 {175 + 91.7} | | | | | | |
+ | {176 + 21.5} | 698.88 | 46.25 | 15.72 | 4.50 | 1.53 | 15.86 |
+ | 19 {176 + 21.5} | | | | | | |
+ | {176 + 62.5} | 1,166.79 | 81.50 | 27.73 | 4.00 | 1.36 | 34.96 |
+ | 20 {167 + 43.9} | | | | | | |
+ | {167 + 92.6} | 975.53 | 95.75 | 32.58 | 3.25 | 1.11 | 36.99 |
+ | 21 {172 + 12.0} | | | | | | |
+ | {172 + 45.2} | 271.48 | 31.75 | 10.80 | 2.50 | 0.85 | 8.65 |
+ | 22 {168 + 41.3} | | | | | | |
+ | {168 + 72.6} | 316.30 | 44.00 | 14.97 | 5.25 | 1.79 | 7.18 |
+ | 23 {173 + 63.6} | | | | | | |
+ | {174 + 04.5} | 529.33 | 54.75 | 18.63 | 4.75 | 1.62 | 1.25 |
+ | 24 {167 + 92.6} | | | | | | |
+ | {168 + 41.3} | 1,010.64 | 66.00 | 22.46 | 5.50 | 1.87 | 10.16 |
+ | 25 {173 + 21.2} | | | | | | |
+ | {173 + 63.6} | 675.21 | 77.75 | 26.46 | 2.50 | 0.85 | 12.00 |
+ | 26 {164 + 72.5} | | | | | | |
+ | {165 + 05.8} | 458.22 | 40.00 | 13.61 | 5.50 | 1.87 | 22.37 |
+ | 27 {172 + 81.9} | | | | | | |
+ | {173 + 21.2} | 409.43 | 35.00 | 11.91 | 9.75 | 3.31 | 4.64 |
+ | 28 {164 + 27.6} | | | | | | |
+ | {164 + 72.5} | 658.46 | 72.00 | 24.50 | 1.50 | 0.51 | 16.40 |
+ | 29 {172 + 45.2} | | | | | | |
+ | {172 + 81.9} | 345.89 | 30.25 | 10.29 | 5.00 | 1.70 | 1.62 |
+ | 31 {174 + 78.0} | | | | | | |
+ | {175 + 18.5} | 507.50 | 35.75 | 12.17 | 3.00 | 1.02 | 17.09 |
+ | 32 {174 + 29.6} | | | | | | |
+ | {174 + 78.0} | 396.99 | 43.75 | 14.89 | 1.75 | 0.60 | 6.50 |
+ | 43 {177 + 94.0} | | | | | | |
+ | {178 + 44.1} | 194.07 | 30.00 | 10.21 | 2.00 | 0.68 | 8.35 |
+ | Pier {168 + 72.6} | | | | | | |
+ | {168 + 81.1} | 106.52 | ... | ... | ... | ... | ... |
+ | 76 {178 + 44.1} | | | | | | |
+ | {178 + 94.1} | 136.32 | 12.75 | 4.34 | 4.75 | 1.62 | ... |
+ | 79 {178 + 94.1} | | | | | | |
+ | {179 + 44.1} | 118.07 | 9.00 | 3.06 | 8.50 | 1.19 | ... |
+ | 82 {179 + 44.1} | | | | | | |
+ | {179 + 93.7} | 126.12 | 6.50 | 2.21 | 2.50 | 0.85 | ... |
+ | 84 {179 + 93.7} | | | | | | |
+ | {180 + 44.2} | 126.77 | 6.75 | 2.30 | 2.25 | 0.77 | ... |
+ | 86 {180 + 44.2} | | | | | | |
+ | {180 + 93.6} | 162.48 | 8.00 | 2.72 | 2.75 | 0.94 | ... |
+ | 90 {180 + 93.6} | | | | | | |
+ | {181 + 17.9} | 92.52 | 4.00 | 1.36 | 1.00 | 0.34 | ... |
+ |___________________|__________|_______|_______|_______|______|_______|
+
+TABLE 1b.--Record of Retaining-Wall Sections, Terminal Station.
+
+West Thirty-first Street from Seventh Avenue to Ninth Avenue.
+
+ (1) Section No.
+ (2) Stations.
+ (9) Cubic yards of concrete in section (net).
+(10) Barrels of cement used in concrete.
+(11) Barrels of cement per cubic yard of concrete.
+(12) Concrete started.
+(13) Concrete finished.
+
+ (1) (2) (9) (10) (11) (12) (13)
+ ______________________________________________________________________
+ | 1 {165 + 05.8} | | | | | |
+ | {165 + 66.0} | 611.53 | 731.50 | 1.20 | 11/4/04 | 11/20/04 |
+ | 2 {165 + 66.0} | | | | | |
+ | {165 + 95.4} | 230.47 | 277.25 | 1.20 | 11/21/04 | 11/27/04 |
+ | 3 {165 + 95.4} | | | | | |
+ | {166 + 41.2} | 346.86 | 398.25 | 1.15 | 11/26/04 | 12/3/04 |
+ | 4 {171 + 03.4} | | | | | |
+ | {171 + 53.4} | 286.29 | 360.50 | 1.26 | 12/2/04 | 12/10/04 |
+ | 5 {177 + 44.0} | | | | | |
+ | {177 + 94.0} | 99.32 | 120.75 | 1.22 | 12/28/04 | 12/30/04 |
+ | 6 {171 + 53.4} | | | | | |
+ | {171 + 83.0} | 236.91 | 292.50 | 1.23 | 1/2/05 | 1/11/05 |
+ | 7 {166 + 41.2} | | | | | |
+ | {166 + 79.0} | 617.75 | 737.00 | 1.19 | 1/13/05 | 2/4/05 |
+ | 8 {171 + 83.0} | | | | | |
+ | {172 + 12.0} | 372.74 | 420.75 | 1.13 | 1/14/05 | 1/28/05 |
+ | 9 {166 + 79.0} | | | | | |
+ | {167 + 20.5} | 930.47 | 1,066.25 | 1.14 | 2/18/05 | 3/13/05 |
+ | 10 {170 + 16.6} | | | | | |
+ | {170 + 58.6} | 734.92 | 852.50 | 1.16 | 1/31/05 | 2/25/05 |
+ | 11 {170 + 58.6} | | | | | |
+ | {171 + 03.4} | 569.48 | 689.75 | 1.21 | 3/11/05 | 3/23/05 |
+ | 12 {167 + 20.5} | | | | | |
+ | {167 + 43.9} | 513.42 | 611.75 | 1.19 | 3/9/05 | 3/26/05 |
+ | 13 {175 + 18.5} | | | | | |
+ | {175 + 61.8} | 530.15 | 630.50 | 1.19 | 3/15/05 | 3/29/05 |
+ | 14 {177 + 02.9} | | | | | |
+ | {177 + 44.0} | 286.83 | 340.25 | 1.19 | 3/26/05 | 3/31/05 |
+ | 15 {175 + 61.8} | | | | | |
+ | {176 + 91.7} | 412.36 | 472.50 | 1.15 | 3/28/05 | 4/14/05 |
+ | 16 {176 + 62.5} | | | | | |
+ | {177 + 02.9} | 647.14 | 788.00 | 1.22 | 4/1/05 | 4/17/05 |
+ | 17 {174 + 04.5} | | | | | |
+ | {174 + 29.6} | 151.92 | 182.50 | 1.20 | 5/3/05 | 5/6/05 |
+ | 18 {175 + 91.7} | | | | | |
+ | {176 + 21.5} | 665.77 | 801.00 | 1.20 | 5/9/05 | 5/19/05 |
+ | 19 {176 + 21.5} | | | | | |
+ | {176 + 62.5} | 1,102.74 | 1,354.50 | 1.23 | 5/15/05 | 5/28/05 |
+ | 20 {167 + 43.9} | | | | | |
+ | {167 + 92.6} | 904.85 | 1,012.75 | 1.12 | 5/25/05 | 6/3/05 |
+ | 21 {172 + 12.0} | | | | | |
+ | {172 + 45.2} | 251.18 | 311.50 | 1.24 | 5/29/05 | 6/3/05 |
+ | 22 {168 + 41.3} | | | | | |
+ | {168 + 72.6} | 292.36 | 338.75 | 1.16 | 6/5/05 | 6/10/05 |
+ | 23 {173 + 63.6} | | | | | |
+ | {174 + 04.5} | 507.83 | 587.25 | 1.16 | 6/5/05 | 6/13/05 |
+ | 24 {167 + 92.6} | | | | | |
+ | {168 + 41.3} | 976.15 | 1,038.75 | 1.07 | 6/8/05 | 6/21/05 |
+ | 25 {173 + 21.2} | | | | | |
+ | {173 + 63.6} | 635.90 | 776.25 | 1.22 | 6/16/05 | 6/24/05 |
+ | 26 {164 + 72.5} | | | | | |
+ | {165 + 05.8} | 420.37 | 532.00 | 1.26 | 6/23/05 | 6/28/05 |
+ | 27 {172 + 81.9} | | | | | |
+ | {173 + 21.2} | 389.57 | 450.00 | 1.16 | 6/27/05 | 7/7/05 |
+ | 28 {164 + 27.6} | | | | | |
+ | {164 + 72.5} | 617.05 | 726.25 | 1.18 | 6/29/05 | 7/7/05 |
+ | 29 {172 + 45.2} | | | | | |
+ | {172 + 81.9} | 332.28 | 384.00 | 1.16 | 7/11/05 | 7/19/05 |
+ | 31 {174 + 78.0} | | | | | |
+ | {175 + 18.5} | 477.22 | 567.50 | 1.19 | 7/29/05 | 8/6/05 |
+ | 32 {174 + 29.6} | | | | | |
+ | {174 + 78.0} | 375.00 | 434.25 | 1.16 | 8/5/05 | 8/12/05 |
+ | 43 {177 + 94.0} | | | | | |
+ | {178 + 44.1} | 174.83 | 219.75 | 1.26 | 11/9/05 | 11/12/05 |
+ | Pier {168 + 72.6} | | | | | |
+ | {168 + 81.1} | 106.52 | 144.00 | 1.35 | 12/6/06 | 12/8/06 |
+ | 76 {178 + 44.1} | | | | | |
+ | {178 + 94.1} | 130.36 | 142.50 | 1.09 | 7/8/07 | 7/10/07 |
+ | 79 {178 + 94.1} | | | | | |
+ | {179 + 44.1} | 113.82 | 129.50 | 1.14 | 7/15/07 | 7/16/07 |
+ | 82 {179 + 44.1} | | | | | |
+ | {179 + 93.7} | 123.06 | 131.75 | 1.07 | 7/22/07 | 7/23/07 |
+ | 84 {179 + 93.7} | | | | | |
+ | {180 + 44.2} | 123.70 | 133.50 | 1.08 | 7/26/07 | 7/27/07 |
+ | 86 {180 + 44.2} | | | | | |
+ | {180 + 93.6} | 158.82 | 167.00 | 1.05 | 7/30/07 | 7/31/07 |
+ | 90 {180 + 93.6} | | | | | |
+ | {181 + 17.9} | 90.82 | 115.00 | 1.27 | 8/18/08 | 8/18/08 |
+ |___________________|__________|__________|______|__________|__________|
+
+NOTE.--The number of cubic yards of crushed stone used in any section
+can be found by multiplying the figure for that section in Column 10 by
+0.7778.
+
+The number of cubic yards of sand used in any section can be found by
+multiplying: the sum of the figures for that section in Columns 4, 6,
+and 10 by 0.3889.
+
+ REMARKS.--Section No. 4. Amount of sand cut down on a part of this
+ section on account of dust in stone.
+ Section No. 8. O'Rourke stone used on this section, large and full of
+ dust.
+ Section No. 9. Stone crushed on the work used on this section, large
+ and full of dust.
+ Section No. 21. 1:3:5 mix was used in part of this section on account
+ of stone being large.
+ Section No. 24. Different sized stone was shipped on barge and mixed
+ on the board for this section.
+ Section No. 25. 1:3:5 mix used in a small part of this section on
+ account of stone being large.
+ Sections Nos. 76, 82, 84, and 86. Stone contained large amount of
+ dust.
+
+TABLE 2a.--Record of Retaining-wall Sections, Terminal Station.
+
+West Thirty-third Street from Seventh Avenue to Ninth Avenue.
+
+ (1) Section No.
+ (2) Stations.
+ (3) Contents of section, in cubic yards.
+ (4) Barrels of cement used for facing.
+ (5) Cubic yards of facing mortar equivalent.
+ (6) Barrels of cement used for bed mortar.
+ (7) Cubic yards of bed mortar equivalent.
+ (8) Cubic yards of embedded stone.
+
+ (1) (2) (3) (4) (5) (6) (7) (8)
+ ___________________________________________________________________
+ | 30 {170 + 73.2} | | | | | | |
+ | {171 + 16.1} | 364.72 | 42.50 | 14.46 | 4.00 | 1.36 | ... |
+ | 33 {178 + 48.7} | | | | | | |
+ | {178 + 84.1} | 180.40 | 29.50 | 10.04 | 3.50 | 1.19 | ... |
+ | 34 {R 2 + 75.5} | | | | | | |
+ | {170 + 03.5} | 214.12 | 38.00 | 12.93 | 1.00 | 0.34 | 1.50 |
+ | 35 {171 + 16.1} | | | | | | |
+ | {171 + 42.5} | 381.56 | 40.25 | 13.70 | 1.00 | 0.34 | 14.37 |
+ | 36 {170 + 03.6} | | | | | | |
+ | {170 + 25.0} | 150.16 | 20.50 | 6.98 | ... | ... | 6.25 |
+ | 37 {171 + 42.5} | | | | | | |
+ | {171 + 91.3} | 869.40 | 59.50 | 20.25 | 4.50 | 1.53 | 44.96 |
+ | 38 {171 + 91.3} | | | | | | |
+ | {172 + 19.2} | 233.49 | 22.75 | 7.74 | 2.75 | 0.94 | 14.45 |
+ | 39 {179 + 27.2} | | | | | | |
+ | {179 + 64.2} | 255.39 | 32.00 | 10.89 | 3.00 | 1.02 | 9.05 |
+ | 40 {170 + 25.0} | | | | | | |
+ | {170 + 73.2} | 500.73 | 44.25 | 15.06 | 1.00 | 0.34 | 29.64 |
+ | 41 {169 + 50.8} | | | | | | |
+ | {R 2 + 75.5} | 215.93 | 28.25 | 9.61 | 2.00 | 0.68 | ... |
+ | 42 {178 + 84.1} | | | | | | |
+ | {179 + 27.2} | 177.62 | 23.00 | 7.83 | 1.50 | 0.51 | 7.06 |
+ | 44 {180 + 05.5} | | | | | | |
+ | {180 + 44.2} | 936.15 | 58.75 | 19.99 | 10.50 | 3.47 | 73.84 |
+ | 45 {180 + 44.2} | | | | | | |
+ | {180 + 74.9} | 1,133.59 | 60.00 | 20.42 | 5.00 | 1.70 | 60.71 |
+ | 46 {179 + 64.2} | | | | | | |
+ | {180 + 05.5} | 477.14 | 35.00 | 11.91 | 3.75 | 1.28 | 24.58 |
+ | 47 {169 + 00.1} | | | | | | |
+ | {169 + 50.8} | 136.19 | 14.25 | 4.85 | 3.50 | 1.19 | 2.00 |
+ | 48 {178 + 24.1} | | | | | | |
+ | {178 + 48.7} | 192.78 | 21.25 | 7.23 | 2.00 | 0.68 | ... |
+ | 49 {177 + 81.1} | | | | | | |
+ | {178 + 24.1} | 241.51 | 25.25 | 8.59 | 2.50 | 0.85 | 1.33 |
+ | 50 {168 + 03.6} | | | | | | |
+ | {168 + 45.6} | 405.61 | 25.50 | 8.68 | 4.00 | 1.36 | 36.10 |
+ | 51 {177 + 38.4} | | | | | | |
+ | {177 + 81.1} | 100.54 | 12.75 | 4.34 | 3.00 | 1.02 | 0.78 |
+ | 52 {168 + 45.6} | | | | | | |
+ | {168 + 80.1} | 181.96 | 19.00 | 6.47 | 1.00 | 0.34 | 9.03 |
+ | 53 {168 + 80.1} | | | | | | |
+ | {169 + 00.1} | 41.32 | 3.50 | 1.19 | ... | ... | ... |
+ | 55 {176 + 90.0} | | | | | | |
+ | {177 + 38.4} | 92.41 | 11.25 | 3.83 | 2.50 | 0.85 | 3.68 |
+ | 56 {167 + 62.1} | | | | | | |
+ | {168 + 03.6} | 383.67 | 33.75 | 11.48 | 3.25 | 1.11 | 36.62 |
+ | 59 {175 + 67.3} | | | | | | |
+ | {175 + 98.9} | 175.61 | 15.50 | 5.27 | 2.50 | 0.85 | 9.37 |
+ | 60 {176 + 49.0} | | | | | | |
+ | {176 + 90.0} | 69.97 | 8.25 | 2.81 | 3.00 | 1.02 | 1.58 |
+ | 61 {175 + 98.9} | | | | | | |
+ | {176 + 49.0} | 104.56 | 8.00 | 2.72 | 3.50 | 1.19 | 3.72 |
+ | 64 {175 + 30.3} | | | | | | |
+ | {175 + 67.3} | 140.15 | 14.75 | 5.02 | 2.75 | 0.94 | ... |
+ | 65 {174 + 85.4} | | | | | | |
+ | {175 + 30.3} | 80.66 | 9.00 | 3.06 | 2.50 | 0.85 | ... |
+ | 66 {174 + 47.9} | | | | | | |
+ | {174 + 85.4} | 68.89 | 5.50 | 1.87 | 3.25 | 1.11 | ... |
+ | 67 {174 + 21.1} | | | | | | |
+ | {174 + 47.9} | 60.14 | 3.00 | 1.02 | 2.00 | 0.68 | 0.92 |
+ | 68 {167 + 12.3} | | | | | | |
+ | {167 + 62.1} | 379.94 | 23.50 | 8.00 | 5.00 | 1.70 | 19.34 |
+ | 69 {173 + 85.6} | | | | | | |
+ | {174 + 21.1} | 77.43 | 6.50 | 2.21 | 3.00 | 1.02 | ... |
+ | 70 {166 + 75.6} | | | | | | |
+ | {167 + 12.3} | 408.81 | 33.75 | 11.48 | 3.75 | 1.28 | ... |
+ | 71 {173 + 46.5} | | | | | | |
+ | {173 + 85.6} | 85.92 | 8.25 | 2.81 | 1.75 | 0.60 | ... |
+ | 74 {172 + 19.2} | | | | | | |
+ | {172 + 73.0} | 449.28 | 22.75 | 7.74 | 6.25 | 2.13 | ... |
+ | 75 {172 + 73.0} | | | | | | |
+ | {173 + 24.0} | 502.20 | 27.25 | 9.27 | 7.00 | 2.38 | ... |
+ | 77 {164 + 77.0} | | | | | | |
+ | {165 + 27.1} | 141.38 | 9.00 | 3.06 | 7.25 | 2.47 | ... |
+ | 78 {168 + 83.4} | | | | | | |
+ | {169 + 18.3} | 63.35 | 3.00 | 1.02 | 1.50 | 0.51 | ... |
+ | 80 {165 + 27.1} | | | | | | |
+ | {165 + 76.6} | 108.86 | 11.75 | 4.00 | 3.00 | 1.02 | ... |
+ | 81 {168 + 45.6} | | | | | | |
+ | {168 + 83.4} | 210.97 | 13.00 | 4.42 | 6.25 | 2.13 | ... |
+ | 83 {165 + 76.6} | | | | | | |
+ | {166 + 20.5} | 108.06 | 8.00 | 2.72 | 3.75 | 1.28 | ... |
+ | 85 {166 + 20.5} | | | | | | |
+ | {166 + 64.6} | 107.52 | 9.00 | 3.06 | 2.25 | 0.76 | ... |
+ | 87 {166 + 64.6} | | | | | | |
+ | {166 + 75.6} | 23.44 | 1.00 | 0.34 | 2.25 | 0.42 | ... |
+ | 88 {164 + 26.3} | | | | | | |
+ | {164 + 77.0} | 317.72 | 24.00 | 8.17 | 2.25 | 0.76 | ... |
+ | 89 {173 + 20.8} | | | | | | |
+ | {173 + 46.5} | 93.51 | 5.60 | 1.70 | 1.50 | 0.51 | ... |
+ | 91 {180 + 74.9} | | | | | | |
+ | {180 + 92.7} | 141.40 | 17.50 | 5.96 | ... | ... | ... |
+ | 92 {180 + 92.7} | | | | | | |
+ | {181 + 28.8} | 118.93 | 19.00 | 6.46 | ... | ... | ... |
+ |_________________|__________|_______|_______|_______|______|_______|
+
+TABLE 2b.--Record of Retaining-wall Sections, Terminal Station.
+
+West Thirty-third Street from Seventh Avenue to Ninth Avenue.
+
+ (1) Section No.
+ (2) Stations.
+ (9) Cubic yards of concrete in section (net).
+(10) Barrels of cement used in concrete.
+(11) Barrels of cement per cubic yard of concrete.
+(12) Concrete started.
+(13) Concrete finished.
+
+ (1) (2) (9) (10) (11) (12) (13)
+ ___________________________________________________________________
+ |30 {170 + 73.2} | | | | | |
+ | {171 + 16.1} | 348.90 | 391.00 | 1.12 | 7/20/05 | 7/26/05 |
+ |33 {178 + 48.7} | | | | | |
+ | {178 + 84.1} | 169.17 | 188.00 | 1.11 | 8/7/05 | 8/11/05 |
+ |34 {R 2 + 75.5} | | | | | |
+ | {170 + 03.5} | 199.35 | 217.25 | 1.09 | 8/14/05 | 8/19/05 |
+ |35 {171 + 16.1} | | | | | |
+ | {171 + 42.5} | 353.15 | 400.25 | 1.13 | 8/16/05 | 8/22/05 |
+ |36 {170 + 03.6} | | | | | |
+ | {170 + 25.0} | 136.93 | 133.75 | 0.98 | 8/19/05 | 8/22/05 |
+ |37 {171 + 42.5} | | | | | |
+ | {171 + 91.3} | 802.66 | 909.00 | 1.13 | 8/22/05 | 9/6/05 |
+ |38 {171 + 91.3} | | | | | |
+ | {172 + 19.2} | 210.36 | 238.50 | 1.13 | 8/24/05 | 8/27/05 |
+ |39 {179 + 27.2} | | | | | |
+ | {179 + 64.2} | 234.43 | 270.25 | 1.15 | 8/29/05 | 9/2/05 |
+ |40 {170 + 25.0} | | | | | |
+ | {170 + 73.2} | 455.69 | 525.75 | 1.15 | 9/11/05 | 9/15/05 |
+ |41 {169 + 50.8} | | | | | |
+ | {R 2 + 75.5} | 205.64 | 236.50 | 1.15 | 10/3/05 | 10/6/05 |
+ |42 {178 + 84.1} | | | | | |
+ | {179 + 27.2} | 162.22 | 194.75 | 1.20 | 10/9/05 | 10/11/05 |
+ |44 {180 + 05.5} | | | | | |
+ | {180 + 44.2} | 838.85 | 987.00 | 1.18 | 11/17/05 | 11/27/05 |
+ |45 {180 + 44.2} | | | | | |
+ | {180 + 74.9} | 1,050.86 | 1,206.00 | 1.15 | 12/13/05 | 12/23/05 |
+ |46 {179 + 64.2} | | | | | |
+ | {180 + 05.5} | 439.37 | 535.00 | 1.22 | 1/15/06 | 1/19/06 |
+ |47 {169 + 00.1} | | | | | |
+ | {169 + 50.8} | 128.15 | 150.50 | 1.17 | 4/4/06 | 4/6/06 |
+ |48 {178 + 24.1} | | | | | |
+ | {178 + 48.7} | 184.87 | 226.00 | 1.22 | 4/24/06 | 4/30/06 |
+ |49 {177 + 81.1} | | | | | |
+ | {178 + 24.1} | 230.74 | 274.00 | 1.19 | 5/21/06 | 5/24/06 |
+ |50 {168 + 03.6} | | | | | |
+ | {168 + 45.6} | 359.47 | 406.00 | 1.13 | 6/13/06 | 6/18/06 |
+ |51 {177 + 38.4} | | | | | |
+ | {177 + 81.1} | 94.40 | 112.00 | 1.19 | 6/20/06 | 6/21/06 |
+ |52 {168 + 45.6} | | | | | |
+ | {168 + 80.1} | 166.12 | 190.00 | 1.14 | 6/25/06 | 6/28/06 |
+ |53 {168 + 80.1} | | | | | |
+ | {169 + 00.1} | 40.13 | 44.50 | 1.11 | 6/29/06 | 6/29/06 |
+ |55 {176 + 90.0} | | | | | |
+ | {177 + 38.4} | 84.05 | 98.25 | 1.17 | 8/17/06 | 8/18/06 |
+ |56 {167 + 62.1} | | | | | |
+ | {168 + 03.6} | 334.46 | 383.50 | 1.14 | 8/28/06 | 9/1/06 |
+ |59 {175 + 67.3} | | | | | |
+ | {175 + 98.9} | 160.12 | 186.00 | 1.16 | 10/15/06 | 10/16/06 |
+ |60 {176 + 49.0} | | | | | |
+ | {176 + 90.0} | 64.56 | 75.00 | 1.16 | 10/17/06 | 10/18/06 |
+ |61 {175 + 98.9} | | | | | |
+ | {176 + 49.0} | 96.93 | 108.00 | 1.11 | 10/19/06 | 10/20/06 |
+ |64 {175 + 30.3} | | | | | |
+ | {175 + 67.3} | 134.19 | 161.50 | 1.20 | 11/21/06 | 11/22/06 |
+ |65 {174 + 85.4} | | | | | |
+ | {175 + 30.3} | 76.75 | 92.75 | 1.21 | 12/14/06 | 12/15/06 |
+ |66 {174 + 47.9} | | | | | |
+ | {174 + 85.4} | 65.91 | 83.50 | 1.27 | 12/18/06 | 12/18/06 |
+ |67 {174 + 21.1} | | | | | |
+ | {174 + 47.9} | 57.52 | 67.50 | 1.17 | 12/21/06 | 12/21/06 |
+ |68 {167 + 12.3} | | | | | |
+ | {167 + 62.1} | 350.90 | 412.50 | 1.17 | 1/2/07 | 1/6/07 |
+ |69 {173 + 85.6} | | | | | |
+ | {174 + 21.1} | 74.20 | 91.00 | 1.23 | 1/29/07 | 1/30/07 |
+ |70 {166 + 75.6} | | | | | |
+ | {167 + 12.3} | 396.05 | 468.50 | 1.18 | 4/2/07 | 4/10/07 |
+ |71 {173 + 46.5} | | | | | |
+ | {173 + 85.6} | 82.51 | 95.75 | 1.16 | 4/17/07 | 4/19/07 |
+ |74 {172 + 19.2} | | | | | |
+ | {172 + 73.0} | 439.41 | 506.00 | 1.15 | 6/20/07 | 6/24/07 |
+ |75 {172 + 73.0} | | | | | |
+ | {173 + 24.0} | 490.55 | 579.00 | 1.18 | 7/8/07 | 8/25/07 |
+ |77 {164 + 77.0} | | | | | |
+ | {165 + 27.1} | 135.85 | 161.50 | 1.19 | 7/13/07 | 7/15/07 |
+ |78 {168 + 83.4} | | | | | |
+ | {169 + 18.3} | 61.82 | 73.00 | 1.18 | 7/13/07 | 7/14/07 |
+ |80 {165 + 27.1} | | | | | |
+ | {165 + 76.6} | 103.84 | 133.50 | 1.28 | 7/18/07 | 7/19/07 |
+ |81 {168 + 45.6} | | | | | |
+ | {168 + 83.4} | 204.42 | 255.75 | 1.25 | 7/20/07 | 7/23/07 |
+ |83 {165 + 76.6} | | | | | |
+ | {166 + 20.5} | 104.06 | 128.50 | 1.23 | 7/25/07 | 7/27/07 |
+ |85 {166 + 20.5} | | | | | |
+ | {166 + 64.6} | 103.70 | 144.50 | 1.39 | 7/29/07 | 7/30/07 |
+ |87 {166 + 64.6} | | | | | |
+ | {166 + 75.6} | 22.68 | 30.00 | 1.32 | 7/31/07 | 7/31/07 |
+ |88 {164 + 26.3} | | | | | |
+ | {164 + 77.0} | 308.79 | 370.00 | 1.20 | 8/8/07 | 8/11/07 |
+ |89 {173 + 20.8} | | | | | |
+ | {173 + 46.5} | 91.30 | 121.75 | 1.33 | 9/7/07 | 9/8/07 |
+ |91 {180 + 74.9} | | | | | |
+ | {180 + 92.7} | 135.44 | 203.50 | 1.50 | 11/18/07 | 11/20/0 |
+ |92 {180 + 92.7} | | | | | |
+ | {181 + 28.8} | 112.47 | 190.00 | 1.69 | 12/1/08 | 12/2/08 |
+ |________________|__________|__________|______|__________|__________|
+
+NOTE.--The number of cubic yards of crushed stone used in any section
+can be found by multiplying the figure for that section in Column 10 by
+0.7778.
+
+The number of cubic yards of sand used in any section can be found by
+multiplying the sum of the figures for that section in Columns 4, 6, and
+10 by 0.3889.
+
+ REMARKS.--Section No. 47. Part of this section was removed on account
+ of damage done by blasting and was replaced by Section No. 78.
+ Section No. 52. All of this section was removed on account of damage
+ done by blasting and was replaced by Section No. 81.
+ Section No. 53. All of this section was removed on account of damage
+ done by blasting and was replaced by Sections Nos. 78 and 81.
+
+TABLE 3a.--Record of Retaining Wall Sections.
+
+ (1) Section No.
+ (2) Stations.
+ (3) Contents of section, in cubic yards.
+ (4) Barrels of cement used for facing.
+ (5) Cubic yards of facing mortar equivalent.
+ (6) Barrels of cement used for bed mortar.
+ (7) Cubic yards of bed mortar equivalent.
+ (8) Cubic yards of embedded stone.
+
+ Power-House.
+
+ (1) (2) (3) (4) (5) (6) (7) (8)
+ ________________________________________________________________
+ | A {L 2 + 75.3} | | | | | | |
+ | {L 3 + 25.3} | 463.28 | 58.25 | 19.82 | 5.50 | 1.87 | 11.50 |
+ | B {L 3 + 25.3} | | | | | | |
+ | {L 3 + 74.9} | 114.78 | 23.00 | 7.83 | 1.75 | 0.60 | 1.50 |
+ | C {169 + 30.8} | | | | | | |
+ | {169 + 74.8} | 179.19 | 34.25 | 11.66 | 1.00 | 0.34 | 3.60 |
+ | D {169 + 74.8} | | | | | | |
+ | {170 + 28.8} | 114.38 | 27.25 | 9.27 | 0.25 | 0.09 | 0.07 |
+ | E {168 + 83.6} | | | | | | |
+ | {169 + 30.8} | 101.20 | 22.00 | 7.49 | 1.50 | 0.51 | 0.65 |
+ | F {L 2 + 78.2} | | | | | | |
+ | {L 3 + 19.6} | 358.80 | 39.50 | 13.44 | 0.75 | 0.26 | 9.50 |
+ | G {L 3 + 19.6} | | | | | | |
+ | {L 3 + 56.9} | 237.33 | 23.00 | 7.83 | 1.00 | 0.34 | 0.74 |
+ | H {L 3 + 56.9} | | | | | | |
+ | {168 + 83.5} | 25.55 | 6.25 | 2.13 | 0.75 | 0.26 | ... |
+ |_________________|________|_______|_______|______|______|_______|
+
+ Seventh Avenue.
+ ________________________________________________________________
+ | 54 {164 + 27.6} | | | | | | |
+ | {L 2 + 32.0} | 764.48 | 69.75 | 23.74 | 3.00 | 1.02 | ... |
+ | 57 {L 2 + 10.3} | | | | | | |
+ | {L 2 + 32.0} | 533.06 | 34.00 | 11.57 | 2.25 | 0.77 | ... |
+ | 58 {L 1 + 87.1} | | | | | | |
+ | {L 2 + 10.3} | 544.54 | 32.25 | 10.97 | 2.00 | 0.68 | 9.80 |
+ | 62 {L 1 + 87.1} | | | | | | |
+ | {L 1 + 64.4} | 575.67 | 30.00 | 10.21 | 3.00 | 1.02 | 6.20 |
+ | 63 {L 1 + 42.4} | | | | | | |
+ | {L 1 + 64.4} | 607.01 | 30.50 | 10.38 | 2.50 | 0.85 | 3.79 |
+ | 72 {L 1 + 42.4} | | | | | | |
+ | {L 1 + 19.6} | 631.97 | 30.00 | 10.21 | 1.75 | 0.60 | 1.18 |
+ | 73 {L 1 + 19.6} | | | | | | |
+ | {L 0 + 97.0} | 573.33 | 25.25 | 8.59 | 0.25 | 0.08 | 2.48 |
+ |_________________|________|_______|_______|______|______|_______|
+
+
+TABLE 3b.--Record of Retaining Wall Sections.
+
+ (1) Section No.
+ (2) Stations.
+ (9) Cubic yards of concrete in section (net).
+(10) Barrels of cement used in concrete.
+(11) Barrels of cement per cubic yard of concrete.
+(12) Concrete started.
+(13) Concrete finished.
+
+ Power-House.
+
+ (1) (2) (9) (10) (11) (12) (13)
+ ________________________________________________________________
+ | A {L 2 + 75.3} | | | | | |
+ | {L 3 + 25.3} | 430.09 | 482.75 | 1.12 | 5/18/05 | 5/25/05 |
+ | B {L 3 + 25.3} | | | | | |
+ | {L 3 + 74.9} | 104.85 | 125.50 | 1.20 | 6/14/05 | 6/16/05 |
+ | C {169 + 30.8} | | | | | |
+ | {169 + 74.8} | 163.59 | 183.00 | 1.12 | 7/10/05 | 7/13/05 |
+ | D {169 + 74.8} | | | | | |
+ | {170 + 28.8} | 104.95 | 119.25 | 1.14 | 7/14/05 | 7/19/05 |
+ | E {168 + 83.6} | | | | | |
+ | {169 + 30.8} | 92.55 | 107.25 | 1.16 | 7/26/05 | 7/28/05 |
+ | F {L 2 + 78.2} | | | | | |
+ | {L 3 + 19.6} | 335.60 | 397.75 | 1.18 | 9/19/05 | 9/24/05 |
+ | G {L 3 + 19.6} | | | | | |
+ | {L 3 + 56.9} | 228.42 | 278.00 | 1.22 | 9/26/05 | 9/29/05 |
+ | H {L 3 + 56.9} | | | | | |
+ | {168 + 83.5} | 23.16 | 28.00 | 1.21 | 9/29/05 | 9/29/05 |
+ |_________________|________|________|______|__________|__________|
+
+ Seventh Avenue.
+ ________________________________________________________________
+ | 54 {164 + 27.6} | | | | | |
+ | {L 2 + 32.0} | 739.72 | 907.50 | 1.23 | 8/6/06 | 8/15/06 |
+ | 57 {L 2 + 10.3} | | | | | |
+ | {L 2 + 32.0} | 520.72 | 610.75 | 1.17 | 9/10/06 | 9/15/06 |
+ | 58 {L 1 + 87.1} | | | | | |
+ | {L 2 + 10.3} | 523.09 | 588.25 | 1.12 | 9/24/06 | 9/28/06 |
+ | 62 {L 1 + 87.1} | | | | | |
+ | {L 1 + 64.4} | 538.24 | 639.50 | 1.19 | 10/24/06 | 10/29/06 |
+ | 63 {L 1 + 42.4} | | | | | |
+ | {L 1 + 64.4} | 581.99 | 678.50 | 1.17 | 11/5/06 | 11/11/06 |
+ | 72 {L 1 + 42.4} | | | | | |
+ | {L 1 + 19.6} | 619.98 | 719.50 | 1.16 | 4/25/07 | 4/30/07 |
+ | 73 {L 1 + 19.6} | | | | | |
+ | {L 0 + 97.0} | 562.18 | 685.75 | 1.22 | 5/13/07 | 5/18/07 |
+ |_________________|________|________|______|__________|__________|
+
+NOTE.--The number of cubic yards of crushed stone used in any section
+can be found by multiplying the figure for that section in Column 10 by
+0.7778. The number of cubic yards of sand used in any section can be
+found by multiplying the sum of the figures for that section in Columns
+4, 6, and 10 by 0.3889.
+
+Channeling with a 10-ft quarry bar, carrying a No. 4 Ingersoll-Rand
+drill with Z-bits, was attempted in place of the close drilling below
+the walls, but, as the rock stood so nearly vertical and was full of
+soft seams, very little could be accomplished, the average cut per day
+of 10 hours, counting the time of moving and setting up, was only 4 sq.
+ft., and, after a thorough trial, the bars were abandoned.
+
+_Disposal._--The excavated material was hauled from the shovels to the
+pier in 10-car trains. The cars were of three classes: 4-yd. Western
+dump-cars, flat cars without skips, and flats carrying specially
+designed steel skips having a capacity of 4 cu. yd. each. As far as
+practicable, earth, and rock containing 1 cu. yd. or less, was loaded
+on dumpers, medium-sized rock on the skips, and large rock on the bare
+flats. As a steam shovel must pick up what is nearest to it first,
+however, this classification could not always be adhered to, and many
+large rocks were loaded into dumpers. Cars of this class which contained
+no material too large to dump were run at once to the hoppers, and were
+dumped and returned to the pit; others, together with the flat and skip
+cars, were run down the incline to the derricks and telphers, where the
+flats and skips were entirely unloaded, and the large rocks ware removed
+from the dumpers, after which they were run to the hoppers and emptied.
+
+The total quantity of excavated material handled at this pier from May
+22d, 1905, to December 31st, 1908, amounted to 673,800 cu. yd. of earth
+and 1,488,000 cu. yd. of rock, place measurement, equal to 3,203,400 cu.
+yd., scow measurement; in addition to which 175,000 cu. yd. of crushed
+stone and sand and 6,000 car loads of miscellaneous building material
+were transferred from scows and lighters to small cars for delivery to
+the Terminal work.
+
+All the earth and 570,000 cu. yd. of the rock, place measurement, were
+handled through the chutes, and the remainder of the rock, 918,000 cu.
+yd., and all the incoming material by the derricks and telphers. In
+capacity to handle material, one telpher was about equal to one derrick.
+A train, therefore, could be emptied or a boat loaded under the bank of
+eight telphers in one-fourth the time required by the derricks, of which
+only two could work on one boat. The telphers, therefore, were of great
+advantage where track room and scow berths were limited.
+
+As noted in the list of contracts under which the work was executed,
+the scows at both the 35th Street dumping board and Pier No. 72 were
+furnished, towed, and the material finally disposed of, by Henry Steers,
+Incorporated. During the same period, this contractor disposed of the
+material excavated from both the Cross-town Tunnels, constructed by the
+United Engineering and Contracting Company, and the tunnels under the
+East River, constructed by S. Pearson and Son, Incorporated. As stated
+in other papers of this series relating to the construction of those
+tunnels, the material excavated by the United Engineering and
+Contracting Company was delivered to barges at 35th Street and East
+River and that by S. Pearson and Son, Incorporated, at two points, one
+in Long Island City and the other at 33d Street and East River,
+Manhattan.
+
+The total number of cubic yards of material disposed of amounted to:
+
+ Place measurement. Total barge
+ Earth. Rock. measurement.
+
+ 35th Street and North River 242,800 22,800 281,500
+ Pier No. 72, North River 673,800 1,488,000 3,203,400
+ From Cross-town Tunnels 570,400
+ From Under-river Tunnels 402,500
+ -----------
+ Total 4,457,800
+ ===========
+
+The material was delivered as follows:
+
+ To the freight terminal of the Pennsylvania Railroad
+ Company at Greenville, N.J. 3,454,800
+ To the Meadows Division of the Tunnel Line between
+ Harrison, N.J., and the North River Portals 711,900
+ To other points selected by the contractors 291,100
+ ---------
+ Total 4,457,800
+ =========
+
+The handling of this large quantity of material required the loading of
+from 10 to 20 scows per day (and for more than two years the average was
+14), and, as the average time spent in one round trip was 3 1/3 days, a
+fleet of more than 50 scows was required to keep all points supplied and
+allow for a few to be out of service undergoing repairs.
+
+All loaded scows were towed from the docks, with the ebb tide, to a
+stake boat anchored in the bay about one mile off shore at Greenville;
+and were taken from there to the different unloading points, as
+required, by smaller tugs which also returned the empty scows to the
+stake.
+
+The unloading plants were similar at the different points, although that
+at Greenville was much larger than the others. It included five land
+dredges and eight traveling derricks of two types, one floating and the
+other mounted on wheels and traveling on a track of 16-ft. gauge. The
+derricks handled the large rock, which was loaded at Pier No. 72 by
+derricks and telphers. They were of the ordinary A-frame type, and were
+designed to handle 20 tons. They were operated by 9 by 10-in. Lidgerwood
+double-drum and swinging-gear engines. The large rock was deposited by
+the derricks either in the channels along which they worked or in the
+fill along shore, without the use of cars. The land dredges were
+equipped with a 60-ft. boom and a 2½-yd. Hayward bucket operated by a
+14 by 18-in. double-drum Lidgerwood dredging engine. They loaded into
+9-yd., standard-gauge, side-dump cars, built by the contractor, and
+unloaded the scows to within about 1 ft. of the deck, a Hayward bucket
+being unsuitable for closer work without greatly damaging the scows.
+The material remaining was loaded by hand into skips which were handled
+to the cars by small derricks, one of which was located at the rear of
+each dredge. The cars were taken to the dump and returned by 25-ton,
+standard-gauge, engines which had previously done service on the
+Manhattan Elevated Railroad, but were spotted for loading by the engine
+on the dredge.
+
+In order to keep a record of the fleet of scows, which would show the
+available supply at a glance, a board, 10 by 15 in., and covered with a
+heavy sheet of ruled paper, was arranged as shown by Fig. 10. It was
+divided into 12 vertical columns, the first of which was headed "Scows,"
+and contained the name or number of each scow in service. The next four
+columns denoted loading points, and were headed "Pier No. 72,"
+"Thirty-third Street, East River," "Thirty-fifth Street, East River,"
+and "Long Island City," respectively; the sixth column was headed
+"Greenville," the seventh "Hackensack," the eighth "Passaic," and the
+ninth "Governors Island," being unloading points, the tenth and
+eleventh, "Stake Boat" and "Dry Dock," respectively, while the twelfth
+was for "Extra pins," not in use. To indicate the condition of the
+scows, small pins with colored heads were used; white indicated empty;
+blue, working; black, loaded; red, being repaired; and a pearl-colored
+pin, missing. Thus a white-headed pin opposite the number 6 in the
+column headed Pier No. 72 indicated that scow No. 6 was lying at that
+pier waiting to be placed in position for loading, whereas a
+black-headed pin at the same point meant that the scow had received
+its load and was ready to be towed.
+
+BOARD RECORDING LOCATION AND CONDITION OF SCOWS
+
+ [Transcriber's Note:
+ This chart was originally presented as an illustration, Figure 10.
+ It is shown here rotated from horizontal to vertical for readability.
+ As in the original, only a partial board is shown; the number of Scows
+ was at least 8.]
+
+ +---------------------+-------+-------+-------+-------+-------+-------/
+ | Scows. | H.S. | H.S. | H.S. | H.S. | H.S. | H.S. /
+ | | No. 1 | No. 2 | No. 3 | No. 4 | No. 5 | No. 6 /
+ +---------------------+-------+-------+-------+-------+-------+-------/
+ | Loading Points | | | | | | /
+ +--+------------------+-------+-------+-------+-------+-------+-------/
+ | | Pier No. 72 | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Thirty-third | | | | | | /
+ | | Street East R. | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Thirty-fifth | | | | | | /
+ | | Street East R. | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Long Island City | | | | | | /
+ +--+------------------+-------+-------+-------+-------+-------+-------/
+ | Unloading Points | | | | | | /
+ +--+------------------+-------+-------+-------+-------+-------+-------/
+ | | Greenville. | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Hackensack. | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Passaic. | | | | | | /
+ | +------------------+-------+-------+-------+-------+-------+-------/
+ | | Governors Island.| | | | | | /
+ +--+------------------+-------+-------+-------+-------+-------+-------/
+ | Stake Boat. | | | | | | /
+ +---------------------+-------+-------+-------+-------+-------+-------/
+ | Dry Dock. | | | | | | /
+ +---------------------+-------+-------+-------+-------+-------+-------/
+ | | /
+ | Extra Pins. | Empty. White Pins not in use placed here. /
+ | | /
+ +---------------------+-----------------------------------------------/
+
+The scows were all taken from the general service about the harbor; some
+of them were practically new, while others had seen much service. They
+were of two general types, truss-framed or bulkhead-framed; all were
+flat-bottomed, with a rake of about 45° at bow and stern. The
+truss-framed scows were built with a cross-truss every 10 to 15 ft., on
+which rested, fore and aft, two classes of beams, main and intermediate.
+The main beams were built of timbers ranging from 10 by 10 in. to 14 by
+14 in., were scarfed at the joints, and trussed with the bottom logs.
+The intermediate beams were of timbers varying from 6 by 6 in. to 10 by
+12 in., had butt joints, and were dapped at the cross-trusses to give a
+convex surface to the deck, which was built of 3-in. and 4-in. plank,
+from 8 to 12 in. in width, running athwartship. The sides of the scows
+of this class were spiked and bolted to trusses similar to those running
+under the main beams. The bulkheaded boats had both sides and two
+longitudinal bulkheads placed so as to divide the scow into three
+sections of equal width, built of 8 by 8-in. or 10 by 10-in. timbers,
+laid one upon the other, and bolted through from top to bottom. The
+beams on these boats ran athwartship, rested on sides and bulkheads, and
+ranged from 6 by 10-in. to 10 by 12-in., spaced 2 ft. apart, and dressed
+to give a convex surface to the deck, which was usually 3 in., in some
+cases 4 in., in thickness, and made up of narrow plank from 4 to 6 in.
+in width.
+
+ [Illustration:
+ Fig. 11.
+ DIAGRAM OF DECK SHOWING BAYS]
+
+These boats had all been designed for lighter work than they were here
+required to perform, and a large amount of breakage occurred from the
+start. In order that the contractors for the excavation should be
+unhampered as to method of loading, the contracts provided that they
+should pay for all damage done to the scows in loading, other than
+ordinary and usual wear and tear, all other damage being at the expense
+of the contractor for the disposal. A rigid system of inspection was
+necessary to determine and record properly the damage for which each
+contractor was responsible; and, as much of the breakage could not be
+noticed from the exterior, a thorough examination of the interior of
+each scow was made before and after every loading. In order to keep
+proper records, the bays of each scow, formed by the cross-trusses, were
+numbered, beginning aft with number 1 and going forward to the bow, and
+the longitudinal bays formed by the main beams were lettered, beginning
+with "_A_" on the port side. A beam broken in "1-_A_," therefore, would
+be an intermediate beam in the stern port corner bay, and a beam broken
+in "10-_A-B_" would be a main beam at the bow end on the port side. The
+underside of each plank was marked with a number beginning with 1 at the
+stern and increasing by unity to the bow. Fig. 11 is a diagram of a scow
+in accordance with this system. In addition to recording the date,
+location, extent, and party responsible for each damage, in a book kept
+for that purpose, the injured member was marked with paint, the color of
+which indicated the party responsible. The repairs were made by the
+contractor for the disposal of material, and the cost was assessed
+according to the marking in the boat.
+
+The careful inspection of the damage done to scows and the cost of their
+repairs enables a fairly accurate statement to be made of the amount at
+different points, and it is here given on the basis of cost of repairs
+per cubic yard, barge measurement, of material handled.
+
+ Cost, in cents
+ per cubic yard.
+
+ Repairs of damage done in loading material
+ from the terminal site 2.00
+ Repairs of damage done in loading material
+ from cross-town tunnels 1.32
+ Repairs of damage done in loading material
+ from under-river tunnels 1.77
+ Repairs of damage done in transporting and
+ unloading material from all points 1.81
+
+The above figures do not include the expense due to scows which were
+overturned or sunk while in the service, which amounted to 0.4 cent per
+cubic yard, additional.
+
+_Ninth Avenue Tunnels._--The two double-track tunnels under Ninth
+Avenue, constructed to obtain 100 ft. of additional tail room on each
+of four tracks, required an excavation 76 ft. wide, Fig. 12. The rock,
+although fair, was not firm enough for so great a span, and, to obviate
+the necessity of timbering, the center wall was built before excavating
+for the full width. The dip of the rock at this point is almost 90°, and
+to prevent blowing away the entire face in excavating for the tunnel,
+the pit excavation was not carried west to the final face below the
+springing line, a 10-ft. bench being left at that elevation. A top
+heading 9 ft. high and 10 ft. wide was started above that bench and,
+after penetrating about 10 ft., was widened to 20 ft. A cross-heading
+was driven in each direction at the west end of the first heading; the
+bench was then shot down, and the first 10 ft. of the longitudinal
+heading was widened sufficiently to receive the center wall, Fig. 12.
+After the middle wall had been concreted, any voids between its top
+and the rock were grouted through pipes left for that purpose; the wall
+was then protected by curtains of heavy round timber securely wired
+together, and the remainder of the excavation was made by widening
+the cross-headings toward the face. The muck was carried out by two
+cableways, one on each side of the completed middle wall, each of which
+was supported by a tower outside of the tunnel and a large hook-bolt
+grouted into the rock at the inner end of the tunnel. Forms were built
+for each tunnel complete, and the concrete was delivered by a belt
+conveyor, running over the top of the lagging, and moved out as the
+tunnel was keyed.
+
+ [Illustration:
+ Fig. 12.
+ TERMINAL STATION SKETCH SHOWING TWO TRACK TUNNELS
+ AT NINTH AVENUE AND THIRTY-THIRD STREET]
+
+
+FOOTNOTES
+
+ [1: Presented at the meeting of May 4th, 1910.]
+
+ [2: Reproduced as Plate IX in the paper by Mr. Noble.]
+
+ [Text reference for footnote 2:
+ "one arm of the creek shown on General Viele's map of 1865"
+ The article is ASCE 1152, The East River Division, available from
+ Project Gutenberg as e-text 18065]
+
+ * * * * *
+ * * * *
+ * * * * *
+
+[Errata:
+
+Table 2a
+ | 87 {166 + 64.6} | | | | | | |
+ | {166 + 75.6} | 23.44 | 1.00 | 0.34 | 2.25 | 0.42 | ... |
+ _"2.25" is unclear; only ".25" is fully legible_]
+
+
+
+
+
+End of the Project Gutenberg EBook of Transactions of the American Society
+of Civil Engineers, vol. LXVIII, Sept. 1910, by George C. Clarke
+
+*** END OF THIS PROJECT GUTENBERG EBOOK SOCIETY OF CIVIL ENGINEERS ***
+
+***** This file should be named 18408-8.txt or 18408-8.zip *****
+This and all associated files of various formats will be found in:
+ http://www.gutenberg.org/1/8/4/0/18408/
+
+Produced by Louise Hope, Juliet Sutherland and the Online
+Distributed Proofreading Team at http://www.pgdp.net
+
+
+Updated editions will replace the previous one--the old editions
+will be renamed.
+
+Creating the works from public domain print editions means that no
+one owns a United States copyright in these works, so the Foundation
+(and you!) can copy and distribute it in the United States without
+permission and without paying copyright royalties. Special rules,
+set forth in the General Terms of Use part of this license, apply to
+copying and distributing Project Gutenberg-tm electronic works to
+protect the PROJECT GUTENBERG-tm concept and trademark. Project
+Gutenberg is a registered trademark, and may not be used if you
+charge for the eBooks, unless you receive specific permission. If you
+do not charge anything for copies of this eBook, complying with the
+rules is very easy. You may use this eBook for nearly any purpose
+such as creation of derivative works, reports, performances and
+research. They may be modified and printed and given away--you may do
+practically ANYTHING with public domain eBooks. Redistribution is
+subject to the trademark license, especially commercial
+redistribution.
+
+
+
+*** START: FULL LICENSE ***
+
+THE FULL PROJECT GUTENBERG LICENSE
+PLEASE READ THIS BEFORE YOU DISTRIBUTE OR USE THIS WORK
+
+To protect the Project Gutenberg-tm mission of promoting the free
+distribution of electronic works, by using or distributing this work
+(or any other work associated in any way with the phrase "Project
+Gutenberg"), you agree to comply with all the terms of the Full Project
+Gutenberg-tm License (available with this file or online at
+http://gutenberg.org/license).
+
+
+Section 1. General Terms of Use and Redistributing Project Gutenberg-tm
+electronic works
+
+1.A. By reading or using any part of this Project Gutenberg-tm
+electronic work, you indicate that you have read, understand, agree to
+and accept all the terms of this license and intellectual property
+(trademark/copyright) agreement. If you do not agree to abide by all
+the terms of this agreement, you must cease using and return or destroy
+all copies of Project Gutenberg-tm electronic works in your possession.
+If you paid a fee for obtaining a copy of or access to a Project
+Gutenberg-tm electronic work and you do not agree to be bound by the
+terms of this agreement, you may obtain a refund from the person or
+entity to whom you paid the fee as set forth in paragraph 1.E.8.
+
+1.B. "Project Gutenberg" is a registered trademark. It may only be
+used on or associated in any way with an electronic work by people who
+agree to be bound by the terms of this agreement. There are a few
+things that you can do with most Project Gutenberg-tm electronic works
+even without complying with the full terms of this agreement. See
+paragraph 1.C below. There are a lot of things you can do with Project
+Gutenberg-tm electronic works if you follow the terms of this agreement
+and help preserve free future access to Project Gutenberg-tm electronic
+works. See paragraph 1.E below.
+
+1.C. The Project Gutenberg Literary Archive Foundation ("the Foundation"
+or PGLAF), owns a compilation copyright in the collection of Project
+Gutenberg-tm electronic works. Nearly all the individual works in the
+collection are in the public domain in the United States. If an
+individual work is in the public domain in the United States and you are
+located in the United States, we do not claim a right to prevent you from
+copying, distributing, performing, displaying or creating derivative
+works based on the work as long as all references to Project Gutenberg
+are removed. Of course, we hope that you will support the Project
+Gutenberg-tm mission of promoting free access to electronic works by
+freely sharing Project Gutenberg-tm works in compliance with the terms of
+this agreement for keeping the Project Gutenberg-tm name associated with
+the work. You can easily comply with the terms of this agreement by
+keeping this work in the same format with its attached full Project
+Gutenberg-tm License when you share it without charge with others.
+
+1.D. The copyright laws of the place where you are located also govern
+what you can do with this work. Copyright laws in most countries are in
+a constant state of change. If you are outside the United States, check
+the laws of your country in addition to the terms of this agreement
+before downloading, copying, displaying, performing, distributing or
+creating derivative works based on this work or any other Project
+Gutenberg-tm work. The Foundation makes no representations concerning
+the copyright status of any work in any country outside the United
+States.
+
+1.E. Unless you have removed all references to Project Gutenberg:
+
+1.E.1. The following sentence, with active links to, or other immediate
+access to, the full Project Gutenberg-tm License must appear prominently
+whenever any copy of a Project Gutenberg-tm work (any work on which the
+phrase "Project Gutenberg" appears, or with which the phrase "Project
+Gutenberg" is associated) is accessed, displayed, performed, viewed,
+copied or distributed:
+
+This eBook is for the use of anyone anywhere at no cost and with
+almost no restrictions whatsoever. You may copy it, give it away or
+re-use it under the terms of the Project Gutenberg License included
+with this eBook or online at www.gutenberg.org
+
+1.E.2. If an individual Project Gutenberg-tm electronic work is derived
+from the public domain (does not contain a notice indicating that it is
+posted with permission of the copyright holder), the work can be copied
+and distributed to anyone in the United States without paying any fees
+or charges. If you are redistributing or providing access to a work
+with the phrase "Project Gutenberg" associated with or appearing on the
+work, you must comply either with the requirements of paragraphs 1.E.1
+through 1.E.7 or obtain permission for the use of the work and the
+Project Gutenberg-tm trademark as set forth in paragraphs 1.E.8 or
+1.E.9.
+
+1.E.3. If an individual Project Gutenberg-tm electronic work is posted
+with the permission of the copyright holder, your use and distribution
+must comply with both paragraphs 1.E.1 through 1.E.7 and any additional
+terms imposed by the copyright holder. Additional terms will be linked
+to the Project Gutenberg-tm License for all works posted with the
+permission of the copyright holder found at the beginning of this work.
+
+1.E.4. Do not unlink or detach or remove the full Project Gutenberg-tm
+License terms from this work, or any files containing a part of this
+work or any other work associated with Project Gutenberg-tm.
+
+1.E.5. Do not copy, display, perform, distribute or redistribute this
+electronic work, or any part of this electronic work, without
+prominently displaying the sentence set forth in paragraph 1.E.1 with
+active links or immediate access to the full terms of the Project
+Gutenberg-tm License.
+
+1.E.6. You may convert to and distribute this work in any binary,
+compressed, marked up, nonproprietary or proprietary form, including any
+word processing or hypertext form. However, if you provide access to or
+distribute copies of a Project Gutenberg-tm work in a format other than
+"Plain Vanilla ASCII" or other format used in the official version
+posted on the official Project Gutenberg-tm web site (www.gutenberg.org),
+you must, at no additional cost, fee or expense to the user, provide a
+copy, a means of exporting a copy, or a means of obtaining a copy upon
+request, of the work in its original "Plain Vanilla ASCII" or other
+form. Any alternate format must include the full Project Gutenberg-tm
+License as specified in paragraph 1.E.1.
+
+1.E.7. Do not charge a fee for access to, viewing, displaying,
+performing, copying or distributing any Project Gutenberg-tm works
+unless you comply with paragraph 1.E.8 or 1.E.9.
+
+1.E.8. You may charge a reasonable fee for copies of or providing
+access to or distributing Project Gutenberg-tm electronic works provided
+that
+
+- You pay a royalty fee of 20% of the gross profits you derive from
+ the use of Project Gutenberg-tm works calculated using the method
+ you already use to calculate your applicable taxes. The fee is
+ owed to the owner of the Project Gutenberg-tm trademark, but he
+ has agreed to donate royalties under this paragraph to the
+ Project Gutenberg Literary Archive Foundation. Royalty payments
+ must be paid within 60 days following each date on which you
+ prepare (or are legally required to prepare) your periodic tax
+ returns. Royalty payments should be clearly marked as such and
+ sent to the Project Gutenberg Literary Archive Foundation at the
+ address specified in Section 4, "Information about donations to
+ the Project Gutenberg Literary Archive Foundation."
+
+- You provide a full refund of any money paid by a user who notifies
+ you in writing (or by e-mail) within 30 days of receipt that s/he
+ does not agree to the terms of the full Project Gutenberg-tm
+ License. You must require such a user to return or
+ destroy all copies of the works possessed in a physical medium
+ and discontinue all use of and all access to other copies of
+ Project Gutenberg-tm works.
+
+- You provide, in accordance with paragraph 1.F.3, a full refund of any
+ money paid for a work or a replacement copy, if a defect in the
+ electronic work is discovered and reported to you within 90 days
+ of receipt of the work.
+
+- You comply with all other terms of this agreement for free
+ distribution of Project Gutenberg-tm works.
+
+1.E.9. If you wish to charge a fee or distribute a Project Gutenberg-tm
+electronic work or group of works on different terms than are set
+forth in this agreement, you must obtain permission in writing from
+both the Project Gutenberg Literary Archive Foundation and Michael
+Hart, the owner of the Project Gutenberg-tm trademark. Contact the
+Foundation as set forth in Section 3 below.
+
+1.F.
+
+1.F.1. Project Gutenberg volunteers and employees expend considerable
+effort to identify, do copyright research on, transcribe and proofread
+public domain works in creating the Project Gutenberg-tm
+collection. Despite these efforts, Project Gutenberg-tm electronic
+works, and the medium on which they may be stored, may contain
+"Defects," such as, but not limited to, incomplete, inaccurate or
+corrupt data, transcription errors, a copyright or other intellectual
+property infringement, a defective or damaged disk or other medium, a
+computer virus, or computer codes that damage or cannot be read by
+your equipment.
+
+1.F.2. LIMITED WARRANTY, DISCLAIMER OF DAMAGES - Except for the "Right
+of Replacement or Refund" described in paragraph 1.F.3, the Project
+Gutenberg Literary Archive Foundation, the owner of the Project
+Gutenberg-tm trademark, and any other party distributing a Project
+Gutenberg-tm electronic work under this agreement, disclaim all
+liability to you for damages, costs and expenses, including legal
+fees. YOU AGREE THAT YOU HAVE NO REMEDIES FOR NEGLIGENCE, STRICT
+LIABILITY, BREACH OF WARRANTY OR BREACH OF CONTRACT EXCEPT THOSE
+PROVIDED IN PARAGRAPH F3. YOU AGREE THAT THE FOUNDATION, THE
+TRADEMARK OWNER, AND ANY DISTRIBUTOR UNDER THIS AGREEMENT WILL NOT BE
+LIABLE TO YOU FOR ACTUAL, DIRECT, INDIRECT, CONSEQUENTIAL, PUNITIVE OR
+INCIDENTAL DAMAGES EVEN IF YOU GIVE NOTICE OF THE POSSIBILITY OF SUCH
+DAMAGE.
+
+1.F.3. LIMITED RIGHT OF REPLACEMENT OR REFUND - If you discover a
+defect in this electronic work within 90 days of receiving it, you can
+receive a refund of the money (if any) you paid for it by sending a
+written explanation to the person you received the work from. If you
+received the work on a physical medium, you must return the medium with
+your written explanation. The person or entity that provided you with
+the defective work may elect to provide a replacement copy in lieu of a
+refund. If you received the work electronically, the person or entity
+providing it to you may choose to give you a second opportunity to
+receive the work electronically in lieu of a refund. If the second copy
+is also defective, you may demand a refund in writing without further
+opportunities to fix the problem.
+
+1.F.4. Except for the limited right of replacement or refund set forth
+in paragraph 1.F.3, this work is provided to you 'AS-IS' WITH NO OTHER
+WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED, INCLUDING BUT NOT LIMITED TO
+WARRANTIES OF MERCHANTIBILITY OR FITNESS FOR ANY PURPOSE.
+
+1.F.5. Some states do not allow disclaimers of certain implied
+warranties or the exclusion or limitation of certain types of damages.
+If any disclaimer or limitation set forth in this agreement violates the
+law of the state applicable to this agreement, the agreement shall be
+interpreted to make the maximum disclaimer or limitation permitted by
+the applicable state law. The invalidity or unenforceability of any
+provision of this agreement shall not void the remaining provisions.
+
+1.F.6. INDEMNITY - You agree to indemnify and hold the Foundation, the
+trademark owner, any agent or employee of the Foundation, anyone
+providing copies of Project Gutenberg-tm electronic works in accordance
+with this agreement, and any volunteers associated with the production,
+promotion and distribution of Project Gutenberg-tm electronic works,
+harmless from all liability, costs and expenses, including legal fees,
+that arise directly or indirectly from any of the following which you do
+or cause to occur: (a) distribution of this or any Project Gutenberg-tm
+work, (b) alteration, modification, or additions or deletions to any
+Project Gutenberg-tm work, and (c) any Defect you cause.
+
+
+Section 2. Information about the Mission of Project Gutenberg-tm
+
+Project Gutenberg-tm is synonymous with the free distribution of
+electronic works in formats readable by the widest variety of computers
+including obsolete, old, middle-aged and new computers. It exists
+because of the efforts of hundreds of volunteers and donations from
+people in all walks of life.
+
+Volunteers and financial support to provide volunteers with the
+assistance they need, is critical to reaching Project Gutenberg-tm's
+goals and ensuring that the Project Gutenberg-tm collection will
+remain freely available for generations to come. In 2001, the Project
+Gutenberg Literary Archive Foundation was created to provide a secure
+and permanent future for Project Gutenberg-tm and future generations.
+To learn more about the Project Gutenberg Literary Archive Foundation
+and how your efforts and donations can help, see Sections 3 and 4
+and the Foundation web page at http://www.pglaf.org.
+
+
+Section 3. Information about the Project Gutenberg Literary Archive
+Foundation
+
+The Project Gutenberg Literary Archive Foundation is a non profit
+501(c)(3) educational corporation organized under the laws of the
+state of Mississippi and granted tax exempt status by the Internal
+Revenue Service. The Foundation's EIN or federal tax identification
+number is 64-6221541. Its 501(c)(3) letter is posted at
+http://pglaf.org/fundraising. Contributions to the Project Gutenberg
+Literary Archive Foundation are tax deductible to the full extent
+permitted by U.S. federal laws and your state's laws.
+
+The Foundation's principal office is located at 4557 Melan Dr. S.
+Fairbanks, AK, 99712., but its volunteers and employees are scattered
+throughout numerous locations. Its business office is located at
+809 North 1500 West, Salt Lake City, UT 84116, (801) 596-1887, email
+business@pglaf.org. Email contact links and up to date contact
+information can be found at the Foundation's web site and official
+page at http://pglaf.org
+
+For additional contact information:
+ Dr. Gregory B. Newby
+ Chief Executive and Director
+ gbnewby@pglaf.org
+
+
+Section 4. Information about Donations to the Project Gutenberg
+Literary Archive Foundation
+
+Project Gutenberg-tm depends upon and cannot survive without wide
+spread public support and donations to carry out its mission of
+increasing the number of public domain and licensed works that can be
+freely distributed in machine readable form accessible by the widest
+array of equipment including outdated equipment. Many small donations
+($1 to $5,000) are particularly important to maintaining tax exempt
+status with the IRS.
+
+The Foundation is committed to complying with the laws regulating
+charities and charitable donations in all 50 states of the United
+States. Compliance requirements are not uniform and it takes a
+considerable effort, much paperwork and many fees to meet and keep up
+with these requirements. We do not solicit donations in locations
+where we have not received written confirmation of compliance. To
+SEND DONATIONS or determine the status of compliance for any
+particular state visit http://pglaf.org
+
+While we cannot and do not solicit contributions from states where we
+have not met the solicitation requirements, we know of no prohibition
+against accepting unsolicited donations from donors in such states who
+approach us with offers to donate.
+
+International donations are gratefully accepted, but we cannot make
+any statements concerning tax treatment of donations received from
+outside the United States. U.S. laws alone swamp our small staff.
+
+Please check the Project Gutenberg Web pages for current donation
+methods and addresses. Donations are accepted in a number of other
+ways including checks, online payments and credit card donations.
+To donate, please visit: http://pglaf.org/donate
+
+
+Section 5. General Information About Project Gutenberg-tm electronic
+works.
+
+Professor Michael S. Hart is the originator of the Project Gutenberg-tm
+concept of a library of electronic works that could be freely shared
+with anyone. For thirty years, he produced and distributed Project
+Gutenberg-tm eBooks with only a loose network of volunteer support.
+
+
+Project Gutenberg-tm eBooks are often created from several printed
+editions, all of which are confirmed as Public Domain in the U.S.
+unless a copyright notice is included. Thus, we do not necessarily
+keep eBooks in compliance with any particular paper edition.
+
+
+Most people start at our Web site which has the main PG search facility:
+
+ http://www.gutenberg.org
+
+This Web site includes information about Project Gutenberg-tm,
+including how to make donations to the Project Gutenberg Literary
+Archive Foundation, how to help produce our new eBooks, and how to
+subscribe to our email newsletter to hear about new eBooks.